LIST OF FIGURES
Figure
1 McKenna Site and Surrounding Study Area (Ft Benning, GA)
Figure 2 McKenna MOUT Site (From DMA Geodetic
Survey, May 1996)
Figure 3 Aerial View of McKennat MOUT Site
from Northwest
Figure 4 Virtual View of McKenna MOUT Site
from Northwest
Figure 5 Generic M&S Database Construction
Figure 6 Comparison Between The Four Data Generation
Cases
Figure 7 Relative Positions of Control
LIST OF TABLES
Table 1 Differences Between DMA Coordinates
and Measurements on the Coordinate Display Form
Table 2 Differences Between Checkpoints Used
for Control Between the PSI and DMA Coordinates
Table 3 Variation Between PSI and DMA Coordinates
Table 4 Comparison Between PSI and TEC Coordinates
Table 5 Azimuth Angle Differences
FINAL REPORT OF THE MILITARY OPERATIONS IN BUILT-UP AREAS (MOBA)
- TERRAIN DATABASE (TDB) PROJECT
EXECUTIVE SUMMARY
1. Introduction
The
1994 Defense Science Board Study on Military Operations in Built-up Areas
(MOBA) recommended to the Secretary of Defense that initiatives be undertaken
to improve the ability of US forces to operate in urban areas and to perform
dismounted combat, peacekeeping, and other activities associated with operations
other than war. A priority initiative included the development of urban
databases and simulations to assist the analysis of operational needs,
and to provide urban training, crisis management, mission planning, rehearsal,
intelligence, and command and control capabilities. A future goal is the
production of information systems to improve situational awareness during
actual urban operations. Improved awareness requires that real-time digital
information regarding the dispositions and actions of forces be displayed
within a geographic context that permits commanders and subordinate units
to understand the environment, perform command and control, and conduct
successful operations.
As a step toward this goal, the Defense Modeling
and Simulation Office (DMSO) and the Defense Mapping Agency (DMA) - now
part of the National Imagery and Mapping Agency
(NIMA) - sponsored a project to produce and evaluate digital terrain data
for the McKenna MOUT (military operations in urban terrain) training site at
Fort Benning, Georgia. NIMA's Terrain Modeling
Project Office (TMPO) is the Department of Defense modeling and simulation
executive agent for the authoritative representation of terrain. During May
1995 through August 1996, TMPO, the DMA St. Louis production facilities, the
Topographic Engineering Center (TEC),
the Institute for Defense Analyses (IDA), TASC,
Inc., GDE, Inc., LNK,
Inc., LADS-Belleview, the TRADOC
Dismounted Battlespace Battle Lab (DBBL), the Marine Corps Modeling and
Simulation Management Office (MCMSMO), and several other organizations planned,
constructed, and evaluated both digital and paper high-resolution terrain products
of the MOUT site. These products included: stereo overhead imagery, detailed
geodetic and Global Positioning System (GPS) site surveys; mapping, charting,
and geodesy (MC&G) elevation and feature files; Geographic Information System
(GIS) databases; micro-terrain profiles; orthophotos with feature overlays;
3-D anaglyphs; maps; radar, video, and other site imagery; 3-D computer-aided
design (CAD) site models of McKenna building exteriors and interiors; texture
libraries; and modeling and simulation (M&S) run-time databases for virtual
reality (VR) simulators. Data were collected for both McKenna and the Griswold
live fire range. High-resolution data were inserted in a larger runtime database
employing USGS elevation data and feature information for a 24 Km x 24 Km region
surrounding Griswold and McKenna sites. The three regions are depicted in Figure
1.
The McKenna training facility was chosen as the focus for this project
due to the strong interest of the Army
Training and Doctrine Command (TRADOC) and the Ft Benning Battle Lab.
McKenna is used for the training of US and allied infantry, marines, and
law enforcement personnel. It consists of a mock European village containing
15 primary buildings, three support buildings, and an underground sewer
system with five manhole cover (MHC) pop-up points. Figure
2 provides the village layout. Letters inside building outlines match
the DBBL reference system (used in evaluation questionnaires), while outside
letters and MHC codes correspond to the DMA site survey codes. The village
is approximately 90 x 150 meters in area, and can be approached through
woods. The terrain immediately surrounding the village is composed of grassy
and brushy open areas, thick forests, swamps, streams, ponds, some sharp
erosional features, and many light/loose surfaced roads and trails. The
5 Km x 5 Km region is approximately 80 percent wooded and exhibits variations
in relief of about 70 meters. It contains a 1,125-meter dirt airstrip capable
of landing C-130 aircraft, and a 300 x 300 meter helipad. Figures
3 and 4 provide live and virtual aerial
comparisons of the village.
Figure 1 McKenna Site and Surrounding Study Area (Ft Benning,
GA)
Figure 2 McKenna MOUT Site (From DMA Geodetic Survey, May 1996)
Figure 3 Aerial View of McKennat MOUT Site from Northwest
Figure 4 Virtual View of McKenna MOUT Site from Northwest
2. Data
Generation
A generic production flow for M&S databases is shown in Figure
5. Four different MC&G databases were created over the McKenna
MOUT Site. The different cases were chosen to provide baseline data on
several possible production and operational scenarios. Each case required
an imagery source and control to perform a triangulation. Every case involved
generation of a digital elevation model (DEM), a feature database, and
3D building models. Some cases used additional imagery sources or other
sources to generate MC&G databases, or generated value-added databases
by combining additional imagery with an MC&G database. In all cases,
a M&S exchange format database was to be compiled from the MC&G
database and value-added data available. Runtime databases for specific
simulators were to be created by transformation from the M&S exchange
format database. Due to resource constraints only the last database was
converted to an M&S database.
Figure 5 Generic M&S Database Construction
Figure 6 Comparison Between The Four Data Generation Cases
3. Product
Descriptions
Digital MC&G products are of two basic types: 1) Digital Elevation
Models (DEM), including a specific DMA standard product termed Digital
Terrain Elevation Data (DTED); and 2) digital feature files known as Interim
Terrain Data (ITD) or enhanced ITD (sometimes termed ITD++). Since several
of the McKenna elevation files are non-standard products, the generic term
"DEM" is used to imply either type of elevation product. Elevation files
provide the x,y reference and z posts used to construct the terrain surface
or skin.
DMA provided the extraction rules used for generating all the high resolution
feature databases. The extraction rules were based on the existing Interim
Terrain Data (ITD) specification, enhanced with features and attributes
agreed between DMA and the DBBL (Annex B). The enhanced ITD added to the
feature description by supplying further information about buildings, point
drains, roads, transportation, soils, lakes, rivers, vegetation, sewers,
linear features, wrinkles, gullies, and obstacles.
Three dimensional models were created to provide the exterior and interior
building details.
These three file types (DEM, ITD, and 3D Models), when combined, form
the complete McKenna MOBA terrain database (MOBA TDB). One method to combine
them is in the S1000 format database. This provided the user with the tools
to manipulate and use the MOBA TDB.
4. MC&G
Data Base Generation
This section covers the generation of the four different cases. The original
production plan is defined, and any deviations form the plan, as well as
the reasons for the deviation are recorded. In addition, resources that
were expended to complete each case study are enumerated. Finally, each
case description concludes with an assessment of the production process.
This includes an evaluation of difficulties encountered, both expected
and unanticipated, any unusual or exceptional situations encountered, and
a review of any lessons learned.
4.1 Case
Study I
The first case (Data Generation by Commercial Processes) was the generation
of a high resolution TDB produced from high resolution conventional photography
supported by a ground survey. Data generation of the elevation, features,
and exterior building geometry were done by a DoD contractor, using a Digital
Stereo Photogrammetric Workstation (DSPW). Elevation data consisted of
a DEM with a resolution of 1 meter in a 1 Km x 2 Km patch covering the
McKenna MOUT facility, and the airfield. Feature data was extracted to
the MOBA feature specification. TEC was to compile the DEM, feature data,
and three dimensional (3D) building models into an S1000 format database.
This case was to demonstrate the ability of high resolution conventional
photography to support the detailed feature and attribute requirements
of a MOBA TDB. It is understood that this imagery may not be available
for all operational areas.
4.1.1 Source
of Data
1:5000 scale frame aerial photography (45 images) were used for this case
study. Camera positions were photogrammetrically adjusted by aerial triangulation
to ground control and in flight GPS collected camera stations.
4.1.2 Resources
Expended
A total of 330 hours of direct man-hour costs were expended. This includes
12 hours for scanning, 24 hours for triangulation, 160 hours for terrain
extraction, 60 hours for feature extraction, and 74 hours for preparation
of the original report. Of the 60 hours used for feature extraction, approximately
12 hrs were used to create the specification used by the DPWS. This time
would be reduced for follow on projects. There was no breakdown of resources
into direct and indirect costs.
4.1.3 Production
Process Assessment
During the scanning procedure, the Orientation/Automatic process was less
accurate than the Semi Automatic process. For triangulation procedure,
not enough ground control was supplied (only six points were supplied),
GPS values for camera position didn't meet accuracy specification, and
the dense tree cover caused problems measuring tie points. (APM measured
57%). Also, blunder detect needs to be more robust to handle user or terrain
induced anomalies. In the terrain extraction procedure: the tool to eliminate
trees and building areas from the DEM was not very effective. Also, the
terrain extraction process would greatly benefit from a TIN capability
4.1.4 Lessons
Learned
The DEM Model and Feature Database Generation study for the McKenna MOUT
site provided valuable, real-world insight into the kinds of benefits and
problems experienced with the use of high resolution data. It established
a timeline benchmark for future similar studies. It generated a very large
data set which can be used for developing and testing more productive semi
automatic feature extraction tools. It also demonstrated several deficiencies
in the Feature Extraction process that require improvements to the existing
tool. The attribution process for high resolution databases needs to be
simplified (i.e. fewer attribution parameters in the specification file)
to improve the overall process productivity while still capturing significant
detailed features.
4.2 Case
Study II
The second case (Data Generation by Current Procedures) was the generation
of a high resolution MOBA TDB using current DMA production procedures.
