BCIS Initial Draft MFP
20 June 98

APPENDIX 9.4

FIELDING COMMAND CHECKLIST

 Action Target Date
 Submit first Draft Materiel Fielding Plan to FORSCOM for review and comment

JUL 98 
 Submit updated Draft MFP for review and comment

AUG 99
 Submit final Draft MFP, current Distribution Plan with the
Materiel Fielding Agreement to FORSCOM for review,
comment and signature

DEC 99
 Verifiy end item requirements and request initial support list
supporting commands

MAR 00
 Distribute Final MFP, approved MFA and coordinate
Materiel Requirements List (MRL)

MAY 00
 Conduct MRL coordination Meeting with Gaining Command

JUN 00 
 Obtain project code and obtain DODAACs of gaining units

JUL 00
 Assess supportability for fielding and verify handoff dates
With Gaining Command

AUG 00
 Materiel Fielding Team (MFT) deploys to fielding location
For New Material Introductory Brief and materiel staging preparation

20 SEP 00
 MFT verifies documentation and coordinates inventory and
Handoff procedures with Gaining Units

26 SEP 00
 Begin hardware deliveries and staging

02 OCT 00
 Contractor Installation Teams deploy to fielding location
For Installation Preparation

10 OCT 00
 Installation Begins

16 OCT 00
 Final Draft TMs (verified) available at first Gaining Unit at Handoff

20 OCT 00
 NET Team deploys to training location for coordination

15 JAN 01
 NET (1/22 INF) Begins

16 JAN 01