Chapter 2 - Alternatives Including the Proposed Action
DRAFT ENVIRONMENTAL IMPACT STATEMENT (DEIS)
FOR THE
EVOLVED EXPENDABLE LAUNCH VEHICLE (EELV) PROGRAM
April 1998
2.1.2 Concept B
Under Concept B, the contractor would use SLC-37 at Cape Canaveral AS
and SLC-6 at Vandenberg AFB for EELV system activities, as well as other
facilities at both locations.
The following is a general description of the launch vehicle and facility
requirements for Concept B. Specific descriptions for implementation of this
alternative at Cape Canaveral AS and Vandenberg AFB follow the general
description. Construction would include modifications to existing facilities and
construction of new facilities. Most of the components (boosters, upper
stages, and avionics modules) would be assembled and tested prior to
shipment to the launch site (i.e., Cape Canaveral AS or Vandenberg AFB) in
near flightworthy condition.
2.1.2.1 Launch Vehicle Concept.
The EELV would consist of several
variations of a Delta IVB (DIV) launch vehicle, including small (DIV-S), medium
(DIV-M), and large (heavy) (DIV-H) launch vehicles, shown in Figure 2.1-8.
This system would use a common booster core (CBC), with a Hypergolic
Upper Stage (HUS), Delta Cryogenic Upper Stage (DCUS), or Heavy Delta
Cryogenic Upper Stage (HDCUS) as second stages, depending upon the
payload requirements. The small and medium vehicles would use one CBC
first-stage core booster; the heavy vehicle would use one first-stage CBC and
two CBC strap-ons. The strap-ons are the standard version of the CBC with
Titan IV nose cones and appropriate separation hardware added. They have
shorter burn times than the center core and would be jettisoned prior to
burnout of the center core vehicle. A Delta IVB Medium Plus (DIV-M+)
vehicle, consisting of a DIV-M with solid rocket motors (SRMs), would be
utilized for some commercial missions (not shown in Figure 2.1-8). The SRM
booster casing would be composed of graphite epoxy. Table 2.1-6 provides
data for the launch vehicle components.
The medium and heavy upper stages would be fueled by LH2 and LO2, and
the small vehicle upper stages would utilize Aerozine-50 (A-50) and N2O4. All
propellant transfer would occur on the launch pad.
The CBC is a new design for the EELV program using a Rocketdyne RS-68
engine and would be a common element for all Concept B launch vehicles.
The CBC casing would be composed of aluminum alloy and composite
structures. The CBC propellants are LH2 and LO2.
The HUS would be designed to satisfy the low end of the NMM in terms of
payload delivery to orbit and would be used on the DIV-S only. The DCUS
would be used for the DIV-M, and the HDCUS would be used for the DIV-H.
The DIV-S and the DIV-M both satisfy the medium lift requirement of the
NMM.
For some small vehicle missions, a third stage (Star 48B) containing solid
propellant would be utilized. The propellant would be composed of
ammonium perchlorate (NH4ClO4), aluminum (Al), and hydroxyl-terminated
polybutadiene (HTPB) (binder material). The third stage would be
encapsulated with the payload and transported to the launch pad.
For the medium and heavy vehicles, fueling of the reaction control system
(RCS) would occur in the payload processing facility. The RCS propellant
would be anhydrous hydrazine (N2H4) and helium (He).
The payload fairings would be developed from existing Delta and Titan IV
designs. The fairing structures for the DIV-H would be made of aluminum;
small and medium vehicle payload fairings would be a graphite-epoxy
composite.
The CBC avionics’ basic architecture and all elements would be developed
from Delta II/III avionics that provide single-fault tolerant control that monitors
electrical power for all critical functions. The upper-stage avionics provide the
inertial sensing and data processing for the navigation, guidance, control,
and sequencing; radio frequency (RF) communication electronics; flight
termination; and the telemetry, power, and distribution network.
The FTS would be a redundant system that would provide the capability to
terminate a vehicle undergoing erratic flight before it could endanger people
and property. The system for Concept B would rely upon existing
technologies that have been used for the Titan, Delta, and space shuttle
programs.
