


Table of Contents
|  |

National Performance Review
Report on Reinventing the Department of Defense September 1996

ARMY CORPS OF ENGINEERS
The Army Corps of Engineers New York District moved boldly to
cut red tape should a barrier island protecting the Long Island
shore be threatened with an imminent breach. The procedure, embodied
in a novel Breach Contingency Plan (BCP), slashes Corps reaction
time from a traditional six -12 month period to just 10 days.
And, while sealing barrier island breaches faster, the procedure
also does so more cheaply.
Fundamental to the system is a streamlined procedure for delegating
responsibility and authority to the non-federal sponsor (New York
State) and the New York Engineer District, plus an accelerated
contracting process.
In the past, the Corps could act only if asked by the governor
of New York after a declaration of emergency signified that all
state resources were exhausted. In response, the Corps would
prepare a report justifying federal participation in emergency
work. This report went to Corps Headquarters in Washington for
review. If approved, the Corps would prepare plans and specifications
and negotiate a Project Cooperation Agreement (PCA) with the state.
Following approval of the PCA, a construction contract would
be advertised and awarded. In a typical case, Pikes Beach in Westhampton,
NY after the 1992 Northeaster, it took six months to approve the
report and award a contract, and five more months to effect final
closure of the breach. In the interim, the breach -- initially
50 feet wide and six inches deep, had grown to 3000 feet wide
and 20 feet deep.
Under the BCP, the Corps carries out an upfront analysis of potential
breach locations, economic evaluation and a complete environmental
assessment. Divided into three phases, the BCP procedure relies
on the Corps preparing a fact sheet which declares the existence
of an emergency and provides site-specific details, including
condition, location and proposed solution. The process is advanced
by an accelerated contracting process which, in an emergency,
can be implemented in a week. A PCA would delegate the district
to act with the State in funding the emergency action.
Since the inception of the BCP, several storms have hit Long Island.
The Federal and state governments, after extensive coordination,
are now comfortable with their roles. The state accepts that
under normal overwash conditions, it will assume responsibility
to maintain integrity of the barrier island. The New York District
is prepared to act swiftly when required to minimize cost of emergency
action.
- Albuquerque Contracting Concept Empowers Corps Employees.
The Albuquerque District of the U.S. Army Corps of Engineers,
through innovation and a willingness to explore new ideas, developed
a Design/Build Request for Proposal (RFP) package, directly supporting
both the goals of the National Performance Review and Executive
Order 12931 (Federal Procurement Reform). The process focused
on empowering employees to make decisions at the lowest possible
level, resulting in the District working more efficiently, better
serving the customer and reducing customer costs. The District
successfully implemented this idea at Whiteman Air Force Base,
MO, and Kirtland Air Force Base, NM, resulting in the delivery
of a quality product in 15% of the normal development time with
a 30% reduction in cost.
Development of a Family Housing RFP at Whiteman AFB required that
District personnel make decisions on the spot to ensure a well
defined scope of work within a short amount of time. This new
procedure allowed the District to incorporate the customer's needs
and requirements immediately, as well as obtain information and
resolve issues in a short time frame. To meet the short suspense,
the team outsourced administrative support. The whole process
for Whiteman used a "back to basics" concept employing
a minimum number of personnel and equipment required to perform
the tasks.
Development of the RFP for a utility infrastructure improvement
project at Kirtland AFB confirmed the viability and the effectiveness
of the process used at Whiteman AFB. Through a team effort between
Little Rock and Albuquerque Districts, a water system RFP package
was developed, with both a reduction in the time and money required
to produce a quality product.
Through the initiatives of Federal employees and the cooperation
of our customers, the Albuquerque District has expanded its pallet
of services.
- Leasing Of Lakeside Recreation Suite Allows Corps To
Concentrate On "Basics" In Serving Customers.
The Albuquerque District of the United States Army Corps of Engineers,
in a major move to improve the quality of the recreation services
at Conchas Lake, NM, leased the lake's southside area for operation
and management to Mesa Technical College (Mesa Tech) in Tucumcari,
NM. This agreement will provide better service to the public,
help the District concentrate more assets on serving these customers
(back to basics), and create a unique and beneficial partnership
between the Corps of Engineers and a public educator.
This unprecedented cooperative agreement will have positive results
for the regional public, Mesa Tech faculty and students, and the
Corps of Engineers. The partnership will expand the curriculum
for Mesa Tech students and enhance recreation services for some
half million visitors to Conchas each year. It should also boost
the local economy and service to the public.
The 25-year lease was signed in February 1996 and the college
plans to have facilities open by Memorial Day. The college will
invest in repairing and upgrading the resort area, which is valued
at $3.5 million. The school will focus on maintenance, administration,
marketing, and support staff requirements to get the area open
and running for the upcoming peak recreational season and into
the future. In turn, the Corps of Engineers will provide expertise
in recreation resources and assist the college in expanding its
curriculum to include biology, engineering services, resort management,
business administration, heavy equipment operation and a host
of other career building opportunities for students.
The college will be able to use several of its established educational
programs, such as diesel and automotive technology, to repair
and maintain vehicles and equipment. Any profits earned by the
college during the first five years of operating the southside
resort area will be recycled back into the area for further improvements.
The resort area Mesa Technical College will operate includes a
lodge, restaurant, golf course with pro shop, convenience store,
marina, storage facility, and campsites. The recreation area
has been largely closed down for the past year due to the lack
of a concessionaire. This arrangement will now re-open these
facilities, helping to provide quality recreation facilities in
a family oriented setting
- Baltimore Wetland Regulators Streamline Permit Process.
Under Section 404 of the Clean Water Act, the U.S. Army Corps
of Engineers has authority over dredging and filling of all "waters
of the United States," including wetlands. Over the past
two years, the Corps Baltimore District has implemented several
improvements in customer service. Among these improvements are
the State Programmatic General Permits signed with the states
of Maryland and Pennsylvania. In effect, these permits say that
work covered by Section 404 in these states, which have strong
wetland protection programs, is approved by the Corps once it
is approved by state officials in their permit process. This effort
has fostered state and federal partnerships while streamlining
the regulatory process.
In addition, the Baltimore District has opened new lines of communication
with its regulatory program customers. These include the publishing
of a quarterly news bulletin and increasing the service capabilities
of our field offices. These improvements meet the Administration's
Reinventing Regulation goal of the National Performance Review.
- Corps District, County Government Join Forces To Cut
Red Tape. The U.S. Army Corps of Engineers Chicago District
has reduced duplication of effort and cut red tape for property
owners and permit applicants by issuing a general permit work
done in DuPage County, Illinois under local water and wetland
protection ordinances.
Under Section 404 of the Clean Water Act, all dredging and fill
work in the "waters of the United States"--including
wetlands, requires a permit from the Corps of Engineers. The
general permit authorizes the government of DuPage County, Illinois,
to review projects regulated under Section 404, excluding only
those projects sponsored by county-level agencies, such as the
DuPage County Department of Transportation, the Department of
Environmental Concerns, or the DuPage County Forest Preserve.
DuPage County's regulatory authority derives from the DuPage County
Stormwater and Floodplain ordinance, originally approved by the
county government in 1990. The Ordinance is a comprehensive document
covering all water-related issues, including wetlands.
The general permit will reduce the duplication of regulatory review
at different levels of government while adequately protecting
the aquatic resources of DuPage County. The current Department
of the Army permit program and the DuPage County Ordinance both
regulate activities in wetland areas, and the review of both agencies
is essentially the same. The general permit will lead to increased
efficiency of operations by reducing the time Chicago District
staff spend reviewing projects in DuPage County.
The general permit will empower DuPage County to make decisions
involving the wetland resources of the county, and to better integrate
wetland issues into other water-related issues such as flood control,
wildlife habitat, wildlife habitat, riparian issues and water
quality.
- Fort Worth District Partnering Builds New Brooke Army
Medical Center. The new Brooke Army Medical Center (BAMC)
an eight-story teaching hospital, a modern, state-of-the-art facility
encompassing 1.5 million square feet (six times the size of the
old main hospital), 450 beds and clinical and logistical support,
was completed ahead of schedule and within budget through teamwork
and partnering between the Army Corps of Engineers Fort Worth,
TX, District, the Army Medical Command, and contractors. The
new hospital replaces the original BAMC built in 1936, which over
the years had expanded to occupy over 50 separate buildings and
clinics. Many services had to be duplicated among these sites,
but are consolidated in the new hospital. In addition, there
is a new research building housing the U.S. Army Institute of
Surgical Research and the Department of Clinical Investigations.
The contract documents included over 10,000 sheets of drawings
and 5,400 pages of specifications with reference to hundreds of
industry standards, codes, and military and federal specifications.
The design review alone was an immense undertaking. Teams of
Architect-Engineer firm representatives, Corps specialists, and
BAMC's Health Facilities Planning Agency staff met for days to
solve the challenges faced in designing such a complex facility.
The major contributing factor to the success of the new BAMC has
been partnering. Partnering is a challenge in the construction
industry where parties sometimes have conflicting objectives.
At times, these conflicts become adversarial. With that in mind,
the Fort Worth District commander at the time, Colonel John Mills,
committed everyone on the project up front to partnering.
