BCIS fielding to the 4th Infantry Division (-) at Ft. Hood, TX is in the early planning stage. Logistic support for the system is provided in Section 4 of this MFP. Once BCIS is handed-off to the units, BCIS will be fully supportable in the field with minimum impact on manpower. The initial issues to be resolved prior to the draft MFP distribution are:

 Actions Required

 Responsibility
 Coordinate TM and provisioning plans with PMs Abrams and Bradley

PM CI 
 Review and comment on initial draft MFP

FORSCOM
 Identify coordination Points of Contact in the Gaining Command

FORSCOM
 Identify newly assigned TSM

TRADOC
 Identify locations and reserve space for BCIS facility requirements

DFFC/FIO
 Define and plan support for BCIS oscillator (RT) calibration

PM CI/TRW
 Award contract and develop BCIS/CCTT integrations

PM CI/PM CCTT
 Identify Materiel Fielding Team personnel and schedule

PM CI
 Identify Contractor Installation Team personnel and schedule

PM CI
 Identify BCIS depot

DESCOM