Figure 2.1-2 depicts a representative launch vehicle ascent sequence. After
completing its mission, the CBC would fall into the ocean and would not be
recovered. Less than 25 gallons of hydraulic fluid would remain in the
booster when it falls into the ocean and sinks. The payload fairings would
separate from the vehicle prior to orbit, fall into the ocean, and would not be
recovered. The upper-stage engine would cut off when the payload reached
the desired orbit. The upper stages (HUS, DCUS, and HDCUS) of the launch
vehicle would boost the payload into orbit, where the upper stage would
separate from the payload. Residual propellant within the upper stages
would be vented to minimize orbital debris due to breakup.
2.1.2.2 Primary Support Structures.
Various support structures and
equipment would be necessary to process and launch the vehicle. These
would consist of structures at the proposed SLC (i.e., SLC-37 or SLC-6), as
well as facilities and utilities located elsewhere on the launch site. The
primary support structures and equipment that would be required at both
Cape Canaveral AS and Vandenberg AFB are described in the following
paragraphs. Exact facility locations at each launch site are described for
Cape Canaveral AS in Section 2.1.2.6 and for Vandenberg AFB in
Section 2.1.2.9.
Unloading Facilities. Barge/boat unloading facilities at each location would
be used to unload CBCs transported by barge or boat. Airstrips at each
location would be utilized to unload flight hardware transported by cargo
aircraft. Hardware transported by truck would be received at appropriate
processing facilities or interim storage facilities.
Storage Facilities. CBCs, upper stages, fairings, and other flight hardware
may be stored in these facilities, if necessary, prior to processing. These
facilities would also be utilized to store ground support equipment (GSE).
Horizontal Integration Facility (HIF). An HIF would be utilized for vehicle
processing. Functions performed in the HIF would include the receiving,
integration of CBCs and strap-ons for the DIV-H, and check-out of the CBC
and upper stages. In addition, this facility would house many support
functions required for integration of the launch vehicle.
Payload Processing Facility. Preprocessed and fueled payloads would be
encapsulated within this facility. The Star 48B would be integrated with the
payload and encapsulated. The payload would be inspected, any final
assembly and checkout conducted, and if required, storable propellant (N2H4)
loaded. Encapsulation of the payload within the fairing would be the final
operation prior to transport to the launch pad.
Launch Complex. The launch complex would include the launch table and
installation/interface points for various support services. It would also contain
launch exhaust ducts that direct the exhaust flame from the launch vehicle
away from the launch deck and complex for safe dispersal. The launch pad
would include an MST, a Fixed Umbilical Tower (FUT), and an SEB that would
provide miscellaneous support systems that need to be close to the launch
pad, as well as propellant and gas storage areas.
Launch Control Center. Launches would be controlled at the launch control
center once SLC operations/procedures had been completed.
Propellant and Gas Holding Areas. Propellant and gas holding areas would
include a gas storage area and LH2 and LO2 holding areas at the SLC. An
LH2 system, consisting of a double-walled tank; a leak detection system; and
a piping system would be used for CBC, DCUS, and HDCUS fueling. This
would include an 850,000-gallon tank at Cape Canaveral AS and an
850,000-gallon tank at Vandenberg AFB. This area would also include an
unloading area, a piping system, a sloped spill runoff area, a propane flare
stack, a hydrogen burn stack to burn excess vapor, a fire suppression system,
power, and instrumentation. Piping to the launch pad would be installed. In
addition, an LO2 system consisting of a double-walled tank, pumps, and a
piping system would be required for CBC, DCUS, and HDCUS loading.
Facilities would include a 250,000-gallon tank at Cape Canaveral AS and a
300,000-gallon tank at Vandenberg AFB. An unloading area, an LH2 leak
detection system, and a piping system would also be required. At
Vandenberg AFB, an existing berm that slopes to an existing containment
area would be utilized for secondary containment. At Cape Canaveral AS, a
containment system would be designed in accordance with Range Safety and
OSHA requirements. The earthen berm containment areas would
accommodate 100 percent of the liquid volume because of the rapid
volatilization of any potential spills.