This case was intended to represent existing, widely practiced, procedures
for the construction of M&S TDBs. Data sources that are not likely
to be available over operational areas (large scale conventional photographs,
ground surveys, and engineering drawings of buildings) were not be used.
The source for this process was MC&G imagery. DMA processed MC&G
imagery, using MC&G triangulation procedures without ground control,
and produced two standard products (ITD and DTED II). Then high resolution
MC&G imagery and the DMA products were to be provided to a contractor
to add additional details and features to the DMA standard products. Models
of the exterior geometry of the buildings were to be extracted from high
resolution MC&G imagery. Data sources not likely to be available over
denied areas were not utilized.
4.2.1 Source
of Data
Operational MC&G imagery was used to produce all of the standard feature
and elevation products for Case Study II. The most recent imagery was used
for the ITD data, but due to the presence of clouds over the project area,
imagery from an earlier date was used to produce the DTED Level II data.
4.2.2 Resources
Expended
A total of 466 hours of direct man-hour costs were expended in the production
of Case Study II. This includes 31 man-hours for geopositioning, 35 man-hours
for extraction of the elevation data, 189 hours for the extraction of the
feature data, and 211 man-hours for the preparation of this document. An
estimated total of 88 man-hours of indirect labor costs were incurred.
8 hours were spent by geopositioning, and 40 hours apiece for elevation
and feature data set management.
4.2.3 Production
Process Assessment
The purpose of Case Study II was to document existing and widely practiced
procedures typically used for the construction of M&S terrain databases.
Although the resolution of operational imagery and the data content of
DMA's standard products do not meet the strict requirements of this project,
this data is intended primarily for use as a standard of comparison to
the more robust data sets. Since this case study involves the utilization
of standard procedures and production processes for geopositioning, data
extraction, and quality review, problems were neither expected nor encountered.
The only problems occurred where deviations from standard practices were
required, for example, when the data formats and output tape types and
capacities varied from the norm.
4.2.4 Lessons
Learned
The lessons to be learned from this are twofold: First, there must be a
clear understanding at the outset of a project of all hardware and software
inventories and capabilities for both data generators and users. This can
easily be accomplished by listing all hardware items including their capacities,
and all software items, including the versions used. If the data generators
know which systems are being utilized, they can tailor the output to match.
Secondly, there should be a standardized tape and file naming system. All
output tapes should clearly identify the data producer, the case study
number(s), the data set(s) contained on the tape, all data and file formats,
and a list and short description of the content of all data files. Furthermore
there should be a standardized means of listing and describing all data
files with this information appearing, not only on the exterior label of
the tape, but, internally, in soft copy. With this method, even if the
tape label was lost, not copied, or incorrectly copied, a complete list
of all necessary items could still be obtained by opening and reading the
tape.
4.3 Case
Study III
The third case (Data Generation by M&S Tailored DMA Procedures) was
generation of a MOBA TDB using a DMA production process tailored to meet
the high resolution MOBA M&S requirements. This case study consisted
of the production of enhanced ITD and DTED Level III and IV, using both
operational and high resolution MC&G imagery triangulated without ground
control. Extraction of both ITD and one of the two DTED data sets occurred
only within the 3 Km x 3 Km area inside the 5 Km x 5 Km project area. The
other DTED data set covered the entire 5 Km area.This case was intended
to demonstrate DMA potential data generation capability as opposed to established
DMA production processes. Data sources that are not likely to be available
over operational areas (large scale conventional photographs, ground surveys,
and engineering drawings of buildings) were not used.
4.3.1 Source
of Data
Both operational and high resolution MC&G imagery were used to produce
the feature and elevation products for Case Study III. High resolution
MC&G imagery was used for the extraction of enhanced ITD and DTED Level
IV, while operational MC&G imagery was used for the DTED Level III
data set.
4.3.2 Resources
Expended
A total of 758 hours of direct man-hour costs were expended in the production
of Case Study III. This includes 31 man-hours for geopositioning, 125 man-hours
for the extraction of DTED Level III, 151 hours for DTED Level IV, 240
hours for the extraction of the feature data, and 211 man-hours for the
preparation of this document. An estimated total of 88 man-hours of indirect
labor costs were incurred. 8 hours were spent by geopositioning, and 40
hours apiece for elevation and feature data set management.
4.3.3 Production
Process Assessment
Some concerns developed over imagery issues as well as from extraction
artifacts in the elevation data sets. Operational MC&G imagery is routinely
utilized as a source for the production of DTED Levels I and II. Due to
the wide spacing of grid points on these products the quality, scale and
resolution of this imagery do not present any serious problems. It cannot,
however, support products with 1 or 3 meter grid spacing requirements.
Although it was used to produce DTED Level III, this extended data extraction
beyond the capabilities of the imagery.
The most serious concerns were due to the presence of extraction artifacts
known as cornrows, which are a product of manually produced DTED. Historically,
cornrows have not presented significant data quality problems, since the
elevation post spacing on standard DTED products are quite large. With
close grid spacing, however, cornrows are quite numerous, especially in
heavily forested areas, where the "ground" location is uncertain. Although
the effect of cornrows can be greatly reduced through processing techniques,
there is a concern that such processing may adversely affect data quality.
4.3.4 Lessons
Learned
The results of Case Study III confirm the belief that standard production
processes can be successfully utilized and adapted, where needed, in most
cases, to produce customized digital terrain data sets. The primary problems
associated with this case study, however, had to do with post production
activities, preproduction confusion over project requirements, and image-related
issues.
The lessons to be learned from this are twofold: First, there must be
a clear understanding at the outset of a project of all hardware and software
inventories and capabilities for both data generators and users. Secondly,
there should be a standardized tape and file naming system. Furthermore
there should be a standardized means of listing and describing all data
files with this information appearing, not only on the exterior label of
the tape, but, internally, in soft copy. With this method, even if the
tape label was lost, not copied, or incorrectly copied, a complete list
of all necessary items could still be obtained by opening and reading the
tape.
There were two image-related issues that need adjustment for future
work. Although high resolution MC&G imagery was a requirement for this
project, it took six months to get it. Missions requiring such imagery
must plan sufficient lead time for imagery acquisition or arrange for higher
priority for imagery procurement. The other image-related issue concerns
the season when the imagery was taken. Use of winter imagery would have
resulted in much more accurate elevation data sets.
4.4 Case
Study IV
The final case (Data Generation from Unconstrained DMA Procedures) was
the generation of a high resolution MOBA-TDB using unconstrained resources.
The TDB was generated by DMA from high resolution conventional photographs,
MC&G imagery, high resolution MC&G imagery, a site survey, and
supported by a geodetic survey. It was intended to produce the best possible
database, using any available data and data support sources. It is understood
that this approach may not be possible over operational areas. It was similar
to Case III except that additional data sources (large scale conventional
photographs, ground surveys, and engineer drawings of buildings) were used.
All available sources were used. DMA used conventional photographs, MC&G
and high resolution MC&G imagery but triangulated to ground control
collected by DMA. The triangulated high resolution conventional photographs
were the primary source for elevations and feature locations. The MC&G
and high resolution MC&G imagery were used to assist in identification
of features and collection of feature attributes. The 1 Km x 2 Km patch
of 1 meter resolution DEM, generated for Case I, was also used in this
case. A DEM of 3 meter resolution and high resolution feature data were
collected over the 3 Km x 3 Km area. These data sets were generated directly,
without intermediate production of a medium resolution standard product.
Complete 3D building computer aided design (CAD) models were generated
from engineering drawings. These models include interior and exterior building
geometry. TEC compiled the 3 meter and 1 meter DEMs, feature data, and
3D building models into an S1000 database.
4.4.1 Source
of Data
90 conventional commercially-derived aerial photography at a scale of 1:5,000
and 7 photographs at a scale of 1:20,000 were used.
4.4.2 Resources
Expended
A total of 2,202 hours of direct man-hour costs were expended in the production
of Case Study IV. This includes 449 man-hours for geopositioning, 1083
man-hours for conducting the geodetic survey and follow-up reporting, 250
hours for the extraction of the feature data, and 300 man-hours for the
preparation of this document. An estimated total of 158 man-hours of indirect
labor costs were incurred. 8 hours were spent by geopositioning, and 150
hours for feature data set management.
4.4.3 Production
Process Assessment
While there were no insurmountable problems in Case Study IV, a number
of time consuming inconveniences were encountered in the feature extraction
process. The areas of difficulty were related to the type of imagery used,
and the hardware and software of the system used to exploit the imagery.
Image related difficulties originated from the necessity of creating
small, numerous models. The small size of each aerial photograph, along
with the overlap and sidelap requirements for the stereo use of such imagery
dictated the creation of small stereo models. Since data extraction models
can be no larger than the stereo models in which they are contained, many
small data extraction models were also necessary. Model creation and closing,
as well as the required internal quality assurance checks, are time consuming
processes, and the greater the number of models to process, the greater
the associated processing time. The MC&G imagery (used in Case Studies
II and III) required the construction of only 1 stereo model each, and
from 1 to 10 associated data extraction models (depending on the case study),
while the aerial photography used in this case study required 28 stereo
models and 31 data extraction models.
Time consuming difficulties related to the software had to do with processing
of individual photo strips, conducting a software fix allowing image exploitation,
and time saving automated processes that did not work well. Software restrictions
allowed only one photo strip to be processed at a time. The result was
that the photo analyst could not quickly move from one end of the project
to the other, since it involved the cumbersome and time intensive processes
of activating the proper photo strip, orienting the correct stereo model,
and, finally, opening the appropriate extraction model, each being a 20
to 30 minute process.
The FE/S was designed to exploit hard copy imagery sources. Since DMA
uses hard copy MC&G imagery on the FE/S almost exclusively, the orientation
processes and procedures for conventional photography were not completely
developed, somewhat cumbersome, and more time consuming than the orientation
process for MC&G imagery. Before extraction could take place, Fortran
code had to be written, allowing the ellipsoid heights in the control data
to be converted to MSL values as required by the FE/S.
