FY98 Army Military Space RDDS

0208010A Joint Tactical Communications Program (TRI-TAC)

COST (In Thousands) FY 1996 Actual FY 1997 Estimate FY 1998 Estimate FY 1999 Estimate FY 2000 Estimate FY 2001 Estimate FY 2002 Estimate FY 2003 Estimate Cost to Complete Total Cost
D107 Echelons Above Corps (EAC) Comm 12647 18229 8983 9941 4571 8131 8119 8127 122300 201048

A. Mission Description and Budget Item Justification: A requirement exists to automate Signal Corps unit's capability to manage multiple tactical communications systems in support of battlefield operations. The Integrated System Control (ISYSCON) facility will provide automated, integrated management of the tactical communications network, establish an interface with each technical control facility in the Army Tactical Command and Control System (ATCCS) architecture, and enable automation assisted configuration and management of a dynamic battlefield. ISYSCON is being developed in an evolutionary manner with incremental software releases. A change to the requirements document has added planning and management of satellite resources as a requirement. The ISYSCON has been selected as the baseline for network management system for joint task force use. The Battlefield Spectrum Management (BSM) software has been designated as part of the migration system for DOD use. The work efforts in FY 1996 - FY 1999 support the development of the first three software releases (P0, IOT&E & P2, P3), the fabrication of Low Rate Initial Production (LRIP) prototype, support for an IOT&E, and initiation of Nodal Management, Automatic Network Management and work efforts for follow-on software releases. This program element also supports any development required for PM, Joint Tactical Area Communications System ( JTACS) Area Common User Systems (ACUS). This program is assigned to Budget Activity 7 since it includes those development projects, in support of a development acquisition program or upgrades, still in engineering and manufacturing development but which have received approval for production through DAB or other action, or production funds have been included in the DOD budget submission for the budget or subsequent fiscal year. The ISYSCON Program serves as a baseline foundation to support future network management initiatives tied to and part of the evolution to the Digitized Division and the WIN Architecture.

Acquisition Strategy: The acquisition strategy for the development phase was to competitively award an Engineering Manufacturing Development phase contract (awarded Sep 92). A Milestone III Decision for the Full Production Phase is scheduled for FY 98 following a successful IOT&E in 4QFY97.

FY 1996 Accomplishments:
1046 Initiated systems design for IOT&E software baseline
523 System integration test (P0)
2616 Completed detail design and conducted Developmental Progress Review (DPR)
3100 Task Force XXI
600 Completed BSM Version 4.0
3178 Began code, unit test, and system test of the IOT&E software baseline
584 Delivered draft training materiel
500 CDR for hardware prototypes
500 Developed and deliver draft tech pubs
Total 12647


FY 1997 Planned Program:
5200 Participation in the Army Warfighter Experiment (AWE) Exercise
1543 Conduct DPR for IOT&E baseline
2489 Complete systems design for IOT&E software baseline
1869 IOT&E training/testing support
2043 Initiate systems design for Phase 2 (P2) baseline
3368 Code, unit test, system test for P2 baseline
1272 Continue systems design for P2 baseline
445 Small Business Innovative Research/Small Business Technology Transfer (SBIR/STTR)
Total 18229


FY 1998 Planned Program:
506 Conduct DPR for P2 baseline
2160 Conduct code, unit test, system test for P2 baseline
3173 Complete systems design for P2 baseline
1155 P2 software release
1989 Conduct Follow-On Test & Evaluation (FOT&E) for P2
Total 8983


FY 1999 Planned Program:
2462 Continue systems design for P3 baseline
3187 Code, unit test, system test for P3 baseline
996 Conduct DPR for P3 baseline
1171 Complete systems design for P3
1000 P3 software release
1125 Support Limited User Test (LUT)
Total 9941








B. Project Change Summary
FY 1996 FY 1997 FY 1998 FY 1999
FY 1997 President's Budget 12972 18693 9409 10420
Appropriated Value 13368 18229
Adjustments to Appropriated Value -721
FY 1998 Pres Bud Request 12647 18229 8983 9941


C. Other Program Funding Summary FY 1996 FY 1997 FY 1998 FY 1999 FY 2000 FY 2001 FY 2002 FY 2003 To Comp Total Cost
Other Procurement, Army-2, BX0007 12766 9821 10645 10539 4174 0 0 0 47945


D. Schedule Profile FY 1996 FY 1997 FY 1998 FY 1999
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
P0 Software
PDR
CDR
IOT&E Software
DPR *X *X
IOT&E X
P2 Software
DPR X X
FOT&E X
P3 Software
DPR X X
LUT X
P4 Software
DPR X X


*Milestone Completed

A. Project Cost Breakdown FY 1996 FY 1997 FY 1998 FY 1999
Software Development (Contractor) 10784 16221 7251 8124
Contractor Engineering Support 567 439 571 584
Government Engineering Support 1000 923 876 955
Program Management Support 296 201 285 278
SBIR/STTR 445
Total 12647 18229 8983 9941


B. Budget Acquisition History and Planning Information: Not applicable.