The gas storage area would include storage and handling facilities for GHe
and liquid nitrogen (LN2). At both Cape Canaveral AS and Vandenberg AFB,
one 20,000-gallon tank of LN2 and four 300-cubic-foot vessels of GHe would
be required. GN2 would also be provided to the launch facilities via existing
pipelines. Additional piping would be installed, as required. Two additional
GN2 truck connections would be required at Cape Canaveral AS.
A-50 and N2O4 for the HUS would be transported to the site by DOT-approved
supply tankers following procedures similar to those used currently for the
Delta II program. These chemicals would not be stored on site. The loading
area would include secondary containment and a leak detection system.
Mobile scrubbers and a bubble overflow scrubber on the FUT would require
air permits similar to those required for current Delta II operations.
Small quantities of MMH required for the DCUS would be provided in DoD-approved
drums. It has not yet been determined whether air permits for
scrubbers would be required; because of the small amounts of MMH used,
permits may not be required. Hypergolic rinseate would be managed and
disposed of in accordance with applicable federal, state, and installation
requirements.
Solid propellant would not be stored in the launch pad area. Existing solid
propellant storage facilities would be utilized at each launch location. At
Cape Canaveral AS, solid propellant would be stored in a new Delta III
building within Area 57E to be constructed in 1998, and within portions of
Buildings 50801 and 50803. At Vandenberg AFB, solid propellant would be
stored in Building 1670.
2.1.2.3 Launch Site Operations.
The launch vehicle components would be
shipped separately to each launch site (i.e., Cape Canaveral AS or
Vandenberg AFB). Upon arrival, the components would undergo a variety of
receiving inspections and off-line processing in the facilities noted above
before final integration on the launch pad. Figure 2.1-9 provides an overview
of the Concept B launch operation concept.
Launch process operations that would occur at the launch site include launch
preparation, launch operations, and post-launch refurbishment of the launch
pad. Table 2.1-7 lists the types and total estimated quantities of hazardous
materials used for these processes for each Concept B launch. All hazardous
materials used would be handled in accordance with applicable federal, state,
and local regulations. Any spill of these materials would be collected and
disposed of by a certified subcontractor in accordance with the SPCC plan.
Vehicle Receiving/Inspection. The major transportation methods for this
concept would include barge/boat, air, and truck. The CBCs, CBC/interstage,
and CBC strap-ons would be shipped to the launch site by barge/boat and
received at the barge unloading facilities. Upon arrival, the CBCs would be
moved to the HIF or an interim storage facility. Some of the payload fairings
would be transported to the launch site via aircraft and received at the airstrip;
the upper stage and the remainder of the payload fairings would be
transported by truck.
Once at the launch site, the payload fairings would be transported to the
payload encapsulation facility. The HUS, CUS, and HDCUS would be
transported to the HIF or an interim storage facility. Items received would be
inspected and prepared for integration/encapsulation at designated facilities.
Liquid propellant for the launch vehicle would be shipped directly from the
manufacturing location. All propellant would be shipped in accordance with
DOT regulations in Title 49 CFR Parts 100-199. LO2 and LH2 would be
transported by truck and would be shipped from the manufacturing locations
to the launch site. After the Directorate of Aerospace Fuels Management,
located at Kelly AFB, Texas, approves the shipment of N2O4, it would be
shipped by rail or truck from the manufacturing location to the launch site.
MMH and A-50 would be transported via truck by one of the authorized
shippers (Directorate of Aerospace Fuels Management or NASA) to the
launch site. Solid rocket motors could be shipped by truck, rail, barge, or
aircraft.
Horizontal Integration Facility Processing. Receiving, integration, and
check-out of the CBC and upper stages would be performed in the HIF.
When the launch vehicle is ready, it would be transported to the launch pad.
Payload Encapsulation. This process would involve encapsulating the
payload within the payload fairing, which would entail mating the payload-attach
fittings, payload, and fairing, and conducting automated tests to
ensure that all interfaces are verified. The third stage would be encapsulated
with the payload, if required, for some small vehicle missions. Fueling of the payload
would be conducted prior to encapsulation in payload processing.
