
CHAPTER 8
LAUNCH SITE OPERATION
Launch Site Operation mainly includes:
The typical working flow and requirements of the launch site operation are introduced in this chapter. For different launch missions, the launch site operation will be different, especially for combined operations related to joint efforts from SC and LV sides. Therefore, the combined operations could be performed only if the operation procedures are coordinated and approved by all sides.
LM-2C uses JSLC as its main launch site. The launch site operations in JSLC are focused in this Chapter. The operations in XSLC are similar.
8.1 LV Checkouts and Processing
Two-stage LM-2C or LM-2C/CTS launch vehicle is transported from CALT facility (Beijing, China) to JSLC (Gansu Province, China) and undergoes various checkouts and processing in the North Technical Center and the South Launch Center. The typical LV working flow in the launch site is shown in Table 8-1.
Table 8-1 LV Working Flow in Launch Site
|
No. |
Item |
Working Period |
Accumulative Period |
||
|
T E C H . |
1 |
To Unload LV from the Train and Transfer LV to LV Test Building (BL). |
1 day |
1 day |
|
|
2 |
Unit Tests of Electrical System |
7 days |
8 days |
||
|
3 |
LV Status Recovery before Transfer |
3 days |
11 days |
||
|
L A U N C H C E N T E R |
4 |
To Transfer LV to the Launch Center and Erect LV on the Launch Tower |
1 days |
12 days |
|
|
5 |
Tests to Separate Subsystems |
2 days |
14 days |
||
|
6 |
Matching Test Among Subsystems |
2 days |
16 days |
||
|
7 |
overall checkout on the first and second stages |
2 days |
18 days |
||
|
8 |
To Mate SC/Fairing Stack with LV |
1 days |
19 days |
||
|
9 |
CTS subsystem tests and matching tests |
1 days |
20 days |
||
|
10 |
The First Overall Checkout |
1 day |
21 days |
||
|
11 |
The Second Overall Checkout ( Launch Rehearsal, SC Involved) |
1 day |
22 days |
||
|
12 |
The Third Overall Checkout |
1 day |
23 days |
||
|
13 |
Reviews on Checkout Results |
1 days |
24 days |
||
|
14 |
Functional Check before Fueling, Gas Replacement of Tanks |
1 days |
25 days |
||
|
15 |
N 2O4/UDMH Fueling and Launch |
2 day |
27 days |
||
|
Total |
27 days |
27 days |
|||
After SC is transferred to Launch Center, some of SC and LV operations can be performed in parallel under conditions of no interference.
8.2 Combined Operation Procedures
Take LM-2C/CTS launching multiple SCs as an example.
8.2.1 SC/LV Integration and Fairing Encapsulation in North Technical Center
In BS2 & BS3, SC team carries out all the SC operations. LV side is responsible for mating SCs with CTS and installing SC/LV separation devices. The following describes the typical working procedure:
Refer to Figure 8-1.

8.2.2 SC Transfer and Fairing/Stage-2 Integration
CLTC is responsible for transferring the encapsulated fairing from BS3 to the North Launch Center. The following working procedures are performed:
Refer to Figure 8-2.

8.3 SC Preparation and Checkouts
8.4 Launch Limitation
8.4.1 Weather Limitation
8.4.2 "GO" Criteria for Launch
8.5 Pre-launch Countdown Procedure
The typical pre-launch countdown procedure in the launch day is listed below:
|
No. |
Time |
Event |
|
1 |
-7 hours |
Launch Status Preparation; |
|
2 |
-5 hours |
LV Power-on, Functional Checkouts on Each Sub-system |
|
3 |
-4 hours |
Connecting Plugs for Battery and Pyrotechnics |
|
4 |
-3 hours |
LV Status Checkouts, Sealing; |
|
5 |
-2 hours |
GSE Status Checkouts; |
|
6 |
-90 minutes |
Final Launch Status Preparation; |
|
7 |
-60 minutes |
SC side send "GO" signal; Battery air-conditioning stops; LV tanks are pressurized; Aiming; |
|
8 |
-40 minutes |
Flight Software Loading; One of Air-conditioning Pipes Drop-off; |
|
9 |
-30 minutes |
Moveable Platforms on the Umbilical Tower Withdrawal; |
|
10 |
-15 minutes |
Umbilical Disconnection; |
|
11 |
-7 minutes |
The Final Air-conditioning Pipe Drop-off; |
|
12 |
-2 minutes |
LV Power Switch Over, In-Flight-Disconnectors (IFD) Drop-off; |
|
13 |
-1 minute |
Swinging Arms Withdrawal; |
|
14 |
-40 seconds |
TT&C Systems Starting; |
|
15 |
-5 seconds |
Camera On |
|
16 |
0 |
Ignition |
8.6 Post-launch Activities
The orbital parameters of the injected orbit will be provided to Customer in half-hours after SC injection.
The launch evaluation report will be provided to the Customer in a month after launch.