Several processes and procedures typically used as shortcuts to save
time in the data extraction process (the use of the auto node and auto
tag processes, and the use of maintenance data) could not be utilized
on this project. These processes save much time and effort, since manual
placement of nodes and tags is quite time consuming. On this project, however,
both processes generated numerous errors, requiring much repair time. Use
of auto node and auto tag was discontinued, necessitating the labor and
time intensive manual approach.
There was also a hardware related problem. The FE/S hardware has a built-in
restriction in it's magnification (zoom) capabilities. While this does
not adversely affect extraction from MC&G imagery, it proved to be
very restrictive with conventional aerial photography. The photo analyst
could not "zoom up" to get an overall view of an area, in order to get
a better idea of how features should be split apart or included together.
Instead, mapping had to take place at a high magnification level, which
does not allow the analyst a view of the "big picture", and as a result,
interpretations of feature outlines required much editing.
The combination of small model sizes, restricted "zoom" capability,
lengthy orientation and photo strip processing times, and inability to
utilize such time saving processes as auto node, auto tag, and maintenance
data, made it difficult to map, to get an overall view of the mapping area,
and to easily change previously compiled linework from another photo model.
More processing time directly correlates to less data extraction time,
especially when a limited time frame for project completion is considered.
4.4.4 Lessons
Learned
The results of Case Study IV confirm the belief that standard production
processes can be successfully utilized and adapted to produce customized
digital terrain data sets. The geopositioning activities followed well
established procedures, and did not encounter any significant problems.
There was some room for improvement in a few areas related to the geodetic
survey. In the feature extraction arena, with a number of improvements
in processes and procedures, production times could be shortened, and certain
problems could be avoided.
Geodetic crews should be involved in coordinating the preflight plan
with the aerial photography contractor. This would allow the geodetic team
to locate additional identifiable, suitable GPS control points on the ground.
When the geodetic crews were in the field, the aerial photography, photocopies
of the imagery, charts and point sketches were used as guides to identify
and locate the preselected control points. Since there was only one set
of paper prints of the imagery available for use, individual crew members
had to use photocopies of the exposures to locate the control points. In
most cases, these photocopies did not show enough detail to be of much
use. If duplicate sets of paper prints had been available, multiple field
crews could have accessed the imagery at the same time, thus ensuring confidence
in point site recognition, as well as speeding up the process.
The lessons to be learned from this are twofold: First, there must be
a clear understanding at the outset of a project of all hardware and software
inventories and capabilities for both data generators and users. This can
easily be accomplished by exchanging lists of all hardware items, including
their capacities, and all software items, including the versions used.
Secondly, there should be a standardized tape and file naming system. All
output tapes should clearly identify the data producer, the case study
number(s), the data set(s) contained on the tape, all data and file formats,
and a list and short description of the content of all data files. Furthermore
there should be a standardized means of listing and describing all data
files with this information appearing, both on the exterior label of the
tape and in soft copy. With this method, even if the tape label was lost,
not copied, or incorrectly copied, a complete list of all necessary items
could still be obtained by opening and reading the tape.
There was also an image-related issue concerning the season when the
imagery was taken. Both the MC&G imagery and the conventional aerial
photography were "summer scenes" with full foliage on the deciduous trees.
Imagery taken in the middle of winter, when all of the deciduous trees
have lost their leaves, would have allowed a better view of the ground.
Use of winter imagery would have resulted in much more accurate extraction
over forested areas, and possibly would have made the extraction of an
elevation data set by DMA for this case study feasible .
Finally, the type of imagery used to generate the best data set possible
was originally believed to be the conventional aerial photography. While
image interpretations made in open areas were not a problem, the overall
dark tones and general lack of variability in tonal patterns, made differentiation
of vegetation types in heavily forested areas quite difficult at best,
and impossible at worst. The MC&G imagery was a better image source,
at least in heavily vegetated areas, then the conventional aerial imagery.
5. CAD
Generation
This section documents the generation of Computer Aided Design (CAD) models
of the McKenna MOUT site. The intent was to generate a high resolution
database from both detailed engineering drawings, aerial photographs, and
texture maps extracted from still photographs of the site buildings. These
models, along with the elevation and feature data generated in Case Study
IV, were used in the creation of the S1000 database.
5.1 Source
Data
The generation
of CAD models used drawing package and building details, McKenna MOUT,
Ft. Benning, GA, Drawing No's FE 21725 - FE 21889 (164 Drawings), photographs
of building site 8x10 glossy, 144 photographs, and sewer layout details.
5.2 Resources
Expended
A total of 275 hours were expended in the production of the CAD models.
There was no breakout by direct and indirect costs.
5.3 Production
Process Assessment
In general, textures extracted from still photos of building faces that
are orthogonal produce reasonable alignment for doorways and windows. As
the photograph becomes increasingly oblique, which is especially true of
multi-story buildings taken from ground level, the alignment and mismatch
are more apparent. Some tools can manipulate an image to remove perspectives
introduced by the camera lens. This is not true ortho-rectification of
the image but simply stretching pixels of the digital image and did not
guarantee correct alignment.
Another observation is the shadowing introduced by the photographs.
Since the photos were not taken at the same instant in time, shadowing
on the buildings and ground provide "conflicting" information that the
observers' brain will try to differentiate.
Still photos of building faces were shot in black and white. Texture
map file format (RGB, JPEG, TIFF) can handle color. We were able to "synthetically"
introduce color into the MOUT by assigning color attributes to the buildings,
walls, and ground.
The process of digitization of the drawing coordinates is highly labor
intensive and requires high productivity tools. Mixing detailed engineering
drawings with photographs of the actual buildings was hampered by problems
of misalignment due to both camera positional distortions and builder modifications
not captured by the original drawings.
5.4 Lessons
Learned
One unexpected observation made during production was that the builders
often deviated from the original design drawings with respect to window
and door size, and placement. The precision of the drawing was held fixed
and an attempt was made to fit the textures to the wire frame CAD model.
If the texture map images were produced under more controlled conditions,
with respect to scale and obliquity, it would have been better to adjust
the face polygons to fit the "real-world" rather than vice versa.
6. M&S
Data Base Generation
The MOBA-TDB project represents a significant milestone in M&S terrain
database production. Every effort was made to create a terrain database
limited by the availability of the source data, rather than the existing
limitations of current real-time graphics and computer generated forces
systems. In this sense, the resulting MOBA database represents a forward
solution that will only run optimally on future hardware and software systems.
Nonetheless, the use of level of detail representations for terrain, features,
and 3D models is a key aspect of the simulation database production process,
which cannot be ignored.
Case IV represented the most challenging and interesting case for M&S
database production. Use of unconstrained sources accentuated the importance
of selecting the "best available" source data from alternative sources.
However, this, together with the requirement to also process a 24 Km x
24 Km background maneuver area at SIMNET density, led to additional time
and labor resources needed to accomplish front-end GIS processing of the
available feature data. Additional data had to be acquired and processed
from available CONUS sources (i.e. US Army Waterways Experimentation Station,
US Geological Survey, US Census Bureau) to achieve comprehensive source
coverage for the entire database footprint.
6.1 Source
Data
This project involved the production of a M&S TDB from products generated
in Case Study IV. This meant that all available sources, including high
resolution aerial photographs, MC&G imagery, ground surveys, and engineering
drawings were to be incorporated directly in the M&S database production
process in order to produce the best possible M&S database. For the
purposes of this evaluation, only source data provided by DMA and GDE (through
TEC) was to be considered for usage in the high resolution McKenna MOUT
site area. Imagery was used by TEC to upgrade existing and available digital
topographic data received from these sources. In the course of the project,
significant shortfalls were identified in the quality, quantity, and adequacy
of the source data provided. Additional site-specific images were collected
at Ft Benning to support geospecific building textures for the McKenna
buildings. In addition, digital source products had to be procured for
the surrounding 24 Km x 24 Km low resolution area, in order to satisfy
the M&S requirements for this database. These additional products included
digital topographic data available from the US Geological Survey, the US
Census Bureau, and the US Army Waterways Experimentation Station.
6.2 Resources
Expended
A total of 1,856 hours were expended in the production of the M&S Database.
This includes 503 hours of general MOBA tasks, 718 hours for the 24 Km
x 24 Km maneuver box tasks, and 636 hours for the 4 Km x 4 Km tasks. It
should be noted that approximately 198 man-hours were expended as subcontract
labor, and that additional consulting costs were incurred in the process
of hiring a photographer to gather site-specific photographs used as texture
maps. These expenditures were not broken down into direct and indirect
costs.
6.3 Production
Process Assessment
Case IV represented the most challenging scenario for source data evaluation
and fusion. 115 man-hours were spent on these tasks, 30 hours more than
initially planned.
TIN Processing also exceeded initial expectations. This was the result
of a combination of factors, including the high density of the elevation
data being processed, the interaction of high density road data with the
elevation data in integrated TIN simplification, and the inexperience of
personnel who were using the TIN generation tool for the first time.
Manual editing and texture application proved to be time consuming,
but the end result was well worth the effort in the visual effect achieved
by high resolution, photospecific texturing.
Production of the 24 Km x 24 Km database, into which the McKenna MOUT
site was inset, proved to be slightly more time consuming than the population
of the Case IV inset. GIS processing, S1000 population, and associated
tasks (less the editing and texturing of the McKenna MOUT site models)
took a total of 718 man-hours for the 24 Km x 24 Km maneuver box, versus
636 man-hours for the 4 x 4 high density McKenna MOUT site area. These
levels of effort generally correspond to labor resource levels required
for previous SIMNET database projects.
M&S database design was complicated by uncertainty as to the specific
requirements and performance specifications of target simulators, including
real time graphics, simulation host, and computer generated forces applications
that will use this database now and in the future. We anticipate that additional
database enhancements and modifications will be necessary to support currently
fielded, and potential future simulation platforms. Experience gathered
in testing and evaluating this database to date indicates that significant
increases in the quality and efficiency of simulation platform performance
will be needed to enable this database to be run at full efficiency in
a virtual environment. Heightened interaction between simulation systems
developers and M&S TDB producers will assist in identifying specific
shortfalls and required database enhancements.