Launch Vehicle Transfer and Erection. During this process, the unfueled
launch vehicle would be moved to the launch pad from the HIF and erected.
The assembled launch vehicle and umbilicals would then be raised and
connected to the launch table.
Launch Pad Processing. The launch pad processing for all three vehicles
would be similar, with the exception of the propellant servicing of the upper
stages and attitude control systems. The vehicle would be erected and the
launch mount unit secured to the launch table. The MST/mobile assembly
shelter (MAS) (at Vandenberg AFB only) would be moved over the pad, and
access platforms would be lowered or rotated in place to gain access to
critical vehicle points. Interfaces at the pad include electrical, engine purge
lines, GHe purge lines, ground equipment purge lines, LO2 and LH2 fill and
drain lines, and vent lines, as applicable. The encapsulated payload would
be hoisted by the MST crane and positioned over the upper stage.
Upon completion of final vehicle preparations for launch, the MST/MAS would
be moved into the launch position, and final countdown would commence.
The vehicle would undergo a final "hold fire" test to ensure range safe
operation, followed by fueling of the vehicle stages. The final countdown
would then be completed and the vehicle launched.
If deluge water were required, approximately 200,000 to 300,000 gallons of
water per launch would be sprayed into the flame deflector to cool the rocket
exhaust and minimize damage to the launch pad. At Cape Canaveral AS,
deluge water remaining in the launch duct after launch would be released to
grade in accordance with permit requirements. Pretreated deluge water that
could not be released to grade would be released to the WWTP. At
Vandenberg AFB, water would be transported to the SLC-6 deluge treatment
plant for treatment and disposal into evaporation ponds. Wastewater would
be disposed of in accordance with applicable federal, state, and local
regulations.
Approximately 30,000 gallons of water would be required for pad wash- down
after DIV-M+ vehicle launches. This water would be neutralized and disposed
of according to installation requirements.
Flight Support Operations. Flight operations after launch include the
downlinking of composite vehicle performance and system payload telemetry
data to the NASA TDRSS. These data would be routed to recording stations,
as required for processing, data archiving, analysis, and monitoring by launch
team personnel. Pre- and post-launch telemetry data would be used to
perform event reconstruction, trend analysis, and vehicle performance
evaluation. Flight support operations also include range safety control
throughout all phases of the mission.
Post Launch Operations. This process would include pad refurbishment in
preparation for the next launch. Following launch, some of the components
would require sandblasting and repainting; ablative material would be applied
on some areas.
Small leaks and spills could occur during fueling, as could other hazardous
material spills. These materials would be cleaned up, if necessary, by dilution
with water, absorption or adsorption by the appropriate materials, and
collection of the waste materials into DOT-approved waste containers for
disposal. Collected wastewater would be disposed of in accordance with
applicable federal, state, and local regulations.
If a launch were to be canceled or delayed beyond the launch window, it
would be necessary to defuel the launch vehicle in accordance with EWR
127-1 requirements. Defueling is accomplished through pneumatic-activated
valves that allow propellant to drain to ground/mobile storage containers.
Electrically activated valves would allow high-pressure helium to vent to the
atmosphere.
2.1.2.4 Safety Systems.
Concept B would be subject to the same rules and
policies described in Section 2.1.1.4 for Concept A. Systems with aspects
unique to Concept B are described below.
Fire Protection System. Fire protection, alarm, and fire suppression systems
would be provided for all fuel (A-50, LH2, N2H4) holding areas and support
facilities. Gas (H2) detectors, detecting the lower explosive limit in the LH2
storage area, would activate the alarms to the Air Force Fire Department.
Flame detection alarms would also automatically activate deluge systems and
notify the Fire Department. At Cape Canaveral AS, fire suppression water
would be obtained through an existing 10-inch potable water line; a fire
suppression water tank (144,000-gallon minimum) and pumps would likely be
required. At Vandenberg AFB, an existing tank above the launch complex
would be utilized for fire suppression water. All launch pads at both locations
would require installation of an underground fire suppression water loop
encircling the site. This loop would contain approximately 15 hydrants; the
total anticipated fire suppression water flow would be 1,500 to 2,000 gallons
per minute (gpm). For oxidizer fueling performed by truck, a deluge system
would not be included because N2O4 and water are highly reactive.
