FY98 USAF Military Space RDDS

0604479F Milstar LDR/MDR Sat Comm (Space)

COST ($ In Thousands) FY 1996 Actual FY 1997 Estimate FY 1998 Estimate FY 1999 Estimate FY 2000 Estimate FY 2001 Estimate FY 2002 Estimate FY 2003 Estimate Cost to Complete Total Cost
5010 Milstar Sat Comm Sys 533,613 683,685 676,690 555,050 346,425 185,236 84,717 50,948 75,725 9,574,841
Quantity of RDT&E Articles 0 0 0 0 0 0 0 0 0 0

(U) A. Mission Description and Budget Item Justification

Milstar is a joint service program to develop and acquire extremely high frequency (EHF) satellites; a satellite mission control segment; and new or modified Army, Navy, and Air Force communication terminals for survivable, jam-resistant, worldwide, secure communications for the strategic and tactical warfighter in all levels of conflict. Satellites 1 & 2 are Milstar I satellites with a low data rate (LDR) payload only that supports strategic and tactical forces with an emphasis on highly survivable, minimum essential communications. Satellites 3M-6 are Milstar II satellites with both a LDR and a medium data rate (MDR) payload with increased tactical capabilities, including higher data rates to mobile forces and "nulling" that will neutralize close-in enemy jammers. (Satellite 3M was originally a Milstar I satellite, but is being retrofitted with a MDR payload to function as a Milstar II satellite.) This document addresses the space and mission control segments of the Milstar program. This program is in Budget Activity 5, Engineering and Manufacturing Development, based on Defense Acquisition Board and Defense Planning Guidance direction to fabricate and launch Satellites 3M through 6.

(U) FY 1996
(U) $56,900 Milstar I
(U) Launched and performed on-orbit checkout of Satellite 2.
(U) Continued to support on-orbit operations for Satellite 1.
(U) Started Milstar I Phase II IOT&E.
(U) Implemented ECPs as needed based on operational requirement.
(U) Developed and implemented modifications to SMCS to enhance mission control operations.
(U) Continued contractor support for MCS software sustainment for mission planning and satellite operations.
(U) Develop and field operator training equipment.
(U) $427,441 Milstar II
(U) Completed MDR payload manufacturing on Satellite 3M, and started MDR integration and test on Satellite 3M.
(U) Started MDR payload manufacturing for Satellite 4.
(U) Completed bus integration and test for Satellite 3M.
(U) Continued bus component manufacturing for Satellite 4.
(U) Completed LDR integration and test on Satellite 3M, and started LDR integration and test on Satellite 4.
(U) Completed LDR payload manufacturing on Satellite 4.
(U) Continued LDR unit build, MDR payload manufacturing, and bus component manufacturing for Satellites 5 and 6.
(U) Continued Milstar II upgrade of MCS software for mission planning.
(U) $49,272 Other Government Costs
(U) $533,613 Total


(U) FY 1997
(U) $56,400 Milstar I
(U) Continue to support on-orbit operations for Satellites 1 and 2.
(U) Complete Milstar I Phase II IOT&E.
(U) Implement ECPs as needed based on operational requirement.
(U) Continue to implement modifications to MCS to enhance mission control operations.
(U) Transition to organic support for MCS software sustainment for mission planning and satellite operations.
(U) Develop and field operator training equipment.
(U) $578,558 Milstar II
(U) Complete MDR payload manufacturing on Satellite 4, and start MDR integration and test on Satellite 4.
(U) Complete bus component manufacturing on Satellite 4.
(U) Continue LDR integration and test on Satellite 4.
(U) Continue LDR unit build, MDR payload manufacturing, and bus component manufacturing for Satellites 5 and 6.
(U) Complete MDR payload integration and test on Satellite 3M.
(U) Start satellite integration and test on Satellite 3M.
(U) Continue Milstar II upgrade of MCS software for mission planning.
(U) $48,727 Other Government Costs
(U) $683,685 Total


(U) FY 1998
(U) $10,700 Milstar I
(U) Continue to support on-orbit operations for Satellites 1 and 2.
(U) Implement ECPs as needed based on operational requirement.
(U) Continue to implement modifications to MCS to enhance mission control operations.
(U) Develop and field operator training equipment.
(U) $629,894 Milstar II
(U) Complete satellite integration and test on Satellite 3M.
(U) Complete LDR and MDR payload integration and test and start satellite integration and test on Satellite 4.
(U) Complete LDR and MDR payload and bus component manufacturing for Satellite 5.
(U) Start LDR and MDR payload integration and test on Satellite 5.
(U) Continue LDR and MDR payload and bus manufacturing on Satellite 6.
(U) Continue Milstar II upgrade of MCS software for mission planning.
(U) $36,096 Other Government Costs
(U) $676,690 Total

(U) FY 1999
(U) $4,901 Milstar I
(U) Continue to support on-orbit operations for Satellites 1 and 2.
(U) Implement ECPs as needed based on operational requirement.
(U) $514,450 Milstar II
(U) Launch, perform on-orbit checkout, and begin on-orbit testing of Satellite 3M.
(U) Complete satellite integration and test and deliver Satellite 4.
(U) Complete LDR and MDR payload integration and test and start satellite integration and test on Satellite 5.
(U) Continue LDR and MDR payload and bus manufacturing on Satellite 6.
(U) Continue Milstar II upgrade of MCS software for mission planning.
(U) $35,699 Other Government Costs
(U) $555,050 Total




(U) B. Program Change Summary ($ in Thousands)
FY 1996 FY 1997 FY 1998 FY 1999
(U) Previous President's Budget 541,869 700,278 672,577 580,005
(U) Appropriated Value 720,278
(U) Adjustments to Appropriated Value
a. Congressional General Reductions -16,413
b. SBIR -20,180
c. Omnibus and Other Above Threshold Reprogramming -4,618
d. Below Threshold Reprogramming -3,638
(U) Adjustments to Budget Years Since FY97 PB 0 4,113 -24,955
(U) Current PB Submit 533,613 683,685* 676,690 555,050


* Does not reflect -$400,000 Below Threshold Reprogramming (BTR) for Joint Program Office Deskbook and -$1,000,000 BTR for Modified Miniature Receive Terminals (MMRT) on the bomber forces.