More detailed revisions to the 3D CAD models of the McKenna MOUT site
models were found to be necessary, in order to remove extraneous and inefficient
vertices and segments from the 3D models, and to create two levels of detail
for each McKenna building model. These measures were taken in order to
optimize real time updates in the 3D visual systems, which would have been
degraded by retaining the model geometry as digitized from engineering
blueprints. Photospecific texture application was done concurrently with
modifications to 3D model geometry
TIN processing methods also diverged from the initial project plan/process
model. In the initial plan, only one or two TIN iterations were planned
with no subsequent modifications to 2D features as input to a CMU iTIN
tool. A significant change to the initial process was repeated iterative
processing of the terrain skin and associated input feature data in a CMU
iTIN tool and ARC/INFO. The reprocessing of the TIN terrain surface was
necessitated by excessive smoothing of the terrain surface polygons in
the CMU iTIN tool output, which required multiple passes to create adequately
detailed terrain surfaces. Evaluation of TIN processing output was conducted
both before and after the TIN data was exported into S1000. Rather than
attempting to modify the TIN surface and associated 2D transportation features
in S1000, necessary 2D feature edits were done in ARC/INFO, followed by
subsequent reprocessing of the TIN terrain surface in the CMU iTIN tool.
6.4 Lessons
Learned
TIN processing represented a significant project milestone. Initial TIN
generation revealed significant loss of elevation accuracy due to road
density vis a vis specified polygon budgets. It is virtually impossible
to process an acceptable TIN database into S1000 on only one pass, using
state-of-the-art tools. This problem was eliminated by an iterative process
that both increased the polygon budget allocated to the terrain surface,
and by further filtering and editing of the 2D road geometry used in integrated
TIN processing.
Explicit tailoring of source data products to fit modeling and simulation
database design specifications is a necessary and unavoidable evil. Experience
during this project was that the database producer must be able to "pick
and choose" what data can and cannot be directly imported for use in the
terrain database, what data will be retained for analytical purposes only,
and what data will not be used at all.
Generation of multiple levels of detail building models was essential
to make this database usable on even the highest performance real time
graphics platforms. Real time performance would also be improved if S1000
were capable of processing hierarchical TINs at multiple levels of detail,
and morphing forest canopies into individual tree models and stamps.
A very large number of site-specific photographs were made available
to support the M&S database production team. These sources proved essential
to communicate visual database content, and were even more vital links
in the process, since none of the M&S database production team participated
in the site surveys at Ft Benning. Had S1000 modelers been available to
provide guidance to the original on-site photographers, and the initial
photographs been taken in color, redundant photography of the McKenna MOUT
site could have been alleviated.
More software tools are needed to optimize TINs, develop textures, build
adjustable phototexture libraries, accurately position building models,
provide quality control, and permit value adding,
7. TEC
Digital Elevation Models
7.1 Source
of Data
1:5000 scale frame aerial photography (45 images) were used for this case
study. Camera positions were photogrammetrically adjusted by aerial triangulation
to ground control and in flight GPS collected camera stations.
7.2 Original
Production Plan
Two databases were created, one at the scale of 1:5,000 with the same imagery
used at GDE and DMA to produce a DEM and orthophoto, but of a smaller area
than the GDE database. The second, at a scale of 1:20,000, was created
to produce a DEM and an orthophoto over a 5 Km x 5 Km area. One of the
DEMs was used within TEC to create a TIN for the simulation display. In
addition, a "Standard" DEM was created to be used as a comparison against
other DEMs.
7.3 DMA
Data Evaluation
A set of DMA ground control points, obtained from differential GPS ground
survey (but not tied to the state first order triangulation network) was
measured on the DSPW using the Coordinate Display tool. The identification
of the points were located on sketches and the data was provided in Geographics.
This data was converted to UTM. Table 1 lists
the differences between the coordinates in UTM of DMA and the measurements
made in the models and displayed on the Coordinate Display form. The differences
are DMA - TEC and shown in meters.
Table
1 Differences Between DMA Coordinates and Measurements on the Coordinate
Display Form
| Point Id. |
North |
East |
Elevation |
Point Id |
North |
East |
Elevation |
| 19008 |
+0.71 |
-0.71 |
-0.53 |
49012 |
+4.02 |
+2.40 |
+0.17 |
| 19010 |
-0.28 |
-0.08 |
-1.20 |
49013 |
+1.16 |
-1.15 |
-0.19 |
| 19018 |
+1.56 |
+0.30 |
-0.72 |
49016 |
+1.41 |
-1.32 |
-0.09 |
| 19020 |
- |
- |
-1.19 |
49017 |
+1.43 |
-1.44 |
+0.19 |
| 19021 |
- |
- |
-0.60 |
49021 |
+2.95 |
-1.24 |
-1.00 |
| 19027 |
- |
- |
-0.89 |
59003 |
+1.00 |
+0.37 |
-0.50 |
| 19028 |
- |
- |
-1.15 |
59004 |
+0.56 |
-0.37 |
+0.01 |
| 29006 |
+3.85 |
+0.48 |
-0.04 |
59005 |
- |
- |
-0.19 |
| 29007 |
+1.23 |
-0.25 |
-0.30 |
59006 |
- |
- |
+0.40 |
| 39007 |
+1.30 |
-0.49 |
-0.85 |
59007 |
-4.88 |
+2.26 |
-1.30 |
| 39009 |
+0.90 |
+0.42 |
-0.14 |
59008 |
-0.19 |
-0.66 |
+0.09 |
| 39010 |
+1.00 |
-0.84 |
-0.42 |
59009 |
-1.87 |
+1.31 |
-0.29 |
| 39011 |
+1.21 |
-0.53 |
+0.14 |
69018 |
- |
- |
-0.36 |
| 39013 |
- |
- |
+0.19 |
69019 |
- |
- |
+0.14 |
| 39014 |
+1.54 |
0.00 |
-0.22 |
69020 |
+0.41 |
-0.47 |
-0.13 |
| 39015 |
+1.47 |
-0.60 |
-0.68 |
69021 |
+0.31 |
-0.87 |
+0.10 |
| 39016 |
+0.98 |
+0.65 |
-0.45 |
69022 |
+0.59 |
-0.52 |
+0.63 |
| 39018 |
+0.02 |
+2.52 |
+0.13 |
69023 |
-0.44 |
-0.38 |
-0.63 |
| 49010 |
+1.02 |
+4.31 |
-0.04 |
69025 |
+0.01 |
-0.44 |
+0.19 |
|
|
|
|
79005 |
+0.47 |
-0.78 |
-0.77 |
|
|
|
|
|
|
|
|
|
|
|
|
Average: |
+0.78 |
+0.06 |
-0.32 |
The above data shows that the DMA control could be recovered to an accuracy
of one meter or below for the majority of points, but not always. This
is because of the absence of image detail that can be accurately recovered
by image measurement. The proper way is to place panels on the ground before
flying the photography. A dozen or less well selected points would have
been sufficient to verify the accuracy of the PSI data.
Table 2 shows the differences between
the 6 checkpoints used for control between the PSI and DMA as measured
in this dataset. These were measured the same way as the above data. The
data shows that there is very little difference between the PSI and DMA
control comparisons.
Table
2 Differences Between Checkpoints Used for Control Between the PSI and
DMA Coordinates
| PSI |
DMA |
DMA - TEC |
PSI - TEC |
| Pt. Id. |
Pt. Id. |
North |
East |
Elev. |
North |
East |
Elev. |
|
|
|
|
|
|
|
|
| ch1 |
49001 |
+0.60 |
-1.19 |
-0.22 |
+0.12 |
-0.47 |
-0.27 |
| ch2 |
69026 |
-0.91 |
-0.87 |
+0.20 |
-1.49 |
-0.09 |
0.0 |
| ch3 |
39028 |
+0.40 |
-0.86 |
+0.40 |
-0.11 |
-0.30 |
+0.09 |
| ch4 |
29005 |
+0.31 |
-0.27 |
-0.65 |
-0.37 |
+0.90 |
+0.19 |
| ch5 |
69005 |
+0.41 |
-0.67 |
-0.08 |
-0.15 |
+0.11 |
0.0 |
| ch6 |
49009 |
- |
- |
-0.24 |
- |
- |
-0.27 |
|
|
|
|
|
|
|
|
|
Average: |
+0.16 |
-0.77 |
-0.10 |
-0.40 |
+0.03 |
-0.04 |
7.4 Standard
DEM
TEC, upon the request of DMA/TEMPO, created the best possible DEM over
most of the "bare ground" area surrounding the MOUT site. This product's
purpose is to be used as a standard to compare other DEMs.
7.5 DEMs
From Other Sources
DEMs from DMA, ESRI, and USGS were imported and viewed to obtain an idea
of their accuracy.
7.5.1 DMA
DMA provided DTED level 3 and 4 data over the MOUT site, these databases
showed a definite elevation bias. The level 3 was approximately 3 meters
below the ground and the level 4 data about 1.5 meters below the ground.
7.5.2 IFSAR
The IFSAR data from ESRI was corrected by 27 meters from ellipsoid to mean
sea level height. The posts were for the most part quite close to the ground
in the "bare ground" areas, but were on the canopy or slightly lower in
the forested areas.
7.5.3 USGS
DEMs were obtained from USGS and processed before being imported in SOCET
SET. The 7.5 minute quadrangles Cusseta and Ochillee covered the 4 Km x
4 Km area. They were merged for this area. This data was most likely obtained
from the Gestalt system at USGS. The data is presented at 30 meter post
spacing. The data varies from fair to poor. It appears that the correlator
sometimes did not work as in certain areas the posts were at an even elevation.
7.6 Resources
The 1:5,000 scale database took 150 hours to complete. The 1:20,000 scale
database took 68 hours to complete. The "Standard" DEM took 42 hours to
complete.
7.7 Lessons
Learned
Photo Acquisition: Make sure that the company contracted will provide differential
GPS control for the camera and ground control points and has experience
in this technology.
