| MANEUVER UAV | |
|---|---|
| Costs FY95 FY96 FY97 | Maneuver UAV* $26.1M $36.8M $59.2M |
Program Requirements
- Day/night sensor
- Operate from unimproved surface
- Operate at ranges up to 27 nm
- Employ down-sized Hunter ground equipment (Ground Control Station, Ground Data Terminal, and Remote Video Terminal)
- ACTD-like approach
- Contractor integrates air vehicle with GFE (down-sized ground control station, data and video terminals)
- Field first system by FY98
- Nondevelopmental item (NDI) procurement for components with cost as major criterion
Major Accomplishments
- Down-sized ground control station contract awarded to TRW September 1994
- Integrated Product Team (IPT) created June 1995
- Tiger Team developed streamlined acquisition plan, followed by OSD decision to employ ACTD-like approach
![]()
| PIONEER & HUNTER | ||
|---|---|---|
| Costs FY95 FY96 FY97 | Pioneer* $26.1M $36.8M $59.2M | Hunter (w/C&I)* $305.2M $106.5M $226.1M |
Program Requirements
- Operate up to 15,000 ft and at ranges > 100 nm
- Pioneer: Provide interim IMINT for tactical commanders (on land and afloat), pending fielding of Hunter
- Hunter: Provide responsive IMINT to tactical commanders; operate from unimproved runways and from ships
Acquisition Strategy
- Pioneer: NDI acquisition, nine systems
- Hunter: Acquisition Category (ACAT) I program; competitive buy; seven LRIP systems (at not-to-exceed priced option); MS III to determine full production quantity; adopting a robust test-analyze-fix-test approach
Major Accomplishments
- Pioneer: Haiti, Balkan ops in September 1994. Now on two Navy LPD class ships (two more funded). Pioneer Readiness Improvement Program initiated to keep readiness above 85% (mid-FY96 on)
- Hunter: Independent Assessment of Joint Tactical Hunter UAV Program (March 1995). System #5 was accepted August 1995; expect all seven LRIP systems during FY96
| MAE UAV | |
|---|---|
| Costs FY95 FY96 FY97 | MAE Predator* $61.4M $20.0M $18.0M |
Program Requirements
Acquisition Strategy
| HAE UAVs | ||
|---|---|---|
| Costs FY95 FY96 FY97 | CONV HAE#* $74.1M $117.0M $112.5M | LO HAE* $61.2M $48.0M $41.0M |
Program Requirements