Partnering contributed to many initiatives. One of those created
the Equal Employment Opportunity/Affirmative Oversight Committee
for the project. With local community organizations, labor unions,
the Corps' Resident Office and the contractor, in cooperation
with the Department of Labor, this committee initiated educational
and on-the-job training programs, information exchange and an
active involvement of labor unions. This labor involvement by
all parties resulted in the very first Corps contractor to receive
the U.S. Department of Labor's "Exemplary Voluntary Efforts
Award."
On a project of this scope, it is common practice to employ the
services of the designer to address issues that arise during construction.
An on-site representative from the designing Architect-Engineer
firm stayed on-site at the resident office to assist in addressing
issues. The fort Worth District Engineering Division also provided
a full-time representative to the project, who administered the
A-E contract and acted as liaison to the district office for other
types of support. The grand opening of new BAMC was held March
14, 1996.
- Huntington, WV Corps District Saves $ Millions On Dam
Design. In 1995, the Huntington, WV District of the U.S.
Army Corps of Engineers was successful in a variety of cost and
time saving initiatives that are customer-focused and do not downgrade
the products or services provide to District customers.
The Design Branch of Engineering Division applied innovative design
approaches the Marmet Lock Replacement Project, on the Kanawha
River near Charleston, WV. The proposed changes in design will
reduce the $243 million project cost by an estimated $50 million.
In addition to saving cost on the Marmet Project, the concepts
were applied to the District's Winfield Lock Replacement Project
currently under construction farther downstream on the Kanawha.
This will result in a $4 million cost savings.
The Marmet design changes have been exported to other Corps of
Engineers districts. The Detroit District anticipates that they
will be able to use design ideas acquired from Huntington and
Louisville Districts to reduce the cost of their anticipated Soo
Lock Project by $200 million.
Adopted Marmet design changes include: 1) increased sheet pile
driving distance to limit excavation, 2) a 1,080 foot reduction
in the guide wall length, 3) reuse of sheet piling from temporary
cofferdam structures, 4) elimination of the emergency lock closure
capability, 5) replacement of beams in the guard wall with flow
skirts, 6) reductions in the scope of helper boat assistance required
during construction, 7) use of acquired instructions as temporary
operation facilities during construction, and 8) reductions in
the number of mooring facilities provided and substitution of
floating buoys for the mooring cells. Proposed changes include
1) a bottom filling and emptying system that allows the lock walls
to be built of roller-compacted concrete, 2) an anchored master-pile
upstream guidewall instead of concrete-filled cells, and 3) post-tensioned
box beams for the guard walls allowing for longer spans and requiring
half as many concrete-filled cells.
These innovative design changes were featured in Engineering
News-Record, and that publication named John Clarkson, chief
of Huntington District's Structural Section, as one of its top
25 newsmakers of the year.
Elsewhere in Huntington District, Major Roger Wilson, Planning
Division team leader for a study of a $50 million flood reduction
project in Martin County, KY, recommended changes that reduced
a scheduled 38 month study by six months and reduced the study
cost of $1.8 million by $600,000. The streamlined study approaches
recommended by the planning team have been adopted in the district
for future studies and have been shared with other Corps districts.
- Energy Savings Performance Contracts (ESPC) Save Army
$28 Million through Partnering with Contractors. As
the Army's Technical Center of Expertise for ESPC projects, the
U.S. Army Engineering and Support Center, Huntsville, AL, has
developed the Energy Savings Performance Contract (ESPC). An
ESPC is a long-term contract - up to 25 years - designed to reduce
Department of the Army energy expenditures.
Under an ESPC, the contractor provides the design, capital investment,
construction, and operation and maintenance of energy-efficient
equipment, products, or systems. The contractor's earnings come
from the resulting energy savings, which are shared with the Government.
The total savings over the life of five ESPC's awarded by Huntsville
is $104,453,370, with savings to the Army of $28,198,907.
Huntsville's ESPC is also a time saver, a feature that makes customers
happy. The Center streamlined the ESPC process last year, reducing
the contract development and award time from 18 to 8 months.
To achieve that reduction, Huntsville assigned a senior engineer
as the single point-of-contact from the start to finish of each
ESPC project.
Huntsville Center also partnered with the contracting community
to find innovative ways to reduce the contractor's cost of doing
business. "While staying within legal guidelines, we just
did what seemed to make sense," says Bobby Starling, program
manager at Huntsville Center. As a result of the partnering, ESPC
contractors now submit a resume instead of an expensive bid package,
a change that not only saves contractors money but has resulted
in more bids and more competition. Huntsville Center plans to
reduce contract development costs even more by broadening the
scope of ESPC's so that multiple installations can benefit from
the savings a single contract generates.
- Huntsville Center Saves Money on Energy Program Operation
and Maintenance Contracts. When the Army's Forces
Command needed an efficient contracting method for energy-related
operation and maintenance (O&M) projects, U.S. Army Engineering
and Support Center, Huntsville responded by developing an innovative
O&M contract that saves time and money. Since September 1992,
this multi-year contract has saved FORSCOM installations 3 to
4 percent of the cost of construction over traditional contracting
methods. Designed for quick response time, this centrally managed
contract cuts red tape by taking full advantage of more efficient
contracting procedures and by awarding the whole project at once
instead of bit-by-bit. Under this method, the customer provides
a short scope of work and contractors respond with a "work
plan" of necessary requirements rather than a full-blown
design. The result is that contracts are awarded for energy-related
O&M projects in weeks instead of months.
Another source of efficiency and customer focus is found in Huntsville's
execution of the contract. Engineers at Huntsville Center are
empowered to provide customers with single point-of-contact service
for each project from conception to completion of construction.
Such an arrangement leads to clear and immediate communication
among the installation, the contractor, and Huntsville. Problems
are solved within hours, not days or weeks or months.
Through this unique contract, a true partnership has been formed
between the customer at the installation, the contractor, and
Huntsville Center. Because of its success, this contract is being
expanded so that even more installations can reap the benefits.
- Center Finds Empowered Employee Teams Are Key To Customer
Satisfaction. Looking for ways to improve customer
satisfaction and deliver services more efficiently, the U.S. Army
Engineering and Support Center, Huntsville, AL, is turning to
self-managed teams for some programs.
Why teams? "The things I've seen done well in organizations
tended to be by small groups of folks, with each person bringing
some needed skill to the effort," says the Center's commander,
Colonel Walter J. Cunningham.
Huntsville formed its first team around its Ordnance and Explosives
Program, a complex, long-term task requiring multiple skills,
judgments, and experiences. Instead of pulling employees from
various in-house departments to perform ordnance functions on
a part-time basis, Huntsville created an Ordnance and Explosives
Team of employees fully dedicated to the work. The main purpose
of the switch is to focus on customer needs by reducing red tape
and traditional corporate barriers that create inefficiency. "Energy
is wasted moving across those barriers," Cunningham explains.
What are some energy savers generated by teams? Teams streamline
communications because the hierarchical structure is flattened.
Teams transfer responsibility to the lowest possible level, reducing
resource-consuming approval chains. Teams, because they are self-directed,
reduce the number of middle managers needed. For example, Huntsville's
Ordnance Team has over sixty employees organized into smaller
"sub-teams," all under one director. Teaming requires
fewer supervisors, since work performance is also evaluated by
co-workers and customers. Finally, teaming taps latent creativity.
As one Huntsville team member put it, "The transition to
teams has released tremendous energy. Teaming not only allows
people to contribute; it requires them to."
- Cutting Red Tape on Army Medical Facilities Contracts.
Traditionally, operation and maintenance (O&M) and new construction
for Army medical facilities have been performed through the typical
architect-engineer (A-E) and major construction process, complete
with full design and specifications and a construction contract.
To streamline the medical contract award process for O&M
work, the U. S. Army Engineering and Support Center, Huntsville,
AL, developed a remediation contract for their customers in the
U. S. Army Medical Command.
In the vast majority of cases, the contractor need only provide
a work plan instead of a full design, a process similar to what
the commercial sector uses. Under this program, the Huntsville
Center has awarded five contracts, with delivery orders that are
either time and materials or firm fixed price. The, achieving
savings and improved service to the customer in the following
ways:
- For urgent work, a delivery order contract can be awarded to
a contractors on a time and
material basis, enabling the contractor to begin work on the project
right away. In many cases, the contractor is already performing
other work on the installation and can begin work as soon as the
delivery order is received.
- For work that is not an emergency, most delivery order contracts
can be negotiated and
awarded on a firm fixed price basis within a short period of time,
reducing project and contract management costs.
- Simple sketches can generally be used in the work plan, eliminating
the time and expense
of preparing engineering drawings.
- Center Employees Receive Peer, Subordinate, and Customer
Performance Ratings. The U.S. Army Engineering
and Support Center, Huntsville is currently implementing an employee
appraisal program in which employees are rated by their supervisors,
co-workers, subordinates, and internal customers. The A360 Performance
Management Review meets two goals set forth under the National
Performance Review putting customers first and empowering employees.
The reference to A360 means that the evaluation reflects input
from the full circle of the organization, not just from the supervisors.
