| COST ($ In Thousands) | FY 1996 Actual | FY 1997 Estimate | FY 1998 Estimate | FY 1999 Estimate | FY 2000 Estimate | FY 2001 Estimate | FY 2002 Estimate | FY 2003 Estimate | Cost to Complete | Total Cost | |
| 2638 | Defense Satellite Communications Sys | 33,477 | 27,279 | 10,547 | 17,589 | 6,872 | 6,506 | 3,062 | 2,304 | 5,200 | 634,014 |
| Quantity of RDT&E Articles | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
(U) A. Mission Description and Budget Item Justification
(U) Defense Satellite Communications System (DSCS) is the backbone of the Government's satellite communications system, providing both secure voice and high data
rate transmissions in the SHF frequency band. DSCS provides unique and vital national security communications for global command and control, crisis management, relay
of intelligence and early warning data, treaty monitoring and surveillance information, and diplomatic traffic. The communications relayed through DSCS support the
National Command Authorities, Global Command and Control System, Diplomatic Telecommunications Service, White House Communications Agency, the Navy, the Air
Force Satellite Control Network, and ground mobile forces of all services.
(U) This program is in Budget Activity 7, Operational System Development, because DSCS is a production system consisting of a fully operational satellite constellation
plus satellites awaiting launch as a part of the operational system. Any enhancement to the satellites not yet launched will be sole source contract awards.
(U) Based on the DoD Space Architect's recommendation, the Service Life Enhancement Program (SLEP) will include additional antenna modifications that increase the
capacity of the last four satellites to tactical users by more than 200%. SLEP is on schedule and fully funded.
(U) FY 1996 ($ in Thousands):
| (U) $5,477 | Continued DSCS mission support activities
- Supported program office operations - Conducted programmatic tradeoffs and analyses - Paid performance incentives for development satellites that were still on orbit and operational |
| (U) $28,000 | Start Service Life Enhancement Program (SLEP) modification
- Parts characterization and qualification - Procured components to develop modifications for first article insertion - Completed system preliminary design review (PDR) and prepared for system critical design review (CDR) - Designed low noise amplifier (LNA) upgrade to enhance performance and increase capacity for tactical users - Designed satellite bandwidth modification to increase capacity level of less capable DSCS satellites to that of satellites B8 - B14 - Began development of modkits for variable gain step attenuator and channel 5 switch to gimbaled dished antenna (GDA) |
| (U) $33,477 | Total |
(U) FY 1997 ($ in Thousands):
| (U) $4,279 | Continue Defense Satellite Communications System (DSCS) mission support activities
- Support program office operations - Conduct programmatic tradeoffs and analyses - Pay performance incentives for development satellites that are still on orbit and operational |
| (U) $23,000 | Continue Service Life Enhancement Program (SLEP) modification
- Complete system critical design review (CDR) - Fabricate and assemble components for first article insertion - Continue to develop low noise amplifier (LNA) upgrade to enhance performance and increase capacity for tactical users - Continue to develop satellite bandwidth modification to increase capacity level of less capable DSCS satellites to that of satellites B8 - B14 - Continue to develop modkits for variable gain step attenuator and channel 5 switch to gimbaled dished antenna (GDA) |
| (U) $27,279 | Total |
(U) FY 1998 ($ in Thousands):
| (U) $3,597 | Continue DSCS mission support activities
- Support program office operations - Conduct programmatic tradeoffs and analyses - Pay performance incentives for development satellites that are still on orbit and operational |
| (U) $5,300 | Continue SLEP modification
- Conduct final assembly of first article - Conduct SLEP rework verification test - Continue to develop LNA upgrade to enhance performance and increase capacity for tactical users - Continue to develop satellite bandwidth modification to increase capacity level of less capable DSCS satellites to that of satellites B8 - B14 |
| (U) $1,650 | - Begin integration development for transition of the last two satellites to Evolved Expendable Launch Vehicles (EELVs) |
| (U) $10,547 | Total |
(U) FY 1999 ($ in Thousands):
| (U) $5,539 | Continue Defense Satellite Communications System (DSCS) mission support activities
- Support program office operations - Conduct programmatic tradeoffs and analyses - Pay performance incentives for development satellites that are still on orbit and operational - Investigate and develop DSCS III performance enhancements |
| (U) $12,050 | - Continue transition development of last two satellites to Evolved Expendable Launch Vehicles (EELVs) |
| (U) $17,589 | Total |
(U) B. Program Change Summary ($ in Thousands)
|
FY 1996 |
FY 1997 |
FY 1998 |
FY 1999 | |
| (U) Previous President's Budget | 31,077 | 24,527 | 10,239 | 6,130 |
| (U) Appropriated Value | 28,127 | |||
| (U) Adjustments to Appropriated Value | ||||
| a. Cong Gen Reductions | -589 | |||
| b. SBIR | -259 | |||
| c. Omnibus or Other Above Threshold Reprogram | ||||
| d. Below Threshold Reprogramming | 2,400 | |||
| (U) Adjustments to Budget Years Since Final FY 1997 PB | 308 | 11,459 | ||
| (U) Current Budget Submit/President's Budget | 33,477 | 27,279 | 10,547 | 17,589 |
(U) Change Summary Explanation:
Funding: FY98/99 adjustments realign funding with actual program spending requirements.
