Alternate Process
MS II
- Convene MS II in NOV 99
- Provide Required MS Documentation and Overview of 4 SCD Contractors
- Obtain Approval for Award of Contract-Due back 90-120 days After Award Answering Remaining MS II Exit Criteria
MS II Follow-Up IPR
- Convene MS II Follow-On Meeting (IPR) NLT 90-120 Days After Contract Award
- Complete OPTEC Evaluation from SCD
- Focus on Contractual and Programmatic Efforts Required Prior to OTRR and IOT&E and Exit Criteria for MS III