Under A360, each employee receives input on 30 rating elements
from 16 people. The elements are organized into five categories:
organizational vision, team participation, integrity and dignity,
job knowledge and skills, and continuous improvement. The elements
are uniform for each supervisory and nonsupervisory employee.
Ratings are provided anonymously by each rater, calculated through
an automated program, and then returned to the rated employee
as a composite score for each element on a scale from 2 to 10.
Employees, together with their supervisors, then develop a plan
for improving weak areas of performance.
A360 has many benefits for employees. First, employees are empowered
through broader participation in the appraisal, since ratings
from co-workers and subordinates have equal weight with supervisors
ratings. Also, the A360 system more clearly ties organizational
success to awards. Furthermore, because of anonymous feedback
from a variety of people, employees have more objective information
that they can use to improve their performance. Finally, A360
promotes teamwork, since employees are evaluated directly by the
people they work with.
A360 also benefits customers. First, customers are part of the
rating process. Their rating input plus the opportunity to provide
individual comments on each rated employee gives voice to a customer
service focus. Moreover, A360 rewards employees for customer
service excellence.
To check for bias, Huntsville first tested the system on 45 senior-level
managers. Results showed that four ratees would have received
higher overall ratings under the A360 system than under the traditional
appraisal system, and five would have received lower overall ratings.
In a second test of work-level employees, twelve would have received
higher overall ratings under A360 and four would have received
lower overall ratings. A statistical analysis of the ratings
from both tests indicates no apparent patterns of bias based on
age or sex.
- Developing New Technology: Geographic Information System
Helps Army find Unexploded Ordnance. The U.S.
Army Engineering and Support Center, Huntsville is faced with
the complex task of identifying unexploded ordnance (UXO). The
information available to help the center in this task is confusing
deluge of geophysical data gathered with the remote-sensing devices
used to search for buried UXO. Although every data blip indicating
the possibility of ordnance could be separately investigated in
the field, such an approach would be very expensive for the customer
- and the taxpayer.
To look for solutions, Huntsville Center empowered a small group
of working-level employees who assembled a cross-functional government-contractor
team. That team's solution is built on Geographic Information
System (GIS) computer software used to manage data such as mapping
features, property ownership, and natural resources. To enhance
GIS capabilities, the Huntsville team developed the ordnance GIS
Knowledge Base module, a software tool that actually generates
new data from the remote-sensing data and data from previous ordnance
removals (such as ground truth). Those new data include an estimate
of the depth and size of buried objects and whether the objects
are likely to be UXO or just junk. The goal is to zero in on and
excavate only the hazardous UXO and leave the benign items for
other, more cost effective cleanup methods.
The Knowledge Base is a working product that outperforms other
UXO discrimination techniques developed by either industry or
traditional government research and development organizations.
It is a team solution that saves the customers' time and money
while reducing the risk of exposing people to hazardous UXO.
- Empowered Employees Save $1,000,000 at Power Plant.
The Hammer Award, a framed $6 hammer wrapped in a red, white
and blue ribbon, is Vice President Al Gore's answer to the $600
hammer that symbolized government bloat of the past. The Greater
Kansas City Federal Executive Board nominated the Army Corps of
Engineers Kansas City District for the award for work done on
the turbines at the Harry S. Truman Dam powerhouse in Missouri.
The district's efforts resulted in a cost savings of more than
$1 million.
Kansas City District staff members joined in a Process Action
Team to identify and fix repair problems with powerhouse turbines
that had existed, due to the inability of a contractor to deal
with the problems, since 1985. Empowering district employees
to identify and fix the repair problems resulted in three of the
six units placed back on line and the promise to have all six
turbines repaired by 1997, at a cost savings of $1,144,780.
- L.A. Interagency Support Cuts Red Tape, Protects against
Quakes. For several years, the U.S. Geological Survey
has been using the Army Corps of Engineers Los Angeles District's
microwave radio system to transmit seismic data from remote locations.
The USGS has also developed a system known as CUBE (CalTech USGS
Broadcast of Earthquakes) that uses this data to pinpoint the
epicenter, magnitude, and other data for earthquakes in Southern
California. Within a matter of minutes, the CUBE system disseminates
this information by pager to key personnel and then displays the
information on maps and maintains a data base of any earthquake
recorded. USGS originally asked the Corps of Engineers to pay
$25,000 per year for access to CUBE. The agreement, however,
will allow the District access to the CUBE system at no cost in
return for continued use of the District's microwave radio system--eliminating
the need to process interagency payments.
- Corps "Continuing Authorities Projects" Cut
Red Tape. Although the Corps of Engineers is known for
major engineering feats, it also takes care of "the little
things" through its Continuing Authorities projects.
Continuing Authorities projects, unlike most civil works projects,
do not require congressional approval. They use less than $5
million of federal funds for each project.
Several different types of projects fall under the Continuing
Authorities Program. These include emergency repairs to streambanks
and shorelines, small beach erosion control projects, Section
107 Small Navigation Projects, projects to mitigate shore damage
at federal navigation projects, small flood control projects and
snagging and clearing for flood control.
One example of what the program can accomplish is a Section 14
project in Judsonia, a small town located in north central Arkansas.
"Judsonia is a great example of cooperation by the city,
state and Corps," said Julia Smethurst of the Corps of Engineers
Little Rock District. "The sewage lagoon levee was in danger
of collapsing into the river, and the city did not have the money
for its share of the project costs. The next flood event on the
Little Red River had the potential for dumping sewage into the
river."
The State Office of Emergency Services paid the city's share because
of the emergency situation.
"This project involved lots of teamwork to speed up the process
of getting land acquisition, contracting and construction underway,"
Smethurst said. She commended the district's Real Estate, Construction-Operations,
Contracting, and Engineering Divisions, and Office of Counsel,
Finance and Administration for "jumping" to make it
happen. Another project involved a streambank on the Current
River that had eroded dangerously close to Arkansas Highway 211.
The Corps awarded the construction contract in July 1994 and the
$333,000 project was completed the following October. Costs were
shared with the Arkansas State Highway and Transportation Department,
said Chris Hicklin, chief of Little Rock's Project Reports Section.
Flood Control, or "Section 205" projects are another
aspect of Continuing Authorities. Brenda Puloma, a Little Rock
Planning Division engineer, managed the Crooked Creek Project.
"Crooked Creek runs through downtown Harrison," Puloma
said. "The purpose of the project was to clear and grubb
the creek to allow water to pass quickly and prevent flooding."
Construction on the $1.1 million project started in March 1994
and is slated to be complete this month depending on the weather,
Puloma said
The construction supervision on this project was handled through
the Mountain Home Resident Office.
Puloma said the benefit to cost ratio for annual flood reduction
is 4-to-1, with an average annual flood reduction of $919,000.
The city of Harrison decided to improve Minnie Harris Park with
a manmade fishing area made possible by a fishery mitigation weir
installed by the Corps of Engineers.
"The city has been working with the Corps on and off for
the past 15 years to come up with the right formula to make flood
control and recreation a reality," said Frank Gelinas, engineer
for the city of Harrison. He believes the quality of the Corp's
plans and designs enabled the city to pass a one-cent sales tax
to fund the park.
"It has been an absolute pleasure working with the project
manager, Brenda Puloma, rather than several people," Gelinas
said." The Resident Engineer, Jack , and other engineers
from Mountain Home were super to work with. The Corps people
were very service oriented and the city is appreciative of the
quality of work that was done."
Continuing Authorities Projects are popular with customers because
the cost sharing and cooperation enable small cities to make improvements
they could not otherwise afford.
Not content to rest on their laurels, the members of the Continuing
Authorities team are working to streamline the process.
- Empowered Employees Save Dollars In Dumpsters.
Changing "dumpsters to dollars" was the goal of a Task
Process Action Team in the Army Corps of Engineers' Little Rock
District, and it looks like they may have done just that.
The Task PAT was formed in November 1993, to determine the cause
of increasing solid and liquid waste removal costs in parks at
the Beaver and Table Rock projects of the Upper White River.
A task PAT is a cross-functional task team formed to study a specific
problem that is assigned to them. PAT members represent a cross-section
of people from the different projects and functions.
"Solid and liquid waste removal is such a large issue,"
said George Ann Tabor, a ranger at the Beaver Project Office.
"We decided to focus first on the solid waste removal, because
we had more information readily available on that issue from Table
Rock."
Solid waste removal at Table Rock and Beaver parks is handled
through two separate contracts. At Beaver Lake, the costs of
solid waste removal were continuing to increase, while Table Rock's
prices dropped some when the new contract was started.
The team's target was to reduce the cost of solid waste removal
while maintaining the same level of customer service.
In the waste removal contracts, the Corps of Engineers was charged
for each dumpster that a contractor picked up, whether it is full
or not. Inspectors randomly checked 70 percent of the dumpsters
during the April to September 1994 contract period and found most
of them only partially full.
To solve the problem, the team developed a checklist that would
help determine the size, number and location of dumpsters in relation
to the layout of the parks as well as their pick-up schedule.
Under each heading on the checklist, the team identified several
issues. When deciding how many dumpsters should be in a park,
they suggested that project managers take into consideration the
amount of park visitation, the physical layout of the park, the
size of the park and the number of campers.
