TUAV Schedule
ORD Approval
DAB/Army MSI
Proposal/Fly-Off
MSII
EMD
Deliver
Training
IOTE
MS III & FUE
Production Award
FOUO - Predecisional
Competition
FY99
FY00
FY01
Continued Development
Test Units
TRNG
IOTE
10-12 mo/Lead Time
LRIP or Full Rate
Critical Dates:
DAB 11 Mar 99 Begin Fly-Off 9 Jul 99
Draft RFP 12 Mar 99 Complete Evaluation 14 Sep 99
RFP 31 Mar 99 MSII 23 Sep 99
Downselect 31 May 99 EMD Award 24 Sep 99