Flushdown hoses, however, would be available.
Security. Security requirements, an integral component of project safety,
would be incorporated within the project design and through operational
procedures. Elements of site security would include a perimeter security
fence, a clear zone, security lighting, security standby power, an intrusion
detection system, and security patrol roads. Security procedures include the
use of entry controllers, alarm monitors, closed circuit television (CCTV),
alarm/security response teams, radios, and vehicles in accordance with Air
Force regulations.
Launch Hazard Area Safety. The procedures for launch safety would be the
same for Concept B as described for Concept A, except for the number of
beach closures at Vandenberg AFB. Jalama Beach County Park would be
closed to the public during some SLC-6 launches, depending on the launch
azimuth. Ocean Beach County Park would not be closed during launches
from SLC-6.
Quantity-Distance Criteria. The facilities associated with Concept B would
be sited to meet ESQD criteria.
2.1.2.5 Project Location and Access - Cape Canaveral AS.
EELV launch
operations would be conducted at the 120-acre SLC-37 (Pads 37A and 37B)
at Cape Canaveral AS, in the north-central portion of the station. SLC-37
was originally used for the Apollo Program. The only remaining structures at
SLC-37 are concrete support equipment buildings that served as bases for
the two launch pad umbilical towers, the former launch control center,
miscellaneous retaining walls, and the concrete pad/refractory brick pad
areas.
Cape Canaveral AS is accessible through Gate 1 from SR 401 (Figure
2.1-10). Once on Cape Canaveral AS, access to the site is along Samuel C.
Phillips Parkway to Beach Road, which connects to SLC-37.
2.1.2.6 Support Structures/Operations - Cape Canaveral AS.
Launch
rates associated with Concept B are provided in Table 2.1-8. Approximately
540 personnel are expected to be required to support EELV program
operations by 2007. Launch operations for Cape Canaveral AS would be as
described in Section 2.1.2.3 and would be conducted in the structures listed
in Table 2.1-9. Figures 2.1-10 and 2.1-11 provide the general location of
facilities at Cape Canaveral AS and the site layout plan for SLC-37,
respectively. Most of the area would be utilized for launch operations.
Under Concept B, the projected activities associated with EELV would
generate the following average utility demands at Cape Canaveral AS during
the projected peak launch year (2015):
- Water - 24,400 gpd
- Wastewater - 24,300 gpd
- Solid waste - 1.1 tons per day
- Electricity - 96,200 kWH per day.
Based upon employment projections and project activities, Concept B would
generate an average of 1,730 vehicle trips daily, with 360 trips expected to
occur during the peak hour.
2.1.2.7 Project Construction Activities - Cape Canaveral AS.
Construction
at Cape Canaveral AS would begin after Engineering and Manufacturing
Development (EMD) award (June 1998) and would be completed by
July 2000. Construction personnel requirements would average 220, with a
maximum of 405 personnel required during peak construction activities in
June 1999. Proposed construction activities at Cape Canaveral AS are
described below.
Existing Facility Modification
At SLC-37, launches are planned from both Pads 37A and 37B.
Modifications required to support EELV activities would include the following
(see Figure 2.1-11):
Pad 37A
- The existing roads would be modified.
- A launch pad would be constructed at the previous location of the
existing Pad 37A. An FUT and MST would be constructed on the
pad, which would be raised above the location of the previous
pad to accommodate the exhaust duct and provide a level area
for the MST. Support and tie-downs for the MST and the FUT
would be provided on the pad.
- Facility 33006 (former Utility Building) would be modified for use as
the SEB. A fire detection and suppression system would be
installed.
- A modular security building with parking spaces would be
constructed.
- Lightning protection towers would be constructed.
- A launch table containing the interfaces to the vehicle from the
ground support systems would be constructed to support the
vehicle prior to launch.
- A launch support structure connected to the SEB by a service
tunnel would be constructed to support the launch table and
MST. A fire detection and suppression system would be installed.