The checklist can easily be applied to any park. Using the list
helps insure that all aspects of the dumpsters, from size to location,
fit the needs the park.
"Instead of having eight locations with some small and some
large dumpsters, having them picked up too often and having them
located where it is inconvenient to the campers, we will be able
to decrease the number of dumpsters, have them centrally located
and emptied only once a week," Greg Oller, team leader, said.
"That way we can almost insure that we will be getting our
money's worth by picking up full dumpsters," Oller said.
The team's checklist was included in contracts for the 1995 recreation
season. It is estimated that the changes saved the government
about $40,000. "When you see that this team cut our spending
from about $70,000 to just less than $30,000, I think it's pretty
obvious that we had not been managing our resources well,"
said the manager of one of the parks.
The team also determined that park visitors needed to be educated
about the location of the dumpsters through park maps, messages
on the Automated User Permit System and park attendants.
It took the team less than three months to reach a solution to
their assigned problem.
"We found the TQM process to be very effective," Team
Facilitator Steve Franco said. "Once you are familiar with
the process, it's not hard. All you do is follow the steps. Step
one of the process, choosing the problem to study, was done for
us. We just had to polish it up, and then we zoomed into step
two."
The next step for the PAT was to study the liquid waste removal
process. At Table Rock Lake, contracted pumping costs had risen
from $21,240 in 1991 to $36,180 in 1994, a 70 percent increase
in four years. At Beaver Lake, the cost more than doubled from
$33,164 to $71,558 during the same period
The target for improvement called for a 40 percent reduction in
cost of liquid waste removal from the parks. After determining
the root causes--the scheduled number of pumpings and the increase
in fees at area waste disposal plants--the team recommended installation
of subsurface septic systems at all restroom facilities and trailer
dump stations at the lakes. This included the installation of
waterborne facilities which are currently vault systems. They
also proposed to eliminate facilities at several locations, and
modifying the contract to eliminate scheduled pickups and go to
an "as needed basis" at Beaver Lake.
Cost of implementing the recommendations is estimated at $462,000.
Based on a projected 40-year life expectancy of the installation,
it would take about six years to recoup the initial installation
costs, but savings over the following 34 years would be dramatic.
- Maintenance Task Force Uncovers Morale Problems.
Employees at the U.S. Army Corps of Engineers Little Rock District,
formed into a process action team to resolve maintenance problems
at parks managed by the district, uncovered and resolved a potentially
explosive morale problem as well.
At the root of the problems was a reorganization of office functions
in December 1993 which moved the function of service contract
and facility maintenance from one branch to another. During 1994,
complaints of worsening conditions in the parks and slow response
times in correcting problems began to noticeably affect the parks'
paying campers and day users.
This in turn began creating friction between personnel in the
two branches. "Several heated arguments developed between
employees in the two branches," said Ken Buck, Pine Bluff
project manager. After reviewing limited park visitor survey
data, the team discovered that most complaints from park visitors
were generated by internal complaints from employees. A questionnaire
given to affected Corps employees identified three potential problems
areas -- reorganization, personal conflicts and reduced staffing.
These three areas represented 72 percent of the complaints received
for poor park appearance, slow response time and poor working
relationships.
The team first thought that it had no authority or ability to
make the needed changes in the areas of reorganization and reduced
staffing. However, Buck challenged to the team to come up with
valid organizational changes that would solve the manpower problems.
With this new empowerment, the team tackled the root cause of
the problem -- reassignment and loss of personnel and individual
personalities. With this positive approach, team members developed
countermeasures. To deal with reduced manpower, they called for
reassignment of maintenance functions to the Marine Terminal,
establishing a clear scope of responsibility, and cross-training
park rangers and civil engineering technicians in specification
writing for construction and operations and maintenance contract
administration.
Countermeasures for individual personality problems included improving
working relations through counseling, and improving supervisors'
employee management skills. "Since the recommended countermeasures
were implemented, there have been absolutely no complaints this
season, " Buck said."
The team estimated between $50,000 and $100,000 in first year
savings through the combining of jobs assignments, more efficient
maintenance operations, and the turn-in of two vehicles.
The intangible benefits include efficient team performance, improved
service to park facilities thereby reducing user complaints, and
a reduced number of supervisors per employee
- Army Engineer District Focuses On Empowered Employees.
Total Army Quality--the Army's version of the Total Quality Management
concept of empowering employees--has found a stronghold in three
project offices in the U.S. Army Corps of Engineers Little Rock
District. With the support of the project managers and the enthusiasm
of the employees, TAQ is becoming much more than just a management
philosophy.
TAQ is now in its third year in Little Rock District, and a large
number of project office employees at Pine Bluff, Table Rock and
Mountain Home have completed their training and are using the
principles to solve real problems.
"TAQ is a way to train people who are interested in improving
their work environment and to give them the tools and the freedom
to address the necessary situations," said Richard Groves,
Upper White River project manager. "This is the best money
I've ever spent as a manager."
With TAQ, offices use task Process Action Teams to study problems
assigned by management. This helps speed up the process, because
the teams don't have to spend valuable time finding something
to study. Task PATs are not only given a topic, but they also
are given a time frame to complete the study.
There have been four task PATs at the Upper White River Project
Office and one each at Mountain Home and Pine Bluff. All of the
involved project managers agree that TAQ is both applicable and
timely, especially in today's business climate of reorganization
and change. "Once employees have learned how to conduct
fact-based problem solving, they are able to think the process
through in their everyday decisions," said Ken Buck, Pine
Bluff project manager. "This will be a life saver with the
eventual downsizing of the Corps."
Jack Rintoul, project manager at Mountain Home, also employs TAQ
in everyday work. "What people are saying is that they want
an informed decision to be made. They want data to be gathered
and analyzed, they want facts presented," Rintoul said. "They
want to determine how much room for improvement there is, look
at costs versus benefits, and then decide what to do."
Groves has advice for other offices that are planning on beginning
the TAQ journey. He suggests that managers make an environment
that will encourage teams to accomplish their goals by giving
them enough time to meet and gather information. "If you
give TAQ a chance, it works, and works well," he said. "It
will allow you to accomplish things you don't have the manpower
or resources to do otherwise."
- Empowering Employees: Oil Trap Saves Government $26,000.
The Army Corps of Engineers Little Rock District's Suggestors
of the Year for 1994, Terry Nearn and Norman McIlravy, did not
set out to build a better mousetrap, but they did. Actually,
they helped build an oil trap that saved the government more than
$26,000.
The electrical transformers of the Norfork, AR, switchyard sit
on the bank of the Norfork River. In the event of a catastrophic
accident, such as an earthquake or lightning strike, oil from
the transformers could leak and contaminate the river. "If
the tank ruptured, it would dump thousands of gallons of transformer-insulating
oil into the river," Nearn said.
To prevent this potential hazard, the district submitted plans
to redesign the oil containment system at the switchyard. As
the two electricians reviewed the plans, however, they realized
that the work would be dangerous, expensive, complicated and time
consuming. "Because of the underground copper mat that grounds
all of the electrical machinery in the switchyard, the project
would have required hand excavation," McIlravy said.
The more the two men looked at the labor costs involved, the more
convinced they became that they could find a better way to transport
the oil.
Nearn and McIlravy submitted a suggestion to modify the existing
design to avoid hand excavation. The solution involved using
the existing cable tunnel for piping.
"Most of the money saved was in labor costs," McIlravy
said.
Both Nearn and McIlravy found the recognition for their idea more
rewarding than the money award that they also received. "Yes,
the monetary award is nice, but you cannot beat the recognition.
I am just happy to do anything to help the government save money,"
Nearn said.
In 1994, 71 ideas were submitted and approved in Little Rock District's
Ideas for Excellence Program. Those ideas have saved the District
$58,766 in tangible savings.
- Park Review Helps Corps District Reduce Costs, Provide
Service. The U.S. Army Corps of Engineers Little Rock
District has launched a park study that will help identify ways
to improve service in its parks as the federal work force continues
to be reduced.
The review process, which involves looking at economic and service
indicators for each park, was developed by a Total Army Quality
Process Action Team. The team began working in November with
a deadline of January to present their findings to the district's
Quality Council. "We discovered that in the past, we have
had a tendency to maintain the facilities that we have rather
than adjusting and developing facilities into what the public
wants and would use," explained a team member, who added
that, by improving facilities that are heavily used by the public
and revamping other facilities to meet the users' needs, the district
could maximize the cost effectiveness of its facilities while
increasing customer satisfaction.
The team developed a review process and scoring system that ranks
parks based on usage, service and efficiency. The process uses
statistics that can be found on the annual park usage report.
"After researching, we found that funding was not the primary
limiting factor of park operation and maintenance," the team
member said. "Comparisons such as cost per visitor hour
and cost per visitor show that some small parks that had been
viewed as under-utilized actually cost very little to operate
when compared to larger parks."
The team realized that comparing both the economics and the service
and efficiency of a park would give the reviewers a more accurate
picture of how the facilities are being used. Raters determine
the five year average visitation to each project's parks and rank
the parks. The park with the highest number of visitor hours
gets a score of 50, the lowest gets zero.
