BUDGET ACTIVITY: 4
PROGRAM ELEMENT: 0603800N
PROJECT NUMBER: D2209
PROGRAM ELEMENT TITLE: JOINT ADVANCED STRIKE JASTP
PROJECT TITLE: TECHNOLOGY (JAST) PROGRAM
(U) COST (Dollars in thousands)
| PROJECT NUMBER & TITLE | FY 1996 ACTUAL | FY 1997 ESTIMATE | FY 1998 ESTIMATE | FY 1999 ESTIMATE | FY 2000 ESTIMATE | FY 2001 ESTIMATE | FY 2002 ESTIMATE | FY 2003 ESTIMATE | TO COMPLETE | TOTAL PROGRAM |
| D2209 JASTP | 79,981 | 246,076 | 448,855 | 443,522 | 249,429 | 25,448 | 0 | 0 | 0 | 1,621,099 |
| RDT&E Articles (Unit cost of RDT&E articles not separately priced) | 4 | |||||||||
A. (U) MISSION DESCRIPTION AND BUDGET ITEM JUSTIFICATION: The Joint Strike Fighter (JSF) Program (formally JAST) will develop and field an affordable, highly common family of next generation strike aircraft for the USN, USMC, USAF and allies. Current program emphasis is on facilitating the evolution of fully validated and affordable joint operational requirements, and demonstrating cost leveraging technologies and concepts to lower risk prior to entering Engineering and Manufacturing Demonstration (E&MD) in FY 2001. This is a joint program with no executive service. Navy and Air Force each provide approximately equal shares of annual funding for the program effective in FY 1995. The Defense Advanced Research Projects Agency (DARPA) and the United Kingdom (UK) contribute funding effective in FY 1996. The Netherlands, Norway and Denmark will contribute funding effective in FY 1997 under a Multi-Lateral Agreement.
(U) JUSTIFICATION FOR BUDGET ACTIVITY: This program is funded under DEMONSTRATION & VALIDATION because it integrates hardware for test related to specific ship or aircraft applications.
(U) PROGRAM ACCOMPLISHMENTS AND PLANS:
1. (U) FY 1996 ACCOMPLISHMENTS: (Breakout reflects Navy, Air Force, DARPA and UK funding)
(U) ($ 60,768) Completed concept definition and design research for weapon system concepts for a tri-service family of aircraft; received contractors' preferred weapon system concepts and recommended development and demonstration plans; and continued affordability analyses.
(U) ($ 7,000) Conducted Phase I of the Alternate Engine Program including study efforts and preliminary design risk reduction activities.
(U) ($111,587) Completed technology maturation concept definition and design research; continued demonstrations and assessments in the areas of airframe, flight systems, manufacturing and producibility, propulsion, mission systems and supportability.
FY 1998 RDT&E,N BUDGET ITEM JUSTIFICATION SHEET
DATE: February 1997
BUDGET ACTIVITY: 4
PROGRAM ELEMENT: 0603800N
PROJECT NUMBER: D2209
PROGRAM ELEMENT TITLE: JOINT ADVANCED STRIKE JASTP
PROJECT TITLE: TECHNOLOGY (JAST) PROGRAM
(U) ($ 7,101) Continued strategy-to-task analysis and strike warfare demonstrations and assessments to facilitate the Services' joint requirements definition.
(U) ($ 5,065) Continued modeling and simulation activities to support strike warfare mission area analysis.
(U) ($ 5,502) Completed Advanced Short Takeoff and Vertical Landing (ASTOVL) risk mitigation efforts, integrated with JAST Program Concept Development tasks.
(U) ($ 7,152) Supported program operations, including program office functions.
(U) ($204,175) Total
2. (U) FY 1997 PLAN: (Breakout reflects Navy, Air Force, DARPA, UK and Multi-Lateral funding)
(U) ($411,620) Competitively awarded contracts to Boeing and Lockheed Martin for ground and flight demonstrations and continued concept refinement for a tri-service family of aircraft that meets the Services' needs and optimizes commonality among the variants to minimize life cycles costs (LCC); award contract to Pratt & Whitney for supporting propulsion efforts.
(U) ($ 25,000) Commence Phase II of the Alternate Engine Program, which continues detailed design and begins hardware testing.
(a) Within this amount, $10M has been included for early risk reduction on critical technologies for the alternative engine.
(b) The Department is evaluating acceleration of the alternative engine to meet a Lot 4 production introduction.
(U) ($ 6,308) Continue requirements analysis efforts including Cost & Operational Trades (COPT) to facilitate the Services' joint requirements definition.
(U) ($ 10,292) Continue modeling and simulation activities to support strike warfare mission area analysis.
(U) ($172,695) Continue technology maturation demonstrations and assessments in the areas of airframe, flight systems, manufacturing and producibility, propulsion, mission systems, and supportability. Commence systems engineering support for the Concept Demonstration Phase in the areas of system test, air vehicle analysis and integration, advanced cost estimating, survivability, integrated flight and propulsion control and carrier suitability.