Photo Scanning: Select a pixel size between 20 and 30 microns for the
resolution of the digital data. Make sure that 8-bit data is captured as
close as possible. Scan the full image including the photo identification
data. This will make it easier to insure that the intended photo is viewed
on the photogrammetric workstation. If the camera position needs to be
entered in the header file, the above-mentioned floppy of input data should
be loaded on this computer and the data pasted in.
Block Triangulation: The selection of weights for the camera and ground
control points is important. If differential GPS has been used, set the
weight of the ground control points to the expected accuracy of that point.
If it is a panel point, a weight of 0.05 meters is recommended for xyz.
For the camera control, which should be adjusted as discussed in paragraphs
above, a weight of 0.05 is recommended for X and Y, but a higher weight
should be used for the Z, such as 0.5 meters. This will take care of the
weakness in determining the z offset between antenna and camera and the
general weakness in Z determination of the camera. Another method is to
fly the camera first with the differential GPS over a test area with many
control points for a self calibration of the Z offset.
DEM Creation: Create DEMs with a small overlap between adjacent models.
Run some sample tests first (if not familiar with the strategy files) to
determine the best strategy file to use with the imagery. Use the contour
display and primarily the geomorphic editor to edit the data. If there
are large bodies of water, use the area editor (area fill) to edit these
polygons before correlation to speed up the correlation process.
8. Warfighter
Operational Evaluation Report
This section discusses the production and evaluation of environmental databases
for an urban training area at Ft. Benning, Georgia (the McKenna MOUT Site).
The purposes of the project were to: 1) develop high resolution mapping,
charting, and geodesy (MC&G) urban test data of use to the DoD modeling
and simulation community; 2) perform technical and user evaluations of
the databases with regard to accuracy, completeness, and utility; and 3)
provide results to decision makers faced with determining cost-effective
solutions to high-resolution ("one-meter") data requirements. The task
provided an opportunity to examine alternate production strategies for
the generation of high resolution terrain databases. The study team completed
both technical and subjective evaluations of the original databases and
derived products.
8.1 Evaluation
Results
-
Useful high-resolution digital MC&G elevation and feature data were
provided to describe the McKenna MOUT site at Fort Benning, GA.
-
High-resolution requirements exist; however one-meter data are not needed
uniformly throughout a region, or for every circumstance.
-
Data capture under forest canopy is a continuing problem requiring further
research and the aid of advanced sensor technologies.
-
Less than one percent of the MC&G high-resolution data can now be directly
accommodated in SIMNET runtime load modules.
-
The majority of warfighters queried stated that database features should
be positioned within five meters of their true location; A near majority
wanted positional accuracy within one meter for dismounted operations.
-
More capable computer image generators are needed to support high-resolution,
urban infantry operations.
8.2 Recommendations
-
Cognizant organizations should produce technical additions and improvements
to MOBA environmental databases and dismounted warrior simulation capabilities.
These would include:
-
Exploring autocorrelation and radar technologies for deriving improved
high-resolution DEMs.
-
Building upon the existing Fort Benning MC&G data repository to develop
improved Phase 2 runtime databases.
-
Finding means of better representing vegetation, micro terrain, and other
key features.
-
Working the Multiple-Z (i.e., multiple feature elevations at an X-Y location)
and data topology issues in both the McKenna and future high-resolution
databases.
-
The DMSO should furnish an improved capability to simulate individual combatant
behaviors. Actions would include:
-
Continued effort to improve representations for dismounted operations.
This includes improvement to hardware and environmental reasoning software
germane to simulation interfaces (precision control of dismounted forces
and stealth views).
-
Improved toolkits to assist in the generation of M&S products.
-
Improved ModSAF, ModStealth, and other Distributed Interactive Simulation
(DIS) software.
-
The Army Deputy Chief of Staff for Intelligence should endorse requirements
for better data collection and production, as well as improved mission
simulation systems. Based on the results of this evaluation, we recommend
the earmarking of resources for improvements in databases and tools critical
to the responsive production of topographic products for the warfighter.
9. DEM
Evaluations
This section documents the evaluations that were performed on the DEMs
which were generated for the Ft. Benning MOUT project. The evaluations
relate the ability of the evaluated DEMs to match "ground truth" data (DEM
and GPS survey points). The results of the DEM evaluations will be used
in conjunction with other evaluations to help determine each subject data
set's ability to satisfy the modeling and simulation requirements established
for this project.
These specific evaluations were performed on each test DEM: 1) Absolute
Vertical Accuracy was established by comparing each DEM to the GPS survey
points and to the base (control ) DEM. Range, mean and standard deviation
of differences in Z (vertical plane only) were calculated; 2) "Cornrow"/Artifacts:
The DTED level 4 data set extracted on the BC1-s stereoplotter was evaluated
in a "raw" state and after post processing to minimize the manual profile
(cornrow) artifact; 3) Vegetated Areas: Each test data set was compared
to an accurate (sub-meter relative accuracy) field terrain profile generated
by acquiring a dense profile of GPS survey points collected in heavily
vegetated areas. The vegetation in this area was primarily composed of
a large pine tree canopy; 4) Micro Relief: Each data sets' ability to depict
micro relief was evaluated by comparison to accurate (sub-meter accuracy)
field data (GPS survey points) collected over a terrain profile; 5) Relative
vertical accuracy was evaluated by comparing pairs of points from the control
micro relief profile data to each test data set; and 6) Various visual
displays were also generated to evaluate the characteristics of the data
sets. These included shaded relief, wireframe and contour portrayals.
In addition to the evaluations listed above there were additional evaluations
planned for this project. Two evaluations that were not completed, as software
development requirements could not be completed in time, were 1) A DX,
DY, DZ shift for each DEM compared to the control DEM was to be calculated
and applied to remove any horizontal or vertical shifts detected in the
test DEMs relative to the control DEM; and 2) A more rigorous relative
vertical accuracy was to be computed by comparing pairs of points in the
control DEM with each test DEM over varying distances
9.1 DEMs
Evaluated
-
meter post spacing DEM (equivalent to DTED lv 5) produced by TEC/GDE (control
DEM).
-
DTED level 2 ( 30 meter post spacing)produced by NIMA
-
DTED level 3 ( 10 meter post spacing) produced by NIMA
-
DTED level 4 ( 3 meter post spacing) produced by NIMA (without ground control)
-
IFSARE DEM (2.5 meter resolution) produced by ERIM.
9.2 Procedures
The DEMs were evaluated relative to absolute and relative vertical accuracy
via DEM to DEM and DEM to survey comparisons, and accurate relief depiction
in non-vegetated and vegetated areas via DEM to survey comparisons
DEMs were evaluated on the Interactive Quality Review System (SUN/UNIX
environment) utilizing ARC/INFO GRID functionality with NIMA enhancements
(DTED TOOLS). The TEC produced LV5 DEM was used as the control DEM data
set. GPS survey data produced by NIMA was used as survey control. The data
was loaded to the IQRS and DEM to DEM statistics were generated via ARC/INFO
STAT functionality. DEM to survey statistics were generated via ARC INFO
SEARCH functionality.
9.3 Results
Summaries
9.3.1 Matrix
to Matrix (post to post) Vertical Difference Statistical Comparison
Software used for this evaluation converts differences to integer values
to compute statistics. Differences were calculated as control lv 5 matrix
- test matrix, difference results are in integer meters.
| DEM |
MIN DIF |
MAX DIF |
MEAN DIF |
STD DEV |
90% LE |
| GDE LV 5 |
-5 |
47 |
0.768 |
5.197 |
8.548 |
| NIMA LV 4 |
-4 |
7 |
2.284 |
1.106 |
1.819 |
| NIMA LV 3 (DPS) |
-17 |
12 |
1.794 |
1.746 |
2.872 |
| IFSARE (ERIM) |
-29 |
5 |
-0.73 |
2.543 |
4.183 |
| NIMA LV4 SPRINT |
-4 |
7 |
2.283 |
1.093 |
1.799 |
| NIMA LV2 |
-1 |
16 |
5.559 |
2.311 |
3.801 |
9.3.2 Matrix
to GPS Survey Control Comparison
Values are in meters. Software used for this evaluation converts matrix
elevations to integer values. Data sets which covered more area (Sq. KM)
than the control set were not clipped to the control set size. Thus larger
data sets also had more GPS control within the SEARCH area.