Next the cost per visitor hour is found by subtracting each park's
revenue from its operating costs and dividing the total by the
visitor hours. The parks are ranked. The least expensive park
gets a score of 50, the most expensive gets zero. A total score
of 100 points is possible. For parks scoring below 50, the team
recommends that the reviewers do a root cause analysis to determine
the cause of the low rating.
A park's low rankings could be caused by a number of reasons including
high maintenance costs, low revenue, remote location, and providing
services that are not used by the public or insufficient services
to meet users needs. After the cause of the problem is found,
the project office will recommend the best course of action to
correct it.
Potential solutions could include partnering opportunities with
community groups, cooperative agreements with businesses operating
on Corps property under lease agreements, relocating and consolidating
existing facilities and developing improved park management efforts.
The Little Rock process also involves the public through workshops
which give PAT members a chance to lay out challenges, study findings
and suggested solutions to the public and ask them to help find
a workable solution. It's like partnering with the public.
The park review process is currently being implemented. It is
expected to take seven months to review, rank and suggest changes
or improvements for the district's 205 parks. While the process
will take time to implement and begin seeing results, district
leadership supports the action. "I don't think there's another
district in the Corps that comes close to what we are doing,"
said District Engineer Colonel Scott Morris. "I'm glad to
see us applying business practices to our daily mission of supplying
quality recreation services to our customers."
- Value Engineers Save Air Force $1.1 Million By Focusing
On Customer Needs. The U.S. Army Corps of Engineers Little
Rock District helped save the Air Force more than $1 million by
performing a Value Engineering (VE) study on the C-130 Squadron
Operations/Aircraft Maintenance Unit Project at Little Rock Air
Force Base. The Army retained its role in construction at Air
Force bases when the Air Force became a separate service in 1947.
The study generated more than 20 cost-saving proposals. Ten proposals,
with a combined savings of $1.1 million, were immediately accepted
by the Air Force. By implementing the proposals, the Air Force
will see a return of more than 36 to 1 on their investment. Four
additional proposals are still under consideration. If approved
and implemented, they could save another $400,000. "The
advantage of doing the VE study early in the design process is
the minimal costs of implementing the team's recommendations because
of the small amount of design work that has been completed,"
said Mark Thompson of Little Rock District's Engineering Division.
"We also are able to recommend changes in basic project
strategies and decisions before commitments are made.
"The ability to influence cost constantly decreases as more
and more design and decisions are completed and locked in. Our
return on investment ratio for VE studies is much greater when
accomplished early in the design process." The Little Rock
AFB project consists of two
C-130 Squadron Operations Facilities of about 46,000 square feet
each. The facilities will provide space for flight crew training,
administration offices and the repair and storage of aircraft
parts and life-sustaining equipment. Also included in the project
is construction of a new Petroleum Operations Facility of about
6,000 square feet. Some of the proposals included re-siting the
Petroleum Operations Laboratory and refueling yard, reusing existing
pavement and changing parking configurations.
"This is one of very few VE studies the Air Force Command
has funded nationwide," said Jack Woolfolk, chief of Engineering
Division. "We hope the success of this study will serve
as a catapult to get the Air Force into the VE arena." Value
Engineering is a five-phase process using applied creativity to
generate proposals that satisfy user needs with a quality product
that is produced at the lowest life cycle cost. The information
phase of value engineering gives team members an understanding
of the project by defining its function. Then, during the speculation
or brainstorming phase, team members use creative thinking and
synergy to provide alternative design ideas.
"The brainstorming phase allows free-thinking and teamwork
to generate some excellent ideas" said Paris Embree of Little
Rock District's Engineering Division. The team generated more
than 40 proposals during this phase. In the analysis phase some
proposals are eliminated, and the remaining alternatives evaluated
and ranked. The development phase prepares recommendations and
defines all of the advantages and disadvantages of each. The
presentation phase is when the proposal is presented to the customers.
The presentation for the Little Rock AFB project was made September
25, 1995 at LRAFB and was attended by VE team members and Air
Force representatives.
"The presentation couldn't have gone any more perfectly,"
said Project Manager Jim Pfeifer. "The Air Force representatives
were excited about the potential of some of the proposals and
extended the meeting to allow time to go back over each individual
proposal. By the end of the meeting we had a decision on all
the major proposals."
Value engineering has been used in the Corps of Engineers for
several years, but it will become a bigger part of how it does
its job in the future. In today's business environment where customer
satisfaction and "working smarter, not harder" is being
stressed, VE will become an important tool that will help the
district as well as our customers.
- Corps Serves Contractor Customers With Cd-Rom Bid Documents.
The Army Corps of Engineers Louisville District has initiated
a procedure to distribute bid documents to potential bidders via
CD ROM rather than paper. The first bid document to be distributed
in this new format was in April 1995. This package realized a
savings of approximately $35,000 in printing and mailing. Since
October 1995 the District has issued several bid packages on CD
with text only. On March 18, 1996, the first bid package with
both plans and specifications on CD was issued. This procedure
when fully implemented has the potential of saving the District
approximately $800,000 a year.
- Customers Help Corps Of Engineers With Flood Control.
There is much talk these days about the value of cooperation.
But the Memphis District, U.S. Army Corps of Engineers, and community
leaders along the Mississippi River near Armorel, Arkansas, are
doing more than just talking about it.
Using what they call a "cooperating, non-traditional approach,"
the St. Francis Levee District, a local landowner and the Memphis
District are working together to solve a problem that has dogged
this area for over two decades.
The area first experienced problems during floods that devastated
the area in 1973. When the Mississippi River rose out of its
banks, high flood velocities began scouring huge holes out of
the river bank and washing away valuable farm land. Some of those
holes are now more than 60 feet deep, and over 80 acres of land
have been washed away. Left unchecked, the erosion could eventually
threaten the safety of the Mississippi River mainline levee.
Various piecemeal efforts had been tried, but nothing seemed to
be able to stop the river's onslaught. A big solution to a big
a problem was needed.
With these concerns in mind, levee district officials, J.C. Ellis
(the local landowner) and the Corps of Engineers sat down to develop
such a plan. Mr. Ellis volunteered to take another 80 acres of
land out of production, so the levee district could plant 16,000
cottonwood tree cuttings along the river and around the perimeters
of the scour holes. In addition to supplying most of the funds
for the cottonwood cuttings, the U.S. Army Corps of Engineers
also provided technical assistance and produced project plans.
As the 16-inch-high cuttings mature, they will form a screen
to help maintain the integrity of the bankline, protect the levee
and prevent more devastating scouring action during future floods.
Beyond the flood control and navigation benefits, the reforestation
will also provide edge and cover habitat, and food for wildlife.
When mature, the trees will enhance the environment by creating
diversity and providing a valuable stand of hardwoods for the
area. Jake Rice, assistance engineer for the St. Francis Levee
District, was impressed with how the project has come together.
"We sometimes have this picture of the government being
slow to respond to public needs. But in this case, the Corps
of Engineers, the levee district and the landowner worked together
quickly and efficiently to solve a serious problem. It's been
a WIN-WIN-WIN situation," he said.
- Craney Island Project Serves Human And Avian Customers.
Craney Island Dredged Material Area is a four square mile
manmade peninsula in Norfolk Harbor, VA, constructed in 1958 by
the U.S. Army Corps of Engineers to receive dredged material.
The Corps Norfolk District operates the facility which also serves
as home to the Piping Plover, an endangered species, least terns,
brown pelicans, osprey, and numerous others.
Dredging is vital to maintain navigation at port facilities nationwide.
Sites for dredged material placement are critical to the nation.
In Norfolk Harbor, Craney Island is the least costly, environmentally
acceptable site for dredged material placement in Hampton Roads
harbor. Craney Island is rapidly filling. Without Craney Island,
severe economic hardship would impact the region.
The immediate customers of Craney Island are 119 users (industries,
shipyards, marinas, shipping companies, railroads, cities, Port
Authority, Navy and other Federal agencies who place dredged material
at the site). Other beneficiaries include users of the Hampton
Roads harbor which is viable due to Craney Island. The regional
benefits are huge: Norfolk is a 362 year old port ranking third
in the nation in international trade. A large part of the local
economy exists because of the port which relies on an economically
viable dredging program.
Norfolk District employees have developed a set of vertical strip
drains (plastic strips surrounded by fabric) to increase Craney
Island's capacity. As a result, the actual direct cost savings
to customers of Craney Island will be nearly 1/2 billion dollars
over the next 30 years. Craney Island will insure the continued
viability of the Ports of Norfolk, Portsmouth, Chesapeake, Newport
News, and the largest naval complex in the world. A 1-1/2 million
dollar, effort of foundation investigation, brainstorming, design
effort, and pilot studies, resulted in a project to place strip
drains at the site. These drains will improve foundation conditions;
allow the site to be raised; and increase storage capacity by
millions of cubic yards.
This project is funded from the Energy and Water Development Appropriation
and the Harbor Maintenance Trust Fund; however, approximately
60% of the cost will be returned to the treasury through tolls
and fees charged to users of Craney Island.
- Value Engineering gets Virginia Projects Back to Basics.
