COST ($ In Thousands) | FY 1996 Actual | FY 1997 Estimate | FY 1998 Estimate | FY 1999 Estimate | FY 2000 Estimate | FY 2001 Estimate | FY 2002 Estimate | FY 2003 Estimate | Cost to Complete | Total Cost |
2758 | Combat Intelligence System (CIS) | 0 | 0 | 12,267 | 10,499 | 10,421 | 9,266 | 7,773 | 6,875 | Cont. | TBD |
Quantity of RDT&E Articles | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
(U) Note: This funding request was previously programmed across PEs 0604321F, 0207431F, and 0305158F. They have been consolidated here in PE 0207414F for program clarity and reporting efficiency.
(U) A. Mission Description and Budget Item Justification
(U) Combat Intelligence System (CIS) is the Air Force's single, standard automated intelligence system optimizing both component and unit-level intelligence functions to provide warfighters with the most accurate and timely intelligence data available. CIS is the core capability for automating the receipt, correlation, and dissemination of intelligence information to a variety of intelligence and operational systems which support combat planning and execution. As the intelligence segment to Theater Battle Management Core Systems (TBMCS), it provides an automated capability at the component and unit levels to rapidly receive and process all-source intelligence data to support Contingency Theater Automated Planning System (CTAPS). CIS builds and maintains in-theater situational awareness during deployment to the theater and provides indications and warning support after arrival. CIS is electronically interoperable and compatible with other intelligence systems, providing an integrated network capable of intelligence support to decision makers, battle planners, mission planners, and warfighters. The category of research being performed in this program is Engineering and Manufacturing Development, because it develops new capabilities to upgrade current systems.
(U) Acquisition Strategy: Full and open competition has led to a cost plus award fee contract with Lockheed Martin Command and Control Systems (Colorado Springs, CO) to develop capabilities and integrate this system and software.
(U) FY 1996 and FY 1997: Execution year funding remains programmed across PEs 0604321F, 0207431F, and 0305158F.
(U) FY 1998
(U) $10,167 | Complete software development for TBMCS Version 1.0 release, and initiate TBMCS software Version 2.0 development. |
(U) $ 900 | Implement results of studies for CIS Intelligence Interoperability |
(U) $ 1,200 | System engineering and support. |
(U) $12,267 | Total |
(U) FY 1999
(U) $ 9,414 | Continue software development for TBMCS V2.0 release and intiate TBMCS software version 3.0 planning and design. |
(U) $ 1,085 | Continue studies for CIS Intelligence Interoperability |
(U) $10,499 | Total |
(U) B. Program Change Summary ($ in Thousands)
FY 1996 | FY 1997 | FY 1998 | FY 1999 | Total
Cost |
(U) FY97 President's Budget | 0 | 0 | 0** | 0** | TBD |
(U) Appropriated Value | 0 | ||||
(U) Adjustments to Appropriated Value | |||||
a. Cong Reductions | |||||
b. Small Business Innovative Research | |||||
c. Omnibus/Other Above Threshold Reprogramming | |||||
(U) Adjustments to Budget Years Since FY 1997 PB | 12,315 | 10,480 | |||
(U) FY 1998/1999 Biennial Budget | 0* | 0* | 12,267 | 10,421 | TBD |
(U) Change Summary Explanation:
Funding: * FY96 and FY97: Funding is programmed in PEs 0604321F, 0207431F, and 0305158F.
** FY98 and FY99: Funds were previously programmed in PEs 0604321F, 0207431F, and 0305158. They have been consolidated for clarity and reporting efficiency.
Schedule: Not Applicable
Technical: Not Applicable
(U) C. Other Program Funding Summary ($ in Thousands)
FY 1996 | FY 1997 | FY 1998 | FY 1999 | FY 2000 | FY 2001 | FY 2002 | FY 2003 | To
Complete |
Total
Cost |
(U) RDT&E, PE 0207431F, CAIS | 0 | 7,385 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 7,385 |
(U) RDT&E, PE 0305158F, Const Source | 1,989 | 1,954 | 0 | 0 | 0 | 0 | 0 | 0 | Cont | TBD |
(U) RDT&E, PE 0604321F, CIS-EMD | 3,619 | 2,791 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | TBD |
(U) Other Procurement, PE 0207414F | 9,114 | 9,705 | 15,252 | 13,173 | 18,730 | 14,631 | 12,077 | 12,125 | Cont | TBD |
(U) Other Procurement, PE 0207431F | 3,597 | 4,293 | 5,487 | 4,886 | 6,666 | 5,189 | 4,813 | 4,829 | Cont | TBD |
(U) Other Procurement, PE 0305158F | 968 | 1,951 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 2,919 |
(U) O&M, PE 0207431, CAIS | 10,826 | 3,479 | 3,330 | 3,353 | 4,326 | 5,371 | 5,488 | 5,615 | Cont | TBD |
(U) D. Schedule Profile
FY 1996 | FY 1997 | FY 1998 | FY 1999 |
1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 | |
(U) CIS 1.2 Release | X | |||||||||||||||
(U) TBMCS Contract Awarded | X | |||||||||||||||
(U) TBMCS V1.0 Preliminary Design Review (PDR) | X | |||||||||||||||
(U) TBMCS V1.0 In Plant Test | X | |||||||||||||||
(U) TBMCS V1.0 Release | X | |||||||||||||||
(U) TBMCS V2.0 PDR | X |
(U) A. Project Cost Breakdown ($ in Thousands)
FY 1996 | FY 1997 | FY 1998 | FY 1999 | |
(U) Software Development | 11,067 | 9,414 | ||
(U) Engineering Support | 1,200 | 1,085 | ||
(U) Total | 12,267 | 10,499 |
(U) B. Budget Acquisition History and Planning Information ($ in Thousands)
Performing Organizations:
Contractor or Government Performing Activity | Contract Method/Type or Funding Vehicle | Award or Obligation Date | Performing Activity EAC |
Project
Office
EAC |
Total
Prior to FY 1996 |
Budget
FY 1996 |
Budget
FY 1997 |
Budget
FY 1998 |
Budget
FY 1999 |
Total
Program |
Product Development Organizations |
Lockheed Martin
Cmd & Ctrl
Systems and
various others
F19628-95-C0143 |
SS/CPAF | Oct 95 | TBD | TBD | 0 | 0 | 0 | 11,067 | 9,414 | TBD |
Support and Management Organizations |
TEMS | Ongoing | Various | 374 | 374 | TBD | |||||
MITRE | Ongoing | 632 | 541 | TBD |
Test and Evaluation Organizations |
Test Support | Ongoing | 194 | 170 | TBD |
Government Furnished Property: Not Applicable
Subtotal Product Development | 11,067 | 9,414 | TBD | |||
Subtotal Support and Management | 1,006 | 915 | TBD | |||
Subtotal Test and Evaluation | 194 | 170 | TBD | |||
Total Project | 12,267 | 10,499 | TBD |