FY98 USAF Military Space RDDS

0303110F Def Satellite Comm Sys

COST ($ In Thousands) FY 1996 Actual FY 1997 Estimate FY 1998 Estimate FY 1999 Estimate FY 2000 Estimate FY 2001 Estimate FY 2002 Estimate FY 2003 Estimate Cost to Complete Total Cost
2638 Defense Satellite Communications Sys 33,477 27,279 10,547 17,589 6,872 6,506 3,062 2,304 5,200 634,014
Quantity of RDT&E Articles 0 0 0 0 0 0 0 0 0 0


(U) A. Mission Description and Budget Item Justification

(U) Defense Satellite Communications System (DSCS) is the backbone of the Government's satellite communications system, providing both secure voice and high data rate transmissions in the SHF frequency band. DSCS provides unique and vital national security communications for global command and control, crisis management, relay of intelligence and early warning data, treaty monitoring and surveillance information, and diplomatic traffic. The communications relayed through DSCS support the National Command Authorities, Global Command and Control System, Diplomatic Telecommunications Service, White House Communications Agency, the Navy, the Air Force Satellite Control Network, and ground mobile forces of all services.

(U) This program is in Budget Activity 7, Operational System Development, because DSCS is a production system consisting of a fully operational satellite constellation plus satellites awaiting launch as a part of the operational system. Any enhancement to the satellites not yet launched will be sole source contract awards.

(U) Based on the DoD Space Architect's recommendation, the Service Life Enhancement Program (SLEP) will include additional antenna modifications that increase the capacity of the last four satellites to tactical users by more than 200%. SLEP is on schedule and fully funded.



(U) FY 1996 ($ in Thousands):
(U) $5,477 Continued DSCS mission support activities

- Supported program office operations

- Conducted programmatic tradeoffs and analyses

- Paid performance incentives for development satellites that were still on orbit and operational

(U) $28,000 Start Service Life Enhancement Program (SLEP) modification

- Parts characterization and qualification

- Procured components to develop modifications for first article insertion

- Completed system preliminary design review (PDR) and prepared for system critical design review (CDR)

- Designed low noise amplifier (LNA) upgrade to enhance performance and increase capacity for tactical users

- Designed satellite bandwidth modification to increase capacity level of less capable DSCS satellites to that of satellites B8 - B14

- Began development of modkits for variable gain step attenuator and channel 5 switch to gimbaled dished antenna (GDA)

(U) $33,477 Total


(U) FY 1997 ($ in Thousands):
(U) $4,279 Continue Defense Satellite Communications System (DSCS) mission support activities

- Support program office operations

- Conduct programmatic tradeoffs and analyses

- Pay performance incentives for development satellites that are still on orbit and operational

(U) $23,000 Continue Service Life Enhancement Program (SLEP) modification

- Complete system critical design review (CDR)

- Fabricate and assemble components for first article insertion

- Continue to develop low noise amplifier (LNA) upgrade to enhance performance and increase capacity for tactical users

- Continue to develop satellite bandwidth modification to increase capacity level of less capable DSCS satellites to that of satellites B8 - B14

- Continue to develop modkits for variable gain step attenuator and channel 5 switch to gimbaled dished antenna (GDA)

(U) $27,279 Total


(U) FY 1998 ($ in Thousands):
(U) $3,597 Continue DSCS mission support activities

- Support program office operations

- Conduct programmatic tradeoffs and analyses

- Pay performance incentives for development satellites that are still on orbit and operational

(U) $5,300 Continue SLEP modification

- Conduct final assembly of first article

- Conduct SLEP rework verification test

- Continue to develop LNA upgrade to enhance performance and increase capacity for tactical users

- Continue to develop satellite bandwidth modification to increase capacity level of less capable DSCS satellites to that of satellites B8 - B14

(U) $1,650 - Begin integration development for transition of the last two satellites to Evolved Expendable Launch Vehicles (EELVs)
(U) $10,547 Total


(U) FY 1999 ($ in Thousands):
(U) $5,539 Continue Defense Satellite Communications System (DSCS) mission support activities

- Support program office operations

- Conduct programmatic tradeoffs and analyses

- Pay performance incentives for development satellites that are still on orbit and operational

- Investigate and develop DSCS III performance enhancements

(U) $12,050 - Continue transition development of last two satellites to Evolved Expendable Launch Vehicles (EELVs)
(U) $17,589 Total