Three projects in the Norfolk District of the U.S. Army Corps
of Engineers were among 12 Corps-wide in the Office of the Chief
of Engineers' (OCE) Value Engineering Report for Fiscal Year 1995.
A Barracks Renewal project at Fort Lee, VA, saved over $2.4 million
from the $18 million project as a result of value engineering.
The 26 proposals for savings which were accepted by the design
team included revising interior and exterior finishes, reconfiguring
room layouts, revising interior/exterior wall construction, simplifying
electrical distribution, reducing fixtures in rooms and revising
heating and air conditioning systems. The project is under construction.
Norfolk District's Value Engineering gave the family housing project
at Fort Monroe, VA, a savings of over $900,000 on the $12 million
project. The Value Engineer team for this project included a
historical expert who provided information on restoring the historical
buildings at the fort. Accepted proposals included repairing
windows instead of replacing them, reorienting bathrooms, performing
chemical stripping of paint on the job site, repairing wood columns
instead of replacing all columns, installing gas-fired boilers
instead of hot water boilers, providing electric meters in multiple
housing units, and making electrical improvements. The team's
plan was reviewed by the State Historic Preservation Office, which
has authority over the buildings' restoration.
The Radford Army Ammunition Plant Acid Wastewater Treatment System
was the third Norfolk District project cited in the report. Over
$12 million was saved on the $25 million project. The Value Engineer
team, including representatives from Radford, Hercules, Inc. and
Picatinny Arsenal, came up with a savings plan that included elimination
of some processing systems, reducing the size of process tanks,
eliminating one line from the waste water system which eliminates
the need for a sludge handling system, and revising the criteria
for tank construction.
Employees Rescue Cost Of Ship Repair
Through "Wet Dock". Through innovative project
management and the desire to find better ways to do the job, the
Army Corps of Engineers New Orleans District cut the annual cost
of overhauling the dredge WHEELER by almost $7 million over three
years.
Until 1992, the WHEELER, the Corps largest and most productive
hopper dredge, averaged $9 million in annual maintenance costs;
but New Orleans District team members took a closer look at the
contracting process and shaved off $4.5 million by deleting "foreseeable
costs," an add-on cost in the bid evaluation process. "That
was the first time that we know of where a master marine contract
for the Corps of Engineers did not include foreseeable costs for
a shipyard overhaul," said Jim Courville, chief of the district's
Marine Management Section.
Richard Baldini, Physical Support Branch chief, explained that
foreseeable costs penalized East Coast shipyards because of costs
in time and fuel needed to move the WHEELER, usually from the
Gulf to their drydock.
"Previously, Gulf Coast shipyards could inflate their prices
and still be lowest bidders because of lack of competition,"
he said. "By deleting the foreseeable costs, eastern shipyards
were able to successfully bid against Gulf Coast shipyards, increasing
competition and lowering costs."
Lower costs also prompted the district to wet dock the WHEELER
at New Orleans District this year and subcontract the work, netting
another $2.5- million savings. Subcontracting meant coordinating
21 contracts, along with ship and shop workers. "It took
tremendous effort on the part of the project managers and all
the team players to pull this off," said Jim. Effort and
fortuitous planning, he added.
Because the Coast Guard performed underwater inspection during
last year's annual maintenance, it was not required again this
year, giving the district the opportunity to wet dock the ship
at our new wharf. "We didn't have the facilities to do the
job last year," Jim said. "But the new wharf, built
with the WHEELER in mind, is equipped with electricity and space
for crane operations needed for this type of job."
Those features of the new wharf enabled the dredge to shut down
its service generators which supply electricity to the ship.
The service generators were overhauled, along with both propulsion
engines and the two dredging engines. Work also included repairs
to the valves, pumps, winches, hydraulic system, air conditioning
plant, and the switchboard and electrical generators, in addition
to annual servicing.
"We did what the shipyard's superintendent does," said
Richard, referring to the subcontracting. "And we did a
better job and did it on time."
Richard and Jim were both pleased with a hidden benefit of the
wet dock and subcontracting efforts--the WHEELER left the district
much cleaner than when it leaves the shipyard. "We experienced
a quantum leap in the clean-up of the ship," said Jim. "A
clean ship results in higher morale. The crew of the WHEELER
is proud of the ship. They're able to welcome guests aboard and
show off the plant."
The ship also underwent topside inspections by the Coast Guard,
dock trials, sea trials as it sailed down the Mississippi, and
test dredging once it reached Southwest Pass. There, the WHEELER
spends most of its time, keeping the lower Mississippi River navigable.
- Nashville Park Host Program Puts The Customer First.
In 1993, Congress authorized the U.S. Army Corps of Engineers
to charge day use fees at boat ramps and developed swimming beaches.
Under this same act, the requirement for the Corps to provide
free camping areas was dropped. Corps customer did not agree
with these changes, and expressed their disapproval by refusing
to pay the fees and by vandalizing Government property.
In the Corps Nashville District, a volunteer park host program
went a long way to defuse the situation. Volunteers at Lake Cumberland,
TN, instituted and monitored an honor pay system, provided security
and provided information to the public concerning the fee requirement.
The park host at Fishing Creek oversaw the day use area, which
included a boat ramp, beach and picnic area. This area is extremely
popular and receives many visitors throughout the year. Fishing
Creek had also had problems with rowdy visitor driving away the
family-oriented visitor. The park host program there reduced
undesirable day user incidents, making the area more desirable
for family groups utilizing the area.
By the end of the first year of the fee program, the Nashville
District office had received several positive comments from the
public. One Nashville District project was able to collect over
$10,000 in 1995, an increase of more that $4000.00 from the previous
year. The presence of the park hosts and their positive public
relations presence increased compliance with user fees from 50%
to 90% without warning citations being issued by project Park
Rangers.
Park hosts at Fall Creek, a previously free camping area with
ten campsites, operated the campground, accepted reservations,
sold ice and ensured that campers paid their fees at the honor
box. These volunteers worked from April 1 through October 31
and saved the Federal government $21,700 that otherwise would
have been required to hire a contractor park attendant. All park
hosts were provided a full hook-up campsite and a hat and shirt
patches to identify them as Corps Volunteers. They were asked
to provide a minimum of twenty hours per week. Through their
efforts, the public has enjoyed improved visits to Corps campgrounds
and day use areas with fewer problems, especially rowdyism.
- Corps Employees Streamline Study Process For Flood Control
Project. Planning a major engineering project is a complex
process, but the South River Study, in New Jersey's Raritan River
Basin, has been a success story for the Army Corps of Engineers
New York District. The District utilized the interdisciplinary
team approach to produce a quality report, on time and within
budget. Several factors that lead to this success included team
members from various parts of the District working together to
develop the alternatives to the flooding problem. Instead of
working separately and waiting for others to complete a segment
of work, team members worked concurrently. This resulted in:
- All team members being aware of each other's work and resolving
potential issues early.
- Elimination of the standard 30 day review period. All work
was reviewed concurrently.
Each team member's parent division had to trust that other divisions
knew how to use their product, thereby eliminating further reviews.
- The team leader was a first among equals, ensuring constant
communication between team
members.
Team members were empowered to make decisions within their technical
expertise, and share them with the team. The role of supervisors
was to provide guidance and ensure that the necessary resources
were made available to the team members to accomplish their mission.
Another area of success for the study was the intensive coordination
with congressional offices. These offices were treated as full
members of the study team, and information was passed freely to
ensure decision were made in a timely fashion.
Although the study was initially authorized for flood control
alone, a great opportunity to restore the ecosystem was realized.
The total plan now combines structural flood control with creation
of habitat for important fish and wildlife species.
Coordination with the potential local sponsor, as required under
the Water Resources Development Act of 1986, was started early.
As a result of being included in the decision making, the local
sponsor was willing and able to sign a Feasibility Cost Sharing
Agreement ahead of schedule, and have funding in place to start
the feasibility phase of the study.. Local engineering firms
were also contacted to gain their understanding of the problems
of the study area. By understanding the area's problems and needs,
as related to water resources, the study team had a clear idea
of the problem, and was able to maintain a clear focus of what
type of alternative solutions were needed.
- Corps Inland Waterways Put Customers First, Cut Red
Tape. The partnership between the U.S. Army Corps
of Engineers and its navigation customers on the Ohio River system--outstanding
for well over 100 years--was cemented when a partnering arrangement
was developed with the navigation industry based on Total Quality
Management principles. The partnership includes several barge
companies and three divisions of the Corps of Engineers.
The focus is to study, identify, and carry out improvements to
the inland waterway navigation system of the Ohio Basin and the
Mississippi River north of St. Louis. Our partnership is producing
results in terms of better personnel utilization, goodwill, navigation
improvements and process efficiency. Actions completed or underway
include:
- The annual issuance of the "Notice to Navigation Interests"
combines the Ohio River
Division, North Central Division, Missouri River Division, and
seven district lock operating regulations into a simplified, shorter
version that is user friendly for the navigation industry. Over
127 separate regulations were reduced to less than 10 pages.
This navigation notice combines all requirements for the system,
regardless of which district/division has responsibility, into
one document, making regulation of the waterway system "seamless"
to the industry. This notice is also provided to waterway users
via the Internet World Wide Web.