| DEM |
# OF POINTS |
MEAN |
STD DEV |
90%LE |
| GDE LV 5 |
22 |
-0.010 |
0.558 |
0.917 |
| NIMA LV 4 |
40 |
-1.974 |
1.483 |
2.439 |
| NIMA LV 3 (DPS) |
97 |
-1.748 |
1.655 |
2.723 |
| IFSARE (ERIM) |
40 |
-0.498 |
1.605 |
2.639 |
| NIMA LV 4 (SPRINT) |
40 |
-1.965 |
1.475 |
2.426 |
| NIMA LV 2 |
87 |
-4.286 |
4.743 |
7.802 |
| CONTROL LV 5 |
22 |
-0.056 |
0.449 |
0.739 |
9.3.3 Vegetated
and Micro-Relief Evaluation
Results of comparisons to profiles collected in tree coverage areas (two
separate profiles) were as follows:
Profile 1:
| DEM |
# OF POINTS |
MEAN |
STD DEV |
90%LE |
| CONTROL LV 5 |
203 |
1.096 |
2.656 |
4.370 |
| NIMA LV 4 |
203 |
1.960 |
4.069 |
6.695 |
| NIMA LV 3 (DPS) |
203 |
9.696 |
5.177 |
8.515 |
| IFSARE (ERIM) |
203 |
12.201 |
3.659 |
6.019 |
| NIMA LV 4 (SPRINT) |
203 |
1.748 |
3.623 |
5.960 |
| NIMA LV 2 |
203 |
0.058 |
3.022 |
4.971 |
Profile 2:
| DEM |
# OF POINTS |
MEAN |
STD DEV |
90%LE |
| CONTROL LV 5 |
201 |
-0.939 |
0.761 |
1.252 |
| NIMA LV 4 |
201 |
-2.189 |
0.867 |
1.426 |
| NIMA LV 3 (DPS) |
201 |
-0.145 |
1.496 |
2.462 |
| IFSARE (ERIM) |
201 |
7.43 |
2.293 |
3.772 |
| NIMA LV 4 (SPRINT) |
201 |
2.331 |
0.715 |
1.177 |
| NIMA LV 2 |
201 |
-4.978 |
1.003 |
1.651 |
Results of comparisons to the profile collected in an open area (no trees)
depicting micro relief characteristics are as follows:
| DEM |
# OF POINTS |
MEAN |
STD DEV |
90%LE |
| CONTROL LV 5 |
118 |
-0.061 |
0.711 |
1.170 |
| NIMA LV 4 |
118 |
-3.147 |
0.501 |
0.824 |
| NIMA LV 3 (DPS) |
118 |
-2.606 |
0.545 |
0.895 |
| IFSARE (ERIM) |
118 |
0.817 |
0.643 |
1.058 |
| NIMA LV 4 (SPRINT) |
118 |
-3.034 |
0.529 |
0.871 |
| NIMA LV 2 |
118 |
-11.794 |
0.557 |
0.917 |
9.3.4 Relative
Vertical Accuracy Analysis
Relative vertical accuracy was calculated based on results from the comparisons
of the matrices to the micro-relief GPS ground survey. Every tenth survey
point was used in the analysis. Results of vertical accuracy analysis expressed
as 90% confidence linear error are:
| DEM |
Relative Vertical 90% LE |
| CONTROL LV 5 |
1.46 |
| NIMA LV4 |
1.00 |
| NIMA LV3 DPS |
1.22 |
| IFSARE ERIM |
1.21 |
| NIMA LV2 |
1.10 |
9.4 Analysis
of Results
9.4.1 DEM
to DEM evaluation
-
The NIMA data sets appear to be lower (mean) than the GDE/TEC data sets
(level 3 and 4 about 2 or 3 meters, level 2 about 5 meters). The NIMA data
sets were generated from standard MC&G triangulation solutions without
incorporating the GPS survey results, thus this difference is not surprising.
The GDE (and TEC) data sets were generated from imagery which utilized
the GPS survey as triangulation control.
-
The GDE level 5 data set to TEC control data set comparison yielded larger
than expected 90% (8.5 meters) and min/max range values, this may indicate
that some "intermediate" data set generated by GDE was shipped to NIMA.
All of the level 5 data sets were supplied to NIMA via TEC.
-
The large negative difference (min) reported for the IFSARE comparison
occurred around the lake area, and appeared to possibly be caused by layover
(trees?) close to the boundary of the lake.
9.4.2 DEM
to GPS survey
-
NIMA data is confirmed to be low to the GPS survey (level 3 and 4 about
2 meters, level 2 about 4 meters).
-
The GDE/TEC data sets yield extremely low 90% values from this comparison.
These results can be attributed to two factors; the increased resolution
of the data sets (less interpolation error in the SEARCH directive) and
the fact that the imagery was triangulated using this very data set as
control.
9.4.3 DEM
to GPS Ground Profile (Tree coverage areas)
-
None of the data sets did a particularly good job of portraying the ground
surface under the tree canopy. This conclusion is based on analysis of
the graphical profile data generated via SPYGLASS Transform software.
-
The IFSARE and GPS generated data sets were portraying elevations more
closely representative of the top (or near to the top) of the tree canopy
(reflective surface).
9.4.4 DEM
to GPS Ground Profile (Open micro relief area)
All of the data sets exhibit extremely low 90% LE values. Given the nature
of our evaluation software (rounding to integers) they are virtually identical.
9.4.5 DEM
relative vertical accuracy
Again given the limitations of the software used for this statistical evaluation
all of the data sets are virtually identical.
9.4.6 Visual
display analysis
-
The TEC control level 5 data set and the GDE level 5 data set exhibit extremely
high resolution detail on shaded relief displays in the open (dirt) areas,
and are for the most part devoid of extraction/edit artifacts. It is obvious
that the tree covered areas were interpolated to this resolution from a
less dense post spacing.
-
The NIMA data exhibits the manual profile artifacts a.k.a. "corn rows".
NIMA cartographers attempted to profile the ground surface through the
tree cover. Generally the severity (magnitude) of the artifact varies with
the obscuration factor (in this case tree cover). Open (dirt) areas are
less affected than tree covered areas. Attempts to edit out this artifact
using production software are generally only semi-successful as evidenced
by the "SPRINT" data displays.
-
The DPS produced level 3 data exhibits very good resolution in the open
(dirt) areas, with little extraction or edit artifacts evident. The tree
areas were intentionally left as extracted by the correlator, only large
positive/negative spikes were removed.
-
The ISARE data also does a good job of portraying the ground surface in
the open (dirt) areas. This data set also portrays tree canopy (reflective
surface) heights over dense tree coverage areas, similar to the DPS correlator
solution.
10. Feature
Data Accuracy Evaluation
This section documents the accuracy evaluation of all the feature data
sets produced to evaluate terrain data generated for the McKenna MOUT Site.
The data sets include one generated by GDE Systems, Inc., three constructed
by DMA, and one S1000 database. This was primarily an analysis of feature
horizontal position accuracy, although considerable insight into data completeness
and representational accuracy was gleaned from the effort to assess position
accuracy. A photogrammetric data set, prepared by TEC, was used as the
standard for the evaluation. Coordinates of well- defined points on the
features were read from the TEC Photogrammetric Models. Coordinates of
the same points were determined from each feature data set using ARC/INFO.
Position differences between the points in the photogrammetric model and
the data sets were calculated and graphics were prepared to provide a quantitative
and visual estimate of the absolute and relative horizontal position accuracy
of the terrain feature data. Feature Data Accuracy Evaluation Tables.The
evaluation concluded that the GDE Data Set was the most accurate, one prepared
by DMA from the same imagery was the next most accurate, one prepared by
DMA using sources and techniques used to produce standard ITD was third,
and the DMA Data Set made by supplementing the ITD from larger scale imagery
was least accurate. A further conclusion was that errors in plotting were
more significant than systematic errors. The accuracy was further degraded
in constructing a S1000 database for SIMNET Simulation.
An absolute and relative horizontal positional accuracy evaluation of
the feature data sets prepared by DMA and GDE for the MOUT Project was
conducted by TEC. This evaluation, which was performed in the Topographic
Technology Laboratory (TTL) of TEC, is closely related to the evaluation
of other quality aspects of the feature data sets performed by the Military
Operations in Built-up Areas Terrain Database Technical Evaluation Working
Group. Some of the insights that resulted from the metric accuracy assessment
are included in this report and were provided to TEC's Digital Concepts
and Analysis Center (DCAC) for use in the working group's assessment. The
source data (photogrammetric data base) used in the TTL evaluations was
also used to provide products for use in the Operational Warfighter Evaluations.
10.1 Evaluation
Plan
Originally TEC planned to use the DMA GPS ground control points to evaluate
feature accuracy. However, none of them were located on well-defined feature
points. Therefore, the procedure was modified to compare well-defined feature
point coordinates from the various data sets to coordinates of those same
points read from the TEC "Coordinate Standard" Photogrammetric Data Set.
Absolute accuracies were determined from a direct comparison of these coordinate
values. Differences in control surveys upon which each set was based were
to be taken into account in making the comparisons. Operator interpretation
of the points was recognized as a part of the errors detected. The points
were chosen carefully in an attempt to minimize this factor. Relative accuracies
were determined by aligning all data sets to the photogrammetrically determined
coordinates.
10.2 Evaluation
Procedures
Fifty-two well defined feature points which appeared in both GDE's high
resolution feature data and in DMA's Enhanced ITD data sets were chosen
for use in the assessment. A fifty third point which appeared only on the
GDE Feature Data was also used. Four of these points were later discarded.
UTM Coordinates of each point were read from TEC's Photogrammetric Data
Set. UTM Coordinates of the same points were determined from the GDE and
DMA digital feature data sets using ARC/INFO software. These readings were
then compared to the TEC "standard" coordinates.
During the early part of the evaluation, a variation between the PSI
and DMA GPS Control Surveys was discovered. Table
3 shows the differences at the six paneled ground points established
by PSI. The DMA Triangulation Report shows the same approximate differences.
DMA applied these offsets to its photo stations before doing triangulation.
There was considerable discussion among DMA, TASC, NOAA, and TEC about
these differences, but the consensus seemed to be that the results seen
are at about the limits of GPS positioning accuracy. TEC received informal
information that a DMA resurvey of the area did not resolve the differences.
Table
3 Variation Between PSI and DMA Coordinates
|
DMA Coordinates |
PSI Coordinates |
Difference |
| Point |
Easting |
Northing |
Elev |
Easting |
Northing |
Elev |
East |
Northing |
Elev |
| 39028 |
5387.52 |
5700.77 |
137.745 |
5388.08 |
5700.28 |
137.44 |
-0.56 |
0.49 |
0.31 |
| 49009 |
6574.84 |
3552.94 |
129.427 |
6575.60 |
3552.38 |
129.40 |
-0.76 |
0.56 |
0.03 |
| 49011 |
6518.13 |
3658.20 |
130.197 |
6518.85 |
3657.72 |
130.15 |
-0.72 |
0.48 |
0.05 |
| 69026 |
8145.38 |
4967.59 |
138.987 |
8146.16 |
4967.02 |
138.97 |
-0.78 |
0.57 |
0.02 |
| 29005 |
4906.98 |
2481.93 |
111.833 |
4907.8 |
2481.36 |
111.94 |
-0.82 |
0.57 |
-0.11 |
| 69005 |
8285.68 |
2009.83 |
123.885 |
8286.46 |
2009.27 |
123.97 |
-0.78 |
0.56 |
-0.08 |
|
|
|
|
|
|
AVG |
-0.74 |
0.54 |
0.03 |
Because the GDE photogrammetric data sets and the TEC photogrammetric models
were both based on PSI GPS Control, the comparison between the TEC Photogrammetric
Standard and GDE Feature Data was made directly. DMA data sets were believed
to be based on DMA GPS control and, consequently, the offset between DMA
and PSI Control was applied before the comparisons were made for those
data sets. Later information about the DMA Data Sets and other subsequent
findings led to a change to this approach.
