BCIS Initial Draft MFP
20 June 98
BCIS fielding to the 4th Infantry Division (-) at Ft. Hood, TX is in the early planning stage. Logistic support for the system is provided in Section 4 of this MFP. Once BCIS is handed-off to the units, BCIS will be fully supportable in the field with minimum impact on manpower. The initial issues to be resolved prior to the draft MFP distribution are:
| Actions Required |
|
| Coordinate TM and provisioning plans with PMs Abrams and Bradley |
|
| Review and comment on initial draft MFP |
|
| Identify coordination Points of Contact in the Gaining Command |
|
| Identify newly assigned TSM |
|
| Identify locations and reserve space for BCIS facility requirements |
|
| Define and plan support for BCIS oscillator (RT) calibration |
|
| Award contract and develop BCIS/CCTT integrations |
|
| Identify Materiel Fielding Team personnel and schedule |
|
| Identify Contractor Installation Team personnel and schedule |
|
| Identify BCIS depot |
|