Schedule: None
Technical: None
(U) C. Other Program Funding Summary ($ in Thousands)
|
FY 1996 |
FY 1997 |
FY 1998 |
FY 1999 |
FY 2000 |
FY 2001 |
FY 2002 |
FY 2003 |
To
Compl |
Total
Cost* | |
| (U) Missile Procurement | 19,771 | 28,766** | 76,434 | 29,587 | 32,080 | 24,095 | 28,571 | 24,433 | 73,500 | 1,619,551 |
* Tracked back to FY76.
** Includes $13.5 million advanced procurement for SLEP.
(U) D. Schedule Profile
| FY 1996 | FY 1997 | FY 1998 | FY 1999 |
| 1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 | |
| (U) Launch DSCS/IABS 6 (Oct 97) | X | |||||||||||||||
| (U) Launch DSCS/IABS 7 (Jul 99) | X | |||||||||||||||
| (U) Launch DSCS/IABS 8 (May 00) | ||||||||||||||||
| (U) Launch DSCS/IABS 9 (May 02) | ||||||||||||||||
| (U) Launch DSCS/IABS 10 (May 03) | ||||||||||||||||
| (U) SLEP Implementation Study (Mar 95 - Jan 96) | X | X | ||||||||||||||
| (U) SLEP Modification Program (Mar 96 - Aug 00) | X | X | X | X | X | X | X | X | X | X | X | X | X | X | X | |
| (U) SLEP PDR (Sep 96) | X | |||||||||||||||
| (U) SLEP CDR (Mar 97) | X | |||||||||||||||
| (U) GTS Upgrade Completion (Oct 96) | X | |||||||||||||||
| (U) EELV Integration (May 98 - Jan 00) | X | X | X | X | X | X |
(U) A. Project Cost Breakdown ($ in Thousands)
| FY 1996 | FY 1997 | FY 1998 | FY 1999 | |
| (U) Basic Program Activities | 5,477 | 4,279 | 3,597 | 5,539 |
| (U) Service Life Enhancement Program (SLEP) | 28,000 | 23,000 | 5,300 | |
| (U) EELV | 1,650 | 12,050 | ||
| (U) Total | 33,477 | 27,279 | 10,547 | 17,589 |
(U) B. Budget Acquisition History and Planning Information ($ in Thousands)
Performing Organizations:
| Contractor or Government Performing Activity | Contract Method/Type or Funding Vehicle |
Award or Obligation Date |
Performing Activity EAC |
Project Office EAC |
Total Prior to FY 1996* |
Budget FY 1996 |
Budget FY 1997 |
Budget FY 1998 |
Budget FY 1999 |
Budget to Complete |
Total Program |
| Product Development Organizations |
| Lockheed Martin | FFP/AF | Oct 84 | 437,500 | 437,500 | 376,600 | 29,977 | 24,579 | 6,697 | 2,039 | 4,044 | 443,936 |
| Miscellaneous | CPAF | TBD | N/A | N/A | 124,978 | 0 | 0 | 1,650 | 12,050 | 800 | 139,478 |
|
Support and Management Organizations |
| Aerospace Corp | PO | Various | N/A | N/A | 11,900 | 1,000 | 700 | 0 | 0 | 0 | 13,600 |
| Miscellaneous | Various | Various | N/A | N/A | 7,700 | 2,500 | 2,000 | 2,200 | 3,500 | 19,100 | 37,000 |
|
Test and Evaluation Organizations |
| None |
* Tracked back to FY86. All other prior year funds included in the Miscellaneous line for Product Development Organizations.
(U) B. Budget Acquisition History and Planning Information Continued ($ in Thousands)
Government Furnished Property:
|
Item Description |
Contract Method/Type or Funding Vehicle |
Award or Obligation Date |
Delivery Date |
Total Prior to FY 1996 |
Budget FY 1996 |
Budget FY 1997 |
Budget FY 1998 |
Budget FY 1999 |
Budget to Complete |
Total Program |
| Product Development Property |
| N/A |
|
Support and Management Property |
| N/A |
|
Test and Evaluation Property |
| N/A |
| Subtotal Product Development | 501,578 | 29,977 | 24,579 | 8,347 | 14,089 | 4,844 | 583,414 |
| Subtotal Support and Management | 19,600 | 3,500 | 2,700 | 2,200 | 3,500 | 19,100 | 50,600 |
| Subtotal Test and Evaluation | |||||||
| Total Project | 521,178 | 33,477 | 27,279 | 10,547 | 17,589 | 23,944 | 634,014 |