The TEC Photogrammetric Block was initially triangulated using only
the PSI supplied GPS Control for the camera stations. Later two of the
paneled ground points established by PSI were incorporated into the solution
in an attempt to improve the vertical accuracy of the block. In addition
to the internal checks and evaluations made by TEC in triangulating the
photogrammetric block, some additional accuracy assurances were obtained
by comparing coordinates of ground points established by GPS with those
read from the block.
Table 4 compares coordinates measured
photogrammetrically at TEC with the PSI GPS coordinates for the three paneled
points which fall within the block. Except for one of the elevations, the
two sets of coordinates agree to within less than 0.1 meter at these three
points. This indicates a high degree of consistency between the block and
points used to control it.
Table
4 Comparison Between PSI and TEC Coordinates
|
PSI Coordinates |
TEC Coordinates |
Difference |
| Point |
Easting |
Northing |
Elev |
Easting |
Northing |
Elev |
East |
Northing |
Elev |
| 49009 |
6575.60 |
3552.38 |
129.40 |
6575.54 |
3552.40 |
129.34 |
0.07 |
-0.01 |
0.06 |
| 49011 |
6518.85 |
3657.72 |
130.15 |
6518.90 |
3657.75 |
130.52 |
-0.05 |
-0.03 |
-0.37 |
| 69026 |
8146.16 |
4967.02 |
138.97 |
8146.23 |
4966.95 |
138.96 |
-0.07 |
0.08 |
0.01 |
|
|
|
|
|
|
AVG |
-0.02 |
0.01 |
-0.10 |
Coordinates of the DMA established ground control points were also compared
to readings taken from the TEC Photogrammetric Block. Thirty-four of the
DMA points fell within the approximately 2.5K by 2.5K area covered by the
TEC Block. Two of these could not be identified by TEC from the descriptions
provided by DMA. The coordinates for a third had clearly not been read
at the point described. Two others were later thrown out because they were
poorly defined and compared poorly with the DMA Coordinates. The first
of these was one of a number of points positioned at the point of vegetation
at a road fork. In this case there were several locations which could have
been rationalized to be the point, none of which matched the DMA coordinates
well. The other was a tip of land into a lake which could not be selected
reliably on the 1:5,000 imagery although it appeared quite clear on the
1:20,000 photos flown a few months later. It is no accident that these
points were also eliminated from the comparisons made in the DMA Triangulation
Report.
The horizontal bias (most probable error) detected closely approximates
the differences between the DMA and PSI Surveys. Consequently, the TEC
Coordinates were shifted by the amount of the difference between the DMA
and PSI Coordinates. The comparison of these shifted coordinates to the
DMA Coordinates shows only a slight bias (a circular error of .08 meter)
and standard deviations of .36 meter in easting and .23 meter in northing.
From these values a CPE of .35 meter was calculated. Thus, 50 percent of
the well defined points within the block will be within .35 meter of their
true locations relative to other points in the block and virtually all
points (99.78%) will be within 1.04 meters. With respect to the DMA Control,
50 percent will be within .43 meter and virtually all within 1.12 meter.
Given the nature of the test points this is a very good match. At the three
paneled ground points established by PSI, the match is .16 meter (circular)
or less. Two of the points with larger differences, 69017 and 69022, were
omitted in the DMA Triangulation Report indicating that DMA also had trouble
with them. For three others, DMA also showed large differences, though
not necessarily in the same coordinate.
The vertical bias has not been explained. TTL members used equations
provided by TEC's Geodetic Applications Division to check some of the camera
station elevations used in the triangulation. No significant differences
were found. The source of error may be in converting the elevation from
aircraft antenna to camera lens, although the amount of error seems rather
large for this explanation. Note that the vertical bias decreased to less
than one-third meter after the ground control was incorporated into the
triangulation. The DMA Triangulation Report indicated vertical biases of
approximately the same magnitude.
10.3 Results
Summary
Tables F - 3 through F- 7, Annex F, created by TTL, show the point by point
comparisons for Cases 1 through 4 and SIMNET S1000, respectively. Note
that, except for Case I, not all the test points were found in each data
set. The most probable error, maximum error, minimum error, and standard
deviations are computed for each case and the values are consistent with
the plots of the data in Figures F - 1 through F - 15, Annex F. Based on
analysis of the statistics in the tables, the GDE Feature Data is the most
accurate, Case IV is the next most accurate, Cases II and III are roughly
equivalent, and S1000 is lowest in accuracy.
10.3.1 Control
Bias
The summary tables show a bias (the most probable error) in every data
set. Originally, these comparisons for the DMA Data were made against TEC
coordinates offset to fit the DMA GPS Control. TTL later learned that Cases
II and III were not made from that control. Then a plot of the relative
positions of the control solutions (Figure 7)
showed that Case IV also fit the TEC (PSI) Control better than the DMA
Control. This is despite statements in the triangulation report that camera
stations had been adjusted to fit the DMA Control. One possible explanation
for this anomaly is that the longitude offset may have been applied with
the wrong sign. After this situation came to light, all comparisons were
made to raw TEC Coordinates. Converted to a circular error, the biases
are .57 meter for Case I, .86 meter for Case II, 1.04 meters for Case III,
.63 meter for Case IV, and .86 meter for S1000. These can be considered
as differences in the control solutions for the photogrammetric data sets
from which the data were extracted. The remaining errors are random errors
in compiling the features. Once the biases were removed relative accuracies
could be determined.
Figure 7 Relative Positions of Control
10.3.2 Error
Estimation
For each case, an approximate Circular Probable Error was computed from
the standard deviations in easting and northings. The relative error of
50 percent of the well-defined points within the data set should not exceed
this value. From this value, the 3.5 sigma circular error which includes
99.78 percent of all points was computed. To determine absolute error,
the most probable error was added to the relative values. The figures found
for the cases are shown below.
|
Relative |
|
Absolute |
|
CPE (50%) |
99.78% |
|
CPE (50%) |
99.78% |
| Case I |
1.82 m |
5.41 m |
|
2.39 m |
5.98 m |
| Case II |
4.40 m |
13.09 m |
|
5.26 m |
13.95 m |
| Case III |
4.53 m |
13.47 m |
|
5.57 m |
14.52 m |
| Case IV |
3.11 m |
9.24 m |
|
3.74 m |
9.87 m |
| S1000 |
3.46 m |
10.27 m |
|
4.32 m |
11.13 m |
10.3.3 Azimuth
Checks
Azimuth checks were made on the six longest buildings in the MOUT Area.
Table 5 shows azimuths computed from the
GDE, DMA, and S1000 feature data for the long side of the building extending
from the designated test point compared to azimuths of the same building
sides measured in the TEC Photogrammetric Models. This is not a statistically
significant sample and one must bear in mind that the baselines are so
short that small errors in positioning have a significant effect on the
accuracy of the computed or measured azimuths.
The largest errors are in Case II which is not surprising, given that
the imagery was smaller in scale and the buildings were much smaller. The
most probable errors indicate a counterclockwise rotation of from .23 to
.44 degrees between Cases I, III, and IV and the TEC Photogrammetric Block.
The Case II data seems to be rotated by nearly 2 degrees in the other direction.
The SIMNET S1000 azimuths show little overall bias from TEC. Azimuths over
a longer baseline, from Point 10 to Point 42, were compared to check the
validity of these conclusions. For this baseline, TEC, Case I, and Case
IV Azimuths were essentially identical. The Case III Azimuth still showed
a counterclockwise rotation, but by about half as much. The Case II Azimuth
now showed a counterclockwise rotation of about one degree.
Table
5 Azimuth Angle Differences
| Point |
Description |
TEC |
Case I |
Diff. |
Case II |
Diff. |
Case III |
Diff. |
Case IV |
Diff. |
SIMNET |
Diff. |
| 1 |
NW Bld H Corner |
74.35 |
73.72 |
-0.63 |
76.68 |
2.33 |
72.59 |
-1.76 |
75.06 |
0.71 |
73.66 |
-0.69 |
| 2 |
NW Bld L Corner |
97.87 |
98.04 |
0.17 |
100.92 |
3.05 |
96.60 |
-1.27 |
96.98 |
-0.89 |
97.21 |
-0.66 |
| 3 |
SE Bld A Corner |
8.16 |
7.30 |
-0.86 |
8.78 |
0.62 |
8.19 |
0.03 |
7.92 |
-0.24 |
7.54 |
-0.62 |
| 44 |
SW Bld G Corner |
78.21 |
77.60 |
-0.61 |
74.61 |
-3.60 |
77.11 |
-1.10 |
76.73 |
-1.48 |
77.62 |
-0.59 |
| 46 |
NW Bld I Corner |
71.05 |
71.50 |
0.45 |
79.64 |
8.59 |
72.86 |
1.81 |
71.74 |
0.69 |
73.21 |
2.16 |
| 47 |
NW Bld E Corner |
71.75 |
71.68 |
-0.07 |
71.97 |
0.22 |
71.38 |
-0.37 |
71.60 |
-0.15 |
71.79 |
0.04 |
|
|
|
Prob. Value |
-0.26 |
|
1.87 |
|
-0.44 |
|
-0.23 |
|
-0.06 |
|
|
|
MIN ERR |
-0.07 |
|
0.22 |
|
0.03 |
|
-0.15 |
|
-0.15 |
|
|
|
MAX ERR |
-0.86 |
|
8.59 |
|
1.81 |
|
-1.48 |
|
-1.48 |
|
|
|
STD DEV |
0.47 |
|
3.67 |
|
1.17 |
|
0.79 |
|
1.02 |
Overall, the Case I azimuths have the best relative consistency (about
two-thirds are within .47 degree) and Case IV is the second best (about
two-thirds within .79 degree). By redoing the buildings, Case III seems
to have improved azimuths significantly from Case II.
The S1000 Azimuths, individually, do not track their source (Case IV)
too well, but have an internal consistency that is not much worse.