- A customer survey of the navigation industry has been completed
to determine their needs
and desires for information. Results from the survey were used
to establish a new centralized mailing system which eliminated
duplication and serious inefficiencies in the old mail distribution
system. Potential for savings and improved customer relations
is significant.
- A third initiative under this partnership agreement combined
the annual Corps-Navigation
Industry-Coast Guard meetings held by several Corps divisions
and districts. This resulted in a more unified approach to the
system and saved industry and government time and travel expenses.
- The government-industry partnership also provides current information
on the Internet
World Wide Web. A Navigation Information Connection "home
page" has been established that provides current navigation
reports, river stage forecasts, maintenance schedules, regulations,
vessel location and other pertinent information to navigation
interests.
- Empowering Employees And Serving Customers: Pittsburgh
District Puts Hydrology On The Internet. More and more
people who used to rely on the mail or telephone to obtain information
find themselves turning to their personal computers to get what
they need. Lewis Kwett, hydraulic engineer in the Army Corps
of Engineers Pittsburgh District's Hydrology and Hydraulics Section,
recognized that need several years ago when he proposed an electronic
river recreation bulletin board. Prior to that time inquiries
regarding river recreation were handled by telephone, letter or
face-to-face contact. The disadvantages were numerous: turn around
time could be lengthy, users complained of limited access hours
and untold dollars were spent in employee time answering river
inquiries.
Kwett's system -- the River Recreation Bulletin Board -- enables
users from both the public and the private sectors to obtain real-time
river information 24 hours a day. All that is required is a personal
computer equipped with a modem. As a result of the positive
response, Kwett expanded the system to include real-time water
level, flow and water quality data for all reaches throughout
the upper Ohio River basin. This system is meeting the information
needs of an ever growing range of public and private industries
as well as recreationists who utilize the waterways throughout
the 26,000 square miles that comprise the Pittsburgh District.
Kwett introduced a second system utilizing the Internet and allowing
the user to access a wide range of data through the Pittsburgh
District's Water Control home page. This server allows the user
to access such information as current river conditions, reservoir
pool level and release forecasts, reservoir project information
and bulletins.
Kwett's programs have saved time and dollars in addition to maintaining
the highest level of service to the users. In its three years
of operation, the Bulletin Board has logged over 14,000 telephone
calls and currently has over 300 active users. During the peak
summer months, the system logs 40-50 calls per day. The Water
Control home page has seen increased usage since its inception
seven months ago. Currently about 50 requests for information
are received each day over the Internet.
- Pittsburgh District Empowers its Retirees and Volunteers.
Volunteer efforts continue to contribute to the efficiency and
successes of operations at the U.S. Army Corps of Engineers Pittsburgh
District.
During FY 1995, 2,403 volunteers completed nearly 31,000 hours
of duty in jobs from clerical support and litter clean-up to wildlife
management. Volunteers were active at 15 district reservoirs and
in the District office. Active groups included the Pennsylvania
Sportsmen for the Disabled, 4-H clubs, Department of Veteran's
Affairs, Kinzua Fish, and Wildlife Association and numerous scouting,
community and school groups. In addition to the groups, a number
of individuals continued their long-running volunteer service.
At Berlin Lake in Ohio, Chloe Dishong has logged a total of 13,474
hours of effort since her retirement as a clerk-typist in the
District. Dishong performs various administrative duties at the
project.
Another District retiree, Bob Oslick, has performed nearly 1,300
hours of service since he left the District in 1988. Oslick is
a familiar face to folks in the District office with his twice-yearly
sales of crafts and candy. Proceeds are donated to help fund the
District's Special Recreation Days. Oslick also volunteers to
assist with Natural Resources Section's Camp Sunshine and Environmental
Youth Camp.
Armed with a special interest in the transportation history of
the Conemaugh River corridor, William Dzombak has put in over
5,000 hours of volunteer work developing many different types
of displays to relate that story. Dzombak's efforts have gone
beyond just the conceptualization stage; he also constructed the
displays and even prepared a standard dam tour book for use as
a training tool.
Clearly it is with the help of the volunteer efforts of dedicated
groups and individuals such as the few mentioned in this article
that the Pittsburgh District continues to provide quality service
to the public. This is becoming increasingly important as budgetary
limitations grow. In fiscal year 1995, the monetary value of the
Pittsburgh District's volunteer efforts totaled over $200,000.
- "Back To Basics" Recreational Access And Safety
Ideas Enhance Use. Since it was built in 1973, the 4,650
foot roadway across the top of Woodcock Creek Lake's earthen dam
in Pennsylvania has been an increasingly popular visitor attraction.
Each year more people are attracted to the picturesque view;
local doctors encourage patients to walk the dam to improve their
health; and joggers, skaters, and biking enthusiasts have also
added to the numbers.
By the mid-1980s, however, pedestrian and vehicular traffic were
creating unsafe conditions. Use was increased by families with
their small children on bicycles and scooters, the physically
challenged, and the elderly taking their daily jaunts. The social
aspect of "seeing and being seen" at the dam brought
out more visitors--including teenagers in fast cars.
In 1984, a gate was installed at the beginning of the dam to limit
vehicle access after 4 p.m. or when the road was crowded with
pedestrians. This action brought raves from the customers--now
this walkway was safe for families and they no longer had to look
over their shoulders for oncoming cars. In 1985, a walk-around
was added so customers did not have to straddle the gate to gain
access to the dam. The walk-around was made large enough to accommodate
bicycles and wheelchairs with ease. Word spread fast and even
more customers of all ages were drawn to the now safer Woodcock
Dam. In 1987, the parking lot was expanded to accommodate the
increased usage and a water fountain for the physically-challenged
was installed.
For several years before 1987, it was noticed that many visitors,
especially the elderly and infirm, had no place to get off the
narrow road surface to rest along the nearly one mile long dam.
Plans were scrutinized and accepted and the project staff built
two rest stations, placed strategically along the top of the dam.
The sturdily built wood decks with benches now provide a safe
haven for the weary.
All these additions were made possible by a responsible approach
by the Corps of Engineers to provide a safe and accessible dam
to the visiting public.
- Corps of Engineers, City Of Philadelphia Partner For
New Runway Construction. The Army Corps of Engineers
Philadelphia District, as part of its processing of a Clean Water
Act regulatory permit, developed a partnering plan with the City
of Philadelphia for the Runway Development Project at Philadelphia
International Airport. Under this plan, the Corps will use dredged
material from the Delaware River Federal shipping channel as a
source for the needed 2 million cubic yards of fill material for
the new runway embankment.
After extensive Corps review, technical assistance and interagency
coordination, the dredging option was included in the City's contract
advertisement for this work; and the successful low bidder, Buckley
Construction, included the dredging method in their bid. The
City of Philadelphia has reported a savings of $7,000,000 by using
this source of fill material as compared to conventional upland
sources.
In addition to the significant savings of public resources, the
Corps-City partnership was able to eliminate the adverse environmental
impacts and public inconvenience of transporting 2 million cubic
yards of fill across State roadways. Furthermore, the City's
removal of fill from the Federal channel by advance maintenance
dredging will eliminate the need for the Philadelphia District
to perform this work (estimated $8,000,000 savings) and allow
them to pursue work in other high priority areas of the Delaware
River shipping channel.
- Philadelphia Partnering Cleans Hazardous Waste Site.
The Philadelphia District of the U.S. Army Corps of Engineers
has met the Vice President's National Performance Review's (NPR)
goals through partnering of its largest construction contract,
the Lagoon and Project Site Cleanup of the Bridgeport Rental and
Oil Services (BROS) site located in Bridgeport, NJ. Implementation
of Partnering at the BROS site embodied the NPR goals of cutting
of red tape, placing customers first, and empowering employees.
The BROS contract was awarded in 1989 and almost immediately encountered
problems. The problems grew larger and more numerous until they
came to a head in April 1993 when the District considered terminating
the contractor for default. Termination would have been a great
embarrassment to the contractor and the Philadelphia District,
and a severe disappointment to our customers, the U.S. Environmental
Protection Agency, Region II (USEPA) and the New Jersey Department
of Environmental Protection (NJDEP). If the contract had been
terminated, a great amount of money would have been spent without
making significant advancement in remediating the site and the
USEPA's ability to ever complete the cleanup would have been severely
hampered. As a result, in April 1993, the Philadelphia District
Commander offered to partner the project with the contractor,
providing the contractor displayed commitment to project completion.
The contractor readily accepted. The decision to partner the
project was perhaps the wisest move made by LTC Richard Sliwoski
during his tenure as District Commander.
Partnering made the project a success story rather than a horror
show. All parties associated with the project were involved in
the partnering process: the USEPA and NJDEP as the customer,
Philadelphia District as the USEPA's contractor, Ebasco Constructors
Inc. (now Foster Wheeler Environmental Corporation) as the Corps
remediation contractor, and the TAMS/E&E Joint Venture as
the designers. The Partnering process focused on joint problem
solving at the lowest possible levels without regard to organizational
boundaries, easing of the adversarial relationships that were
unproductive and created costly conflicts, and a "talk before
you write" system of communication. The joint approach to
problems resulted in their timely resolution and the elimination
of new disputes and reduced the resource requirements of each
organization. Easing of the adversarial relationships resulted
in timely resolution of outstanding disputes. The "talk
before you write" approach significantly reduced the amount
of paperwork generated. Overall, the entire project management
system was greatly improved.
