FY98 USAF Military Space RDDS

0305182F Eastern Space Launch Facility (Space)

COST ($ In Thousands) FY 1996 Actual FY 1997 Estimate FY 1998 Estimate FY 1999 Estimate FY 2000 Estimate FY 2001 Estimate FY 2002 Estimate FY 2003 Estimate Cost to Complete Total Cost
4137 Range Standardization and Automation (RSA) Program 47,943 33,956 34,186 33,472 46,974 42,243 40,573 41,481 Continuing Continuing
Quantity of RDT&E Articles 0 0 0 0 0 0 0 0 0 0


(U) A. Mission Description and Budget Item Justification

Two national ranges, the Eastern Range (ER) at Patrick AFB, FL, and the Western Range (WR) at Vandenberg AFB, CA, provide tracking, telemetry, communications, command/control and other support capabilities necessary to safely and successfully conduct civil, commercial, and national security spacelift operations, ballistic missile test and evaluation (T&E), and a variety of aeronautical and guided weapons T&E. Range assets are based on 1950s/1960s designs and technology and are arrayed in a highly inefficient, manpower-intensive architecture. Range instrumentation reliability is deteriorating and over 40% of the components are obsolete with no sources of support. The ranges do not provide the responsiveness and flexibility critical to affordably support the nation's spacelift needs. Replacement of the aging systems is a necessity. Range Standardization and Automation (RSA) will completely overhaul and modernize both the ER and the WR, treating the two as a single integrated range system with an Eastern and Western segment. RSA will develop the integrated range system, using remote control and automation techniques to reduce the number of required operators, sites and facilities, and to produce improved responsiveness. The result will be a range system reconfigurable from one major operation to another in less than 4 hours versus 2-3 days, capable of being operated for 20% less than current ranges, and supportable through existing Air Force logistics infrastructure and standard practices. RSA is critical to the future of the spacelift ranges; performance and cost goals cannot be achieved without RSA. Categorized as Budget Activity 7, Operational Systems Development, because it upgrades existing operational capabilities with new systems. Funding for RSA design and integration for both Eastern and Western Ranges is consolidated in this Eastern Range program element to reflect the standard range being developed for both ranges. A parallel sustaining improvement and modernization activity for existing range systems is separately funded with procurement funds.

(U) FY 1996
(U) $31,178 Continued RSA Phase I Contract: Complete design and begin integration of Cape Canaveral Air Station (CCAS) communications network.
(U) $9,800 Awarded RSA Phase IIA Contract in Nov 95: Initiate range architecture design, including instrumentation, weather, surveillance, Western Range Operations Control Center (WROCC) systems, centralized data processing, and optical systems for both ranges. Contract will continue through 2006.
(U) $2,494 Continued ROCC Engineering Services Contract.
(U) $4,471 Program support includes System Program Office, Air Logistics Center support, and Aerospace support.
(U) $47,943 Total










(U) FY 1997
(U) $8,566 Continue RSA Phase I Contract: Integrate and begin test of communications network.
(U) $20,453 Continue RSA Phase IIA Contract: Complete range architecture design; develop weather, optical instrumentation, Control & Display basic infrastructure, and begin integration and test of first delivery increment.
(U) $4,937 Program support includes System Program Office, Air Logistics Center support, and Aerospace support.
(U) $33,956 Total


(U) FY 1998
(U) $5,993 Continue RSA Phase I Contract: Complete design and begin integration of Consolidated Telemetry Processing System (CTPS).
(U) $22,393 Continue RSA Phase IIA Contract: Continue Control & Display planning and scheduling development; begin development of communications network to an Asynchronous Transfer Mode (ATM) system, including network controllers.
(U) $5,800 Program support includes System Program Office, Air Logistics Center support, Aerospace support, and SATCOM lease.
(U) $34,186 Total


(U) FY 1999
(U) $3,635 Continue RSA Phase I Contract: Finishes integration of CTPS. Completes system test and evaluation.
(U) $21,937 Continue RSA Phase IIA Contract: Continue Control & Display integration and test for operational turnover; continue development of network including network core
(U) $ 7,900 Program support includes System Program Office, Air Logistics Center support, Aerospace support, and SATCOM lease.
(U) $33,472 Total


(U) Acquisition Strategy:

The RSA Phase I Contract was competitively awarded in FY 1993 to provide Consolidated Instrumentation Facilities (CIF) at Antigua and Ascension, satellite communications from these sites to the Eastern Range Operations Control Center, a Central Telemetry Processing System for both ranges, and Cape Canaveral Air Station communications network upgrades. The FY 1996 RSA Phase IIA contract was competitively awarded to provide design and integration of the complete range architecture and also procure a Western Range Operations Control Center; imaging systems; communications systems; mobile metric, telemetry and command assets; surveillance systems; weather data collection and prediction systems; debris tracking systems; planning and scheduling systems and data processing/display systems. An FY 2003 follow-on equipment contract will provide the primary telemetry receiving, metric tracking, and command systems.