10.4 Analysis
of Results
The results of this test show that the photogrammetric method used has
the inherent accuracy to provide accurate feature data. The most probable
errors, attributed to differences in the fit of the photogrammetric data
sets to control, are all rather small. Most of the error resulted from
"random" errors in delineating the features. The accuracy of the data sets
could have been improved by throwing out some of the points with the largest
errors, but this could be seen as rewarding sloppy work. In fact, four
of the original 53 test points were omitted in the evaluation. It may be
instructive to review these points and some of the largest errors in all
the data sets. The comments below can be understood better by referring
to the evaluation plots of the individual points which are included in
Annex H. Note that these plots are over an orthophoto constructed at TEC
based on PSI Control. For many of the buildings, these plots include DMA
GPS Positions provided by DCAC. The locations of these points with respect
to the TEC points is generally consistent with the original control bias.
10.4.1 Discarded
Points
Point 27, the corner of a clearing beside the road, was discarded. Some
of the compilers included the road as part of the clearing and some didn't.
The eastern edge of the clearing is approximately perpendicular to the
road but was not delineated correctly enough to be a test point either.
Point 32, the point of a nearly right angle change in direction of the
shore of a small lake and bounding trees, falls off the orthophoto. It
was not delineated by any of the compilers. Clearly each generalized the
boundary in different ways. Point 33, a road fork was delineated very differently
by GDE and DMA. Because this point, too, falls off the orthophoto, the
stereo model was rechecked to determine where the side trail runs. No indication
of a trail on the alignment shown by DMA could be found. Point 49, a lone
tree, is actually two trees together. DMA chose only to delineate the eastern
most tree while GDE placed the lone tree symbol between the two.
10.4.2 Case
I Errors
GDE provided the most accurate, though not necessarily the most complete
feature set, but it could have been better if some of the largest errors
could have been avoided.
-
The maximum easting error in this data set occurred on Point 37, a lone
tree. TEC found this to be one of the more well-defined trees and the Case
IV compilers positioned it much more accurately. The maximum northing error
was on Point 9, a road fork. From the diagram of the point, it appears
that the roads had to be intersected by TEC. The roads meet at a shallow
angle making it difficult to position accurately. Nearby, there is a fenced
installation with a small building and a tower of some sort which would
have provided excellent test points, but none of the compilers included
it.
-
Some of the other largest errors in this case were in compiling hard stand
corners (Points 13, 14, and 15) which were obscured by trees and shadows.
Enough sections of the edges were visible to have allowed determining their
alignments well enough to position the corners much better.
-
Point 30 might have proved better if GDE had connected the trails at the
intersection. TEC had to connect the end nodes of the two cross trails
with a straight line. The large error on Point 26 could have been avoided
by taking more care in delineating the timber boundaries. Several other
of the larger errors were on lone trees which were definitely difficult
to see in the stereo models.
10.4.3 Case
II Errors
That Case II was among the least accurate of the feature sets is not too
surprising because it was compiled from lower resolution imagery. The data
is not very much less accurate than some of the data compiled from the
large scale imagery. However, many of the smaller features were not included
and the buildings were not delineated very accurately. Again the accuracy
results were degraded by very large errors on a small number of points.
-
The largest northing error in this set is on Point 5, a trail fork or trail
end. On the large scale imagery, there does not seem to be any indication
of a trail extending to the point included in Case II. The largest easting
error was on Point 14, a hard stand corner. Some other of the larger errors
were on other similar corners. While TEC has not seen the imagery used,
the comments concerning these points in the GDE analysis are believed to
be applicable here, too.
-
Large errors were also made in delineating Point 26, a vegetation/lake
or wetlands boundary. This, as in the previous case, seems to be a lack
of care in delineating the boundary.
-
Other significant errors were on buildings, which were probably quite small
on the imagery, and road intersections. (Points 7, 8, 10, and 34.) The
latter may have been caused by trees obscuring the side roads, although
the road alignments appear different from the other cases.
10.4.4 Case
III Errors
Case III is an augmentation of Case II (standard ITD) using large scale
imagery. Points 6-8, 11, 13-15, 22, 30, and 34 were retained from Case
II. Features which created points 9, 12, 16-18, 20, 21, 23, 24, 26, 28,
29, 31, 45, 50, and 51 were added. Features containing many of the remaining
points were redone. That this feature set had a lower positional accuracy
than Case II is puzzling. The systematic error (control bias) in this set
is also larger than and on a different azimuth from Case II, raising questions
about the techniques used to register the ITD Features and the higher resolution
imagery.
-
The maximum easting error in this set was on a point (16, a clearing corner)
on one of the added features. This particular clearing was determined to
be wetlands based on ground truth verification. The boundaries shown do
not seem close to the edge of the clearing except in the northernmost section
of the plate. The delineation was distorted by being connected to an edge
from Case II. The largest northing error was also on an added feature (26,
a vegetation corner). Though not readily discernible on the ortho, there
is a pretty clear right angle in the tree boundary at this point which
none of the compilers has shown properly.
-
Except for Points 9 and 10, road intersections from Case II, which were
not very accurate, were retained. The intersection at Point 10 was redone
much more accurately and the intersection at Point 9 was added fairly well.
All the buildings; Points 1-4, 36, 39-44, and 46-48; were redone without
in general improving the accuracy of their delineation. Also retained were
some of the least accurately positioned hard stand corners in Case II (11
and 13-15).
-
Of the other features added, the one that created the road fork designated
Point 28 was the least accurate. This was because the trail added was joined
to another trail from Case II which was not correctly aligned. A fairly
large error at the drain fork (Point 24) is due to poor alignment of the
drains added. The trail added to form Point 28, a T intersection, is poorly
aligned resulting in a significant error at that point. The same is true
at Point 31. Some of the other larger errors were caused by tying to Case
II features which were misaligned. This compiler, like the others, had
understandable difficulty with the lone trees.
10.4.5 Case
IV Errors
Case IV was compiled from the same large scale imagery used in Case I.
Again, it is instructive to look at some of the larger errors in this data
set.
-
The largest error is a northing error for Point 5, a trail end. This trail
was dropped about 16 meters short of the trail junction delineated in Case
I. The largest easting error was on a hard stand corner, Point 14. Like
the others, this compiler did not use the edges of the hard stand to position
the corner correctly.
-
The next most significant error was on Point 9, a road fork. The same comments
as in paragraph 15.6.2 1. above apply. This is a point that perhaps should
have been omitted. Another large error is seen at Point 34, a T intersection.
The side road in this data set is drawn as if it curved into the other
road.
-
Other relatively large errors were experienced in delineating hard stand
corners. The size of the error at Point 6, the road and railroad crossing,
is surprising. A similar error at Point 26, a vegetation corner, is the
lowest for this point in any of the cases. However, the delineation of
the timber edge is not any better. Most of the other large errors were
in delineating lone trees, which was a problem for all compilers.
10.4.6 S1000
Errors
The accuracy of this data set are not much larger than those of Case IV
from which the S1000 data was derived. The individual points are fairly
consistent between the two data sets. Some of the largest discrepancies
occurred at Points 6, 7, 9, 12, 13, 23, 40, and 48. These discrepancies
are thought to have happened when the features were generalized to fit
into the TINed terrain skin.
10.5 Summary
This evaluation demonstrates that the methods used are capable of providing
feature data with an absolute accuracies of from about 6 to 15 meters.
The accuracies will be degraded somewhat in converting to a SIMNET S1000
Data Base. Clearly, the major portion of these errors is in delineating
the features. Although TEC believes that results could have been better
in this particular case, everyone should bear in mind that these accuracies
are extremely good for terrain data in general.
Compilers using care and perhaps improved techniques could lower the
range of error considerably. Evidence that this is possible was provided
by recalculating the statistics based on the most accurate 30 points in
each case, except Case II which only included 28 of the test points. The
accuracies estimated from these limited points are shown below. The control
biases also changed in both magnitude and direction, decreasing to .17
meter for Case I and increasing to 1.29 meters and .84 meters for Cases
III and IV, respectively. This provides further indication that the plotting
accuracies are the major source of error.
|
Relative |
|
Absolute |
|
CPE (50%) |
99.78% |
|
CPE (50%) |
99.78% |
| Case I |
.62 m |
1.86m |
|
.79m |
2.02 m |
| Case III |
1.58 m |
4.69m |
|
2.87 m |
5.98 m |
| Case IV |
1.08 m |
3.20 m |
|
1.92 m |
4.04 m |
One can see from these results that accuracies in the 2 to 3 meter range
may be possible. Again remember that these data sets were compiled from
high resolution imagery which meant trading additional production time
for higher resolution and accuracy.
10.6 Lessons
Learned
The accuracy of photogrammetric data sets could have been evaluated much
more rigorously had any GPS test points been established and paneled prior
to the flying of the imagery. Then, there would be little doubt where they
are located. At least some feature test points could also be positioned
by GPS at the same time. GPS Surveys are also subject to error, but the
existence of such ground coordinates would add to the reliability of the
evaluation.
Imagery to be used for generation of data to be evaluated should be
flown at the ideal time. The Fort Benning Area, with its dark coniferous
tree cover and light sandy soil, is definitely a difficult area to image.
The situation was made worse when the imagery was flown early in the morning
adding many large shadows to the already high contrast imagery. Larger
scale imagery flown later in the year and more nearly in the middle of
the day is much clearer and allows a much more accurate positioning, even
of lone trees. Incidentally, use of a digital photogrammetric system for
data compilation in difficult areas such as this offers the advantage of
being able to adjust the image photometry in any particular situation to
improve positioning accuracy.
Standard coverage naming and feature classification conventions should
be established in advance and given to all compilers. Also, the projection
and datum should be standardized in advance to avoid errors that might
occur in converting from one to another.
Some changes in techniques for and more care in compiling the features
should provide improved accuracies. Compilers could be given some idea
in advance about how the comparisons will be done.
The techniques for overlaying feature data on orthophotos used for this
project was very effective in comparing the data sets. This technique may
have potential in quality control.