The effect of partnering on the actual project execution and the
attitudes of the employees was clear. After the initial Partnering
conference in July of 1993, the quality of the work and safety
performance improved significantly and the amount of material
excavated and incinerated per month almost tripled. Work which
had been estimated to be complete in 1998 was done by 1996. Individuals
from all parties now enjoyed going to work because things were
getting accomplished.
Without Partnering, the project would have been a much more expensive
undertaking than it was. The Partnering approach to problem resolution
resulted in the acquisition of an amphibious excavator to improve
lagoon excavation. The Government was directing the contractor
to build a land bridge across the lagoon when the contractor proposed
this piece of equipment, which was unproven, as a means to do
the job faster and more economically. A joint decision was made
to go ahead, the equipment performed miraculously, and an estimated
four million dollars in cost were saved. The Partnering approach
also resulted in geotechnical innovation. As backfilling of the
lagoon reached 50 percent, a soft, uncontaminated underlayer of
sediment was encountered over which backfill could not be placed.
The Government's geotechnical engineers developed a plan for
strengthening and bridging over the soft sediments which was presented
to the contractor. Again, a joint decision was made to go ahead,
the plan was successful, and an estimated nine million dollars
were saved by avoiding excavation of the soft material. Finally,
because of Partnering, the project is going to be completed without
any contract claims, avoiding expensive and time-consuming litigation.
Partnering at the BROS project showed how working together as
a team, instead of against each other as traditional adversaries,
can allow the Government and its contractors to solve problems
quicker and more cost effectively. Without partnering, the BROS
site would be tangled in paperwork and red tape, it would have
cost the Government millions of additional dollars and the USEPA
would not have a remediated site.
U.S. Army Corps of Engineers Pacific Ocean Division.
The U.S. Army Corps of Engineers Pacific Ocean Division continues
to reorganize to streamline organizational entities to enhance
processing. Reorganization of Technical Engineering Division,
Design Division, and Quality Assurance Branch to form one unified
Technical Division allows for design and review of projects under
the guidance of a single technical discipline Branch Chief, and
results in a supervisor/employee ratio of 1:14.6.
The Pacific Ocean Division (POD) Construction Division recently
reorganized to abolish the Construction Management Branch and
place the construction management responsibilities into the Resident
Offices, resulting in a more horizontal organization and improving
the way business is done by providing a greater degree of flexibility
for the Resident Offices in resolving technical and contractual
issues.
In 1995, the Pacific Ocean Division successfully consolidated
all Civil Works (CW) programming and budgeting activities within
one office resulting in an estimated annual savings of approximately
$300,000 per year in personnel costs alone. As the single office
of contact for CW, valuable time savings and efficiencies are
realized by both internal and external customers.
As the central design/construction agent in Japan, the Corps of
Engineers Japan District, part of Pacific Ocean Division, continually
focuses on responsive and economical support for all military
services. Examples include:
Requirements contracts that are economical and responsive tools,
covering multiple installations' recurring type work (e.g. painting
and paving). These contracts contain reasonable prices through
economy of scale and simplified designs portraying well defined
scope and existing conditions. Delivery orders are awarded within
a day after receipt of funds.
A cross-organizational initiative to consolidate computer-assisted
design and geographic information systems is being developed.
Once completed, Pacific Ocean Division customers and users will
share the same technical database from which all master planning,
programming, plant/utilities survey, information storage, and
retrieval and other electronic data services can be used, resulting
in time and cost savings.
Japan District provides rapid emergency response to partners who
do not have specialized technical resources readily available.
Examples include assessment of earthquake damage of facilities
at remote installations, including Misawa AFB, the Marine Corps
Base at Camp Fuju, and the US Consulates' residence and office
building following the Great Hanshin earthquake in January 1995.
The World-Wide-Web was added to the Division's existing Internet
access capabilities, thereby providing the POD staff access to
an unlimited number of resources including regulations, publications,
and other valuable information on topics such as engineering,
law, total quality management, NPR initiatives and information
management.
Networking of CD-ROM drives allows the Pacific Ocean Division
staff to access information on CD-ROM media, including publications,
regulations, catalogs, information bases, and images. Networking
reduced costs and man-hours by eliminating multiple subscriptions
and reducing the time required to access information.
Participation in the Korean Cost Sharing Program to procure vehicles
resulted in a cost savings of $264,655 during FY 1995. Continued
participation will enable FED to realize a savings of $925,541
over 1996 and 1997.
The Far East District saved its Army and Air Force customers approximately
$22M in
FY 1995 by providing potable groundwater through its well water
maintenance and construction programs, and eliminating the need/cost
of procuring expensive, off-base municipal water. These savings
will be duplicated in FY 1996.
- St. Paul District Employees Improve Ways Of Doing Business.
The St. Paul District of the Army Corps of Engineers established
a Total Army Quality program during 1995. This program, the Army's
version of the Total Quality Management (TQM) concept, focuses
on empowering front-line employees as Process Action Teams to
solve problems and improve business processes.
The first Process Action Team to complete its analysis implemented
several process changes and recommended others which, combined,
would provide an estimated first-year savings of $128,000 and
a recurring annual savings of $142,000 in following years. The
PAT reviewed the processes associated with purchasing under blanket
purchase agreements (BPAs). As a result, the number of BPAs maintained
by the district was reduced by 60 percent and replaced by increased
use of the government credit card. This effort supports the NPR
goals of empowering employees and reducing red tape.
The St. Paul District's Army Ideas for Excellence Program, meanwhile,
continues to be highly successful. Estimated annual savings from
suggestions approved for implementation during FY 1995 exceeded
$220,000. The AIEP accomplishments include one suggestion on
project status maps that was approved for implementation at every
level including the House and Senate Energy and Water Development
subcommittees. The suggestion recommended a change to the project
status map format which allows the maps to be printed in black-and-white
instead of color. This will produce an annual savings of an estimated
$82,000 Corps-wide. This suggestion supports the NPR goal of
putting customers first. The new maps can be reproduced directly
in Congressional reports, faxed and even E-mailed. Printing the
maps in black-and-white allows the Corps to be more responsive
to requests from the Congressional subcommittees -- the customers.
- Outsourcing of Logistics Allows Combat Troops to Stick
to Basics: As the Army reduces in size, privatization
offers one means of reducing support forces while maintaining
its combat force structure. The Army's Logistics Civil Augmentation
Program (LOGCAP), managed by the Corps of Engineers Transatlantic
Programs Center, is helping to meet that goal.
The LOGCAP contract is a cost-plus award fee contract that uses
a contractor to plan for, and perform when required, logistics
and engineering services to augment U.S. forces during contingency
operations. The contract was used in Somalia, Rwanda, the Middle
East, and Haiti. Most recently, it has been used to support NATO
operations in the Balkans -- the largest application of LOGCAP
effort to date, with an estimated cost of $400 million.
The contractor, Brown & Root Services Corp., provides basic
life support services -- food, water, sanitation, shelter, and
laundry; and the full realm of logistics services -- transportation,
electrical, hazardous materials collection and disposal, fuel
delivery, airfield and seaport operations, and road maintenance.
Generally, the contractor is required to establish camps, then
operate and maintain them. However, the level of service is determined
solely by the Commander in the field.
LOGCAP has provided the Army with a highly flexible contractual
means of providing quality of life services to troops deployed
in some of the harshest environments in the world, without impacting
its combat capability.
TheTransatlantic Programs Center (TAC) recently completed installing
the hardware and software necessary to establish full-time Internet
and e-mail capabilities for all its overseas offices and centers.
This is part of our ongoing effort to support and empower our
employees doing work overseas and to provide the best service
possible to our customers. TAC operates construction project
offices in Egypt, Kuwait, Qatar, Saudi Arabia, and Russia and
provides oversight to the Transatlantic Programs Center, Europe,
headquartered in Wiesbaden, Germany. State-of-the-art technology
now gives our field offices instantaneous communications with
the headquarters here in the U.S. and allows them access to the
world-wide information resources necessary to do their work.
These tools also allow our overseas employees the ability to
keep in close touch with their families via e-mail, providing
them with an avenue of personal contact so vital to those stationed
far from home.
During the Fall of 1994, in response to decreasing workload and
customer demands for reduced costs, the Corps of Engineers Transatlantic
Programs Center embarked on an ambitious program to reduce its
cost of doing business. The Center took actions to reduce indirect
labor costs in both support and production sections of the organization.
There was also a concerted effort to reduce other overhead expenses,
such as travel, communications, and lease costs. These efforts
paid off in a significant reduction in rates charged to customers,
for work managed by TAC headquarters personnel, of 13-20% (depending
on type of work) from August 1994 to March 1996. This reduction
was accomplished while absorbing two pay increases for employees.
The outcome is that customers are receiving improved quality
of design and construction management services from the Transatlantic
Programs Center, at a labor rate less than what they were paying
in mid-1994.

|