FY 1998 RDT&E,N BUDGET ITEM JUSTIFICATION SHEET
DATE: February 1997
BUDGET ACTIVITY: 4
PROGRAM ELEMENT: 0603800N
PROJECT NUMBER: D2209
PROGRAM ELEMENT TITLE: JOINT ADVANCED STRIKE JASTP
PROJECT TITLE: TECHNOLOGY (JAST) PROGRAM
(U) ($ 9,525) Support program operations, including program office functions; Congressionally directed OSD Force Structure Analysis.
(U) ($ 6,035) USN portion of program reduced for transfer to Small Business Innovative Research assessment in accordance with 15 U.S.C. 638.
(U) ($ 12,809) Anticipated USAF and DARPA general reductions.
(U) ($654,284) Total
3. (U) FY 1998 PLAN: (Breakout reflects Navy, Air Force, DARPA, UK and Multi-Lateral funding)
(U) ($718,261) Continue Concept Demonstration efforts by Boeing, Lockheed Martin and Pratt & Whitney for ground and flight demonstrations and continued concept refinement for a tri-service family of aircraft.
(U) ($ 20,000) Continue the Alternate Engine Program.
(U) ($ 7,287) Continue requirements analysis efforts including Cost & Operational Trades (COPT) to facilitate the Services' joint requirements definition.
(U) ($ 11,913) Continue modeling and simulation activities to support strike warfare mission area analysis.
(U) ($231,591) Continue technology maturation demonstrations and assessments in the areas of airframe, flight systems, manufacturing and producibility, propulsion, mission systems, and supportability. Continue systems engineering support for the Concept Demonstration Phase in the areas of system test, air vehicle analysis and integration, advanced cost estimating, survivability, integrated flight and propulsion control and carrier suitability.
(U) ($ 6,355) Support program operations, including program office functions.
(U) ($995,407) Total
4. (U) FY 1999 PLAN: (Breakout reflects Navy, Air Force, DARPA, UK and Multi-Lateral funding)
(U) ($702,484) Continue Concept Demonstration efforts by Boeing, Lockheed Martin and Pratt & Whitney for ground and flight demonstrations and continued concept refinement for a tri-service family of aircraft.
FY 1998 RDT&E,N BUDGET ITEM JUSTIFICATION SHEET
DATE: February 1997
BUDGET ACTIVITY: 4
PROGRAM ELEMENT: 0603800N
PROJECT NUMBER: D2209
PROGRAM ELEMENT TITLE: JOINT ADVANCED STRIKE JASTP
PROJECT TITLE: TECHNOLOGY (JAST) PROGRAM
(U) ($ 23,000) Continue the Alternate Engine Program.
(U) ($ 5,776) Continue requirements analysis efforts including Cost & Operational Trades (COPT) to facilitate the Services' joint requirements definition; receive Joint Operational Requirements Document (JORD) from the Services.
(U) ($ 9,424) Continue modeling and simulation activities to support strike warfare mission area analysis.
(U) ($203,749) Continue technology maturation demonstrations and assessments in the areas of airframe, flight systems, manufacturing and producibility, propulsion, mission systems, and supportability. Continue systems engineering support for the Concept Demonstration Phase in the areas of system test, air vehicle analysis and integration, advanced cost estimating, survivability, integrated flight and propulsion control and carrier suitability.
(U) ($ 6,300) Support program operations, including program office functions.
(U) ($950,733) Total
B. (U) PROGRAM CHANGE SUMMARY: (Dollars in thousands)
| FY 1996 | FY 1997 | FY 1998 | FY 1999 | Total Cost | |
| (U) FY 1997 President's Budget: | $81,215 | $246,833 | $421,848 | $457,300 | $1,592,855 |
| (U) Adjustments from Pres Budget: | -1,234 | -757 | +27,007 | -13,778 | + 28,244 |
| (U) FY 1998 President's Budget: | $79,981 | $246,076 | $448,855 | $443,522 | $1,621,099 |
(U) CHANGE SUMMARY EXPLANATION:
(U) Funding: FY 1996 decrease reflects CNO PA&E (-$18), Jordanian Rescission (-$430), SBIR Transfer (-$1,123)and Reversed to Increase (+$337) adjustments. FY 1997 has been decreased by a net of $757 reflecting the increase of $10,000 for alternate engine efforts offset by decreases for Non-FFRDC reduction ($-244), Navy Working Capital Fund (NWCF) Savings (-$5,136), General Reductions (-$5,136) and Budgetary Resolution (-$241). FY 1998 increase reflects the replacement of funding formerly provided by DARPA (+$32,612) and decreases attributed to Balance adjustments (-$1,046), NRL BRAC Savings (-$15), Respread (-$488), Carryover (-$165), Acquisition Internship Program (-$223), Acquisition Center for Excellence (-$255), AN-SSQ-53 (-$1,800), Desk Book (-$115) and Inflation savings (-$1,432) adjustments. FY 1999 net decrease reflects the replacement of funding formerly provided by DARPA (+$18,226) and the decreases attributed to Balance Adjustments (-$983), NRL BRAC Savings (-$95), Respread (-$496), NWCF Savings
FY 1998 RDT&E,N BUDGET ITEM JUSTIFICATION SHEET
DATE: February 1997
BUDGET ACTIVITY: 4
PROGRAM ELEMENT: 0603800N
PROJECT NUMBER: D2209
PROGRAM ELEMENT TITLE: JOINT ADVANCED STRIKE JASTP
PROJECT TITLE: TECHNOLOGY (JAST) PROGRAM
(-$1,959), Acquisition Internship Program (-$689), Acquisition Center for Excellence (-$245), Inflation Savings (-$2,398), CVN-77 reduction (-$25,000), Desk Book (-$139) adjustments.