(U) B. Program Change Summary ($ in Thousands)



FY 1996


FY 1997


FY 1998


FY 1999
(U) Previous President's Budget 31,077 24,527 10,239 6,130
(U) Appropriated Value 28,127
(U) Adjustments to Appropriated Value
a. Cong Gen Reductions -589
b. SBIR -259
c. Omnibus or Other Above Threshold Reprogram
d. Below Threshold Reprogramming 2,400
(U) Adjustments to Budget Years Since Final FY 1997 PB 308 11,459
(U) Current Budget Submit/President's Budget 33,477 27,279 10,547 17,589


(U) Change Summary Explanation:

Funding: FY98/99 adjustments realign funding with actual program spending requirements.

Schedule: None

Technical: None



(U) C. Other Program Funding Summary ($ in Thousands)


FY 1996


FY 1997


FY 1998


FY 1999


FY 2000


FY 2001


FY 2002


FY 2003
To

Compl

Total

Cost*

(U) Missile Procurement 19,771 28,766** 76,434 29,587 32,080 24,095 28,571 24,433 73,500 1,619,551

* Tracked back to FY76.

** Includes $13.5 million advanced procurement for SLEP.

(U) D. Schedule Profile

FY 1996 FY 1997 FY 1998 FY 1999
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
(U) Launch DSCS/IABS 6 (Oct 97) X
(U) Launch DSCS/IABS 7 (Jul 99) X
(U) Launch DSCS/IABS 8 (May 00)
(U) Launch DSCS/IABS 9 (May 02)
(U) Launch DSCS/IABS 10 (May 03)
(U) SLEP Implementation Study (Mar 95 - Jan 96) X X
(U) SLEP Modification Program (Mar 96 - Aug 00) X X X X X X X X X X X X X X X
(U) SLEP PDR (Sep 96) X
(U) SLEP CDR (Mar 97) X
(U) GTS Upgrade Completion (Oct 96) X
(U) EELV Integration (May 98 - Jan 00) X X X X X X




(U) A. Project Cost Breakdown ($ in Thousands)
FY 1996 FY 1997 FY 1998 FY 1999
(U) Basic Program Activities 5,477 4,279 3,597 5,539
(U) Service Life Enhancement Program (SLEP) 28,000 23,000 5,300
(U) EELV 1,650 12,050
(U) Total 33,477 27,279 10,547 17,589


(U) B. Budget Acquisition History and Planning Information ($ in Thousands)

Performing Organizations:
Contractor or Government Performing Activity Contract Method/Type or Funding Vehicle

Award or Obligation Date


Performing Activity EAC


Project Office

EAC



Total

Prior to

FY 1996*





Budget

FY 1996





Budget

FY 1997





Budget

FY 1998





Budget

FY 1999





Budget to Complete




Total Program
Product Development Organizations
Lockheed Martin FFP/AF Oct 84 437,500 437,500 376,600 29,977 24,579 6,697 2,039 4,044 443,936
Miscellaneous CPAF TBD N/A N/A 124,978 0 0 1,650 12,050 800 139,478


Support and Management Organizations
Aerospace Corp PO Various N/A N/A 11,900 1,000 700 0 0 0 13,600
Miscellaneous Various Various N/A N/A 7,700 2,500 2,000 2,200 3,500 19,100 37,000


Test and Evaluation Organizations
None


* Tracked back to FY86. All other prior year funds included in the Miscellaneous line for Product Development Organizations.



(U) B. Budget Acquisition History and Planning Information Continued ($ in Thousands)

Government Furnished Property:





Item

Description

Contract Method/Type or Funding Vehicle

Award or Obligation Date




Delivery

Date



Total

Prior to

FY 1996





Budget

FY 1996





Budget

FY 1997





Budget

FY 1998





Budget

FY 1999





Budget to Complete




Total Program
Product Development Property
N/A


Support and Management Property
N/A


Test and Evaluation Property
N/A


Subtotal Product Development 501,578 29,977 24,579 8,347 14,089 4,844 583,414
Subtotal Support and Management 19,600 3,500 2,700 2,200 3,500 19,100 50,600
Subtotal Test and Evaluation
Total Project 521,178 33,477 27,279 10,547 17,589 23,944 634,014


THIS PAGE INTENTIONALLY LEFT BLANK