(U) Change Summary Explanation:

Funding: FY96 appropriated value represents implementation of the special termination cost clause on the Milstar contract. FY 97-98 adjustments reflect restoral of the original Automated Communications Management System (ACMS) program schedule. FY 99 decrease reflects the reduction in contractor oversight and system engineering support.

Schedule: See ACMS funding explanation.

Technical: None.

(U) C. Other Program Funding Summary ($ in Thousands)
FY 1996 FY 1997 FY 1998 FY 1999 FY 2000 FY 2001 FY 2002 FY 2003 To Comp Total
(U) Milstar AF Command Post Terminals* 20,970 8,240 6,579 6,899 3,237 2,034 5,648 5,079 Cont TBD

* Funding is maintained in PE 33601F as Other Procurement for the AF-developed ground and airborne Command Post Terminals of the Milstar program. PE 33601F includes additional funding and appropriations for other AF MILSATCOM terminals.

(U) Related RDT&E:

(U) PE #303601F, MILSATCOM Terminals

(U) PE #603430F, Advanced MILSATCOM

(U) PE #604577N, EHF Satellite Communications

(U) PE#603432F, Polar Satellite Communications Program (Polar Adjunct)

(U) D. Schedule Profile

FY 1996 FY 1997 FY 1998 FY 1999
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
(U) Milstar I (LDR Only)
(U) Satellite 2 Launch x
(U) IOC I x
(U) Start LDR IOT&E, Phase II x
(U) Complete LDR IOT&E, Phase II x
(U) Milstar II (LDR/MDR)
(U) Satellite 3M Launch x
(U) Satellite 4 Launch - 1QFY00
(U) MDR IOT&E - 2QFY00
(U) IOC II - 1QFY01
(U) Satellite 5 Launch - 1QFY01
(U) Satellite 6 Launch - 1QFY02
(U) FOC - 1QFY05


(U) A. Project Cost Breakdown ($ in Thousands)
FY 1996 FY 1997 FY 1998 FY 1999
(U) Satellites 1/2/3L 56,900 56,400 10,700 4,901
(U) Satellite 3M 99,366 92,759 98,938 82,534
(U) Satellite 4 215,170 231,705 235,652 150,586
(U) Satellite 5 81,082 147,361 154,020 133,605
(U) Satellite 6 31,823 106,733 141,284 147,725
(U) Other Government Costs 49,272 48,727 36,096 35,699
(U) Total 533,613 683,685 676,690 555,050


(U) B. Budget Acquisition History and Planning Information ($ in Thousands)

Performing Organizations:

Contractor or Government Performing Activity Contract Method/Type or Funding Vehicle

Award or Obligation Date


Performing Activity EAC


Project Office

EAC



Total

Prior to

FY 1996





Budget

FY 1996





Budget

FY 1997





Budget

FY 1998





Budget

FY 1999





Budget to Complete




Total Program
Product Development Organizations
LMSC (Milstar I)

[Sats 1,2,3L]

C/CPAF Jun 83 2,181,587* 2,181,587* 4,670,852 56,900 56,400 10,700 4,901 1,899 4,801,652
LMSC (Milstar II)

[Sats 3M, 4, 5, 6]

SS/CPAF Oct 92/

Nov 94

3,355,600 3,355,600 1,240,954 427,441 578,558 629,894 514,450 561,163 3,952,460




Support and Management Organizations
Aerospace SS/CPFF/AF Various 97,436 15,334 13,930 13,945 13,414 70,202 224,261
LINCOM SS/CPAF Various 13,999 4,693 3,743 2,824 1,000 2,001 28,260
Lincoln Lab SS/MIPR Various 17,785 2,704 4,203 3,098 2,968 2,968 33,726
Ogden SS/MIPR Various 7,055 1,510 1,704 1,659 1,808 14,243 27,979
Logicon SS/CPFF Various 7,597 757 779 802 826 11,527 22,288
ANSER CPFF Feb 91 3,540 1,109 966 0 0 0 5,615
Miscellaneous 323,534 23,165 23,402 13,768 15,683 79,047 478,599


Test and Evaluation Organizations
None.


Government Furnished Property:

Product Development Property
None.


Support and Management Property
None.


Test and Evaluation Property
None.


Subtotal Product Development 5,911,806 484,341 634,958 640,594 519,351 563,062 8,754,112
Subtotal Support and Management 470,946 49,272 48,727 36,096 35,699 179,988 820,728
Subtotal Test and Evaluation
Total Project 6,382,752 533,613 683,685 676,690 555,050 743,051 9,574,841


Note: Due to the overrun on the Milstar I contract, an Over Target Baseline (OTB) was established in Jan 91 to provide a credible cost performance baseline for the remaining contractual effort. The EAC reflects the unclassified cost of remaining work scheduled after the Jan 91 rebaseline. The total program value includes all unclassified prior funding (approx $4B in FY82 - 92), all unclassified fees & incentives, and ECPs not yet definitized.