(U) Schedule: No Change. Program schedule is consistent with recent Concept Demonstration Phase contract awards.
(U) Technical: Not applicable.
C. (U) OTHER PROGRAM FUNDING SUMMARY: (Dollars in thousands) This is a joint program with no executive service. The United Kingdom is a full collaborative partner in the program in accordance with a Memorandum of Understanding (MOU) signed in December 1995. The Netherlands, Norway and Denmark will become associate partners in the program in accordance with a Multi-Lateral Memorandum of Agreement (MOA) to be signed in the second quarter of FY 1997.
| FY 1996 ACTUAL | FY 1997 ESTIMATE | FY 1998 ESTIMATE | FY 1999 ESTIMATE | FY 2000 ESTIMATE | FY 2001 ESTIMATE | FY 2002 ESTIMATE | FY 2003 ESTIMATE | TO COMPLETE | TOTAL PROGRAM | |
|---|---|---|---|---|---|---|---|---|---|---|
| (U)RDT&E 0603800F | 81,277 | 252,043 | 458,052 | 465,611 | 245,439 | 23,641 | 0 | 0 | 0 | 1,609,843 |
| (U)RDT&E 0603800E | 28,917 | 76,865 | 23,900 | 0 | 0 | 0 | 0 | 0 | 0 | 129,682 |
| (U)United Kingdom | 14,000 | 71,000 | 55,000 | 34,000 | 26,000 | 0 | 0 | 0 | 0 | 200,000 |
| (U)Multi-Lateral | 0 | 8,300 | 9,600 | 7,600 | 5,000 | 1,700 | 0 | 0 | 0 | 32,200 |
(U) RELATED RDT&E:
Milestone II for E&MD of the Joint Strike Fighter (JSF) is planned in FY 2001.
| FY 1996 ACTUAL | FY 1997 ESTIMATE | FY 1998 ESTIMATE | FY 1999 ESTIMATE | FY 2000 ESTIMATE | FY 2001 ESTIMATE | FY 2002 ESTIMATE | FY 2003 ESTIMATE | TO COMPLETE | TOTAL PROGRAM | |
|---|---|---|---|---|---|---|---|---|---|---|
| (U)RDT&E 0604800F: | 0 | 0 | 0 | 0 | 0 | 560,234 | 1,399,882 | 1,915,720 | TBD* | TBD* |
| (U)RDT&E 0604800N: | 0 | 0 | 0 | 0 | 0 | 558,184 | 1,398,026 | 1,913,742 | TBD* | TBD* |
* Pending initial SAR approval, 3QTR FY97
FY 1998 RDT&E,N BUDGET ITEM JUSTIFICATION SHEET
DATE: February 1997
BUDGET ACTIVITY: 4
PROGRAM ELEMENT: 603800N
PROJECT NUMBER: D2209
PROGRAM ELEMENT TITLE: JOINT ADVANCED STRIKE JASTP
PROJECT TITLE: TECHNOLOGY (JAST) PROGRAM
D. (U) SCHEDULE PROFILE:
Dec 94 Commenced Concept Development Phase
Mar 96 Released RFP for Concept Demonstration Phase
May 96 Designated a joint, DOD, Acquisition Category ID Program by USD(A&T)
Nov 96 Competitively Awarded Concept Demonstration Contracts to Boeing and Lockheed Martin
Mar 01 Milestone II for JSF E&MD
FY 1998 RDT&E,N BUDGET ITEM JUSTIFICATION SHEET
DATE: February 1997
BUDGET ACTIVITY: 4
PROGRAM ELEMENT: 0603800N
PROJECT NUMBER: D2209
PROGRAM ELEMENT TITLE: JOINT ADVANCED STRIKE JASTP
PROJECT TITLE: TECHNOLOGY (JAST) PROGRAM