(U) B. Program Change Summary ($ in Thousands)


FY 1996


FY 1997


FY 1998


FY 1999

(U) Previous President's Budget 48,279 35,704 36,410 38,466
(U) Appropriated Value 35,704
(U) Adjustments to Appropriated Value
a. Congressional/General -820
b. SBIR -928
c. Omnibus and other Above Threshold
d. Recision -320
e. Below Threshold Reprogramming -16
(U) Adjustments to Budget Years -2, 224 -4,994
(U) Current Budget Submit/President's Budget 47,943 33,956 34,186 33,472


(U) Change Summary Explanation:

Funding: FY 1998/1999 reductions fund higher AF and DoD priorities

Schedule: FY 1998/1999 reductions caused a rephasing of the Range Standardization and Automation (RSA) program deliveries.

Technical: RSA Phase I Contract projected overruns necessitated a restructure of the Consolidated Instrumentation Facilities (CIF) equipment at Antigua and Ascension. Will supply new radar trackers and transmitters to upgrade existing radars in place of the Unified Tracking Antenna (UTA) concept originally planned.

















(U) C. Other Program Funding Summary ($ in Thousands)


FY 1996


FY 1997


FY 1998


FY 1999


FY 2000


FY 2001


FY 2002


FY 2003
To Complete Total

Cost

(U) Other Procurement, AF* 110,447 101,695 81,957 100,938 96,205 102,239 114,955 99,421 Continuing Continuing
(U) MILCON, AF ** 4,000 26,876 30,876


(U) Related RDT&E: Not Applicable.

* In addition to RSA, this PE includes funds required for ongoing Eastern Range sustaining improvement and modernization (I&M) program. Western Range

RSA and I&M is included in PE 35181F. Funding shown is for both PEs.

** FY 1996 and 1998 MILCON funds are in PE 35181F; FY 1996 funds are for Chemical Test and Analysis Laboratory at Vandenberg AFB, and FY 1998 funds are for Western Range Operations Control Center (WR OCC) to house WR OCC RSA systems.

(U) D. Schedule Profile
FY 1996 FY 1997 FY 1998 FY 1999
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
(U) RSA Phase I Prelim Design Review X
(U) Software Maintenance Facility Compl X
(U) RSA Phase IIA Contract Award X
(U) RSA Phase IIA System Reqmt Review X
(U) RSA Phase I Critical Design Review X
(U) RSA Phase IIA System Design Rev X
(U) RSA Phase IIA Integ & Test First Del X
(U) RSA Phase I Developmental T&E X
(U) RSA Phase I Cape FO Network Inst'l X
(U) RSA Phase I SATCOM Installation X
(U) WR Ops Control Cntr MILCON BOD X
(U) RSA Phase IIA Integ & Test 2nd Del X
(U) RSA Phase I Operational T&E X
(U) RSA Phase I System Turnover X




(U) A. Project Cost Breakdown ($ in Thousands)
FY 1996 FY 1997 FY 1998 FY 1999
(U) RSA Phase I Contract 31,178 8,566 5,993 3,635
(U) RSA Phase IIA Contract 9,800 20,453 22,393 21,937
(U) ROCC Engineering Services 2,494
(U) Program Support 4,471 4,937 5,800 7,900
(U) Total 47,943 33,956 34,186 33,472


(U) B. Budget Acquisition History and Planning Information ($ in Thousands)

Performing Organizations:

Contractor or Government Performing Activity Contract Method/Type or Funding Vehicle

Award or Obligat'n Date


Performing Activity EAC


Project Office

EAC



Total

Prior to

FY 1996





Budget

FY 1996





Budget

FY 1997





Budget

FY 1998





Budget

FY 1999





To Complete




Total Program
Product Development Organizations
Harris Corp/

Loral

(RSA Phase I)

C/CPAF Jun 93 88,638 88,638 38,573 31,178 8,566 5,993 3,635 0 87,945
Lockheed Martin

(RSA Phase IIA)

C/CPAF Nov 95 165,000 165,000 0 9,800 20,453 22,393 21,937 88,082 162,665
Harris Corp. (ROCC Eng'r Services) SS/CPAF Apr 94 23,852 23,852 21,358 2,494 0 0 0 0 23,852
Various (Other RSA) Various Various N/A N/A 2,913 0 0 0 0 0 2,913




Support and Management Organizations
Mission Support Various Various N/A N/A 5,550 4,471 4,937 5,800 7,900 Cont. Cont.


Test and Evaluation Organizations
TBD TBD 1998 N/A N/A 0 0 0 0 0 TBD TBD


Government Furnished Property: RSA Phase IIA contract awarded Nov 95; process underway to identify GFE





Subtotal Product Development 62,844 43,472 29,019 28,386 25,572 88,082 277,375
Subtotal Support and Management 5,550 4,471 4,937 5,800 7,900 Cont. Cont
Subtotal Test and Evaluation N/A N/A N/A N/A N/A N/A N/A
Total Project 68,394 47,943 33,956 34,186 33,472 Cont. Cont