- A flame detector and exhaust duct would be installed.
- A Theodolite Building and an MST would be constructed.
- Buildings 33001, 33003, 33007, 33009, 38320, 43401, 43403,
and 43405 are inactive, and would be abandoned in place.
Pad 37B
- The existing roads would be modified.
- The launch pad area would be modified, including removal of
approximately 32,000 square feet of refractory brick that may
contain asbestos and silica. Portions of the roads within SLC-37
would be new.
- A 250,000-gallon LO2 tank would be installed within a gas storage
area.
- An 850,000-gallon LH2 tank would be installed.
- The existing SEB (Facility 33002) would be renovated, and a
Theodolite Building, lightning protection towers, a guardhouse, a
security fence between the Pad 37A and 37B areas, an MST, a
launch table, and exhaust and launch ducts would be
constructed.
- A launch support structure deck would be installed to provide
rooms and passageways under the launch deck for umbilicals and
services.
- The Common Support Building (CSB) (Facility 33000) would be
modified.
- The existing Sentry House (Facility 33005) would be removed.
- A guardhouse would be installed at the entrance of the SLC.
- Chain-link security fence would be installed around the SLC
between SLC-37A and SLC-37B.
- A pipeline and lift station would be installed to transfer wastewater
to the Cape Canaveral AS WWTP.
- A GHe vaporization system and pipeline tie-in would be installed
at SLC-37.
- A compressed GN2 pipeline would be installed to connect the new
gas storage area to the Cape Canaveral AS commercial line at
Samuel C. Phillips Parkway. The underground portion of the line
that ties into the existing line northeast of Building 43400 and
runs along Beach Road to the SLC-37 gas storage area would be
carbon steel; the aboveground piping at the gas storage area
would be stainless steel. The carbon steel underground line
would have cathodic protection.
Port of Canaveral Dock. A dock at the Port of Canaveral would be used for
EELV program activities. Any additional required road or facility improvements
would be the responsibility of the Port of Canaveral.
Building 1348 (Hangar C). This building would be used for GSE storage.
Upgrades to Hangar C would include interior asbestos and lead-based paint
abatement, minor interior modifications, and construction of new entrances.
Additional storage space (approximately 20,000 square feet) would be
required on Cape Canaveral AS; available facility space has not yet been
identified.
Building 75251, Missile Inert Storage (MIS). This building would be used for
hardware storage. Upgrades to Building 75251 would include interior and
exterior modifications and installation of new doors.
Buildings 33008 and 43400. These buildings would be used for storage.
Modifications to Buildings 33008 and 43400 would be required to support
EELV program activities. The extent of modifications required has not yet
been determined.
Buildings 38800, 38804, 38835, Centaur Processing Facility. These
facilities would be used for storage of fairings and upper stages, as well as
other support activities. Interior modifications to these buildings would be
required. The launch control area within Building 38835 would be modified.
Building 43400. A portion of this building would be utilized as a machine
shop. Interior modifications would be required.
Area 57E. Portions of existing Buildings 50801 and 50803, and a new
building scheduled for construction for the Delta III program, all within Area
57E, would be utilized for storage and processing.
Infrastructure. New wastewater, electrical, and water lines would be installed
(see Figure 2.1-11). Some improvements would be made along existing road
corridors; new wastewater and electrical lines may be installed through
undisturbed areas between SLC-37 and Samuel C. Phillips Parkway.
New Facilities
Horizontal Integration Facility. An HIF would be constructed near SLC-37
on the south side of Beach Road (see Figure 2.1-11). The facility would be of
a hangar-like configuration, with a parking lot in front. A fire detection system
and sprinkler system would be installed. An estimated 14 acres would be
disturbed for construction of the HIF.
Electric Substation. An electrical substation and associated connections
would be constructed in the vicinity of Patrol Road and Samuel C. Phillips
Parkway, at the area of Building 43302 (which would be removed). All
electrical lines would be run underground.
Alternative Facilities
Two alternative facilities have been identified at Cape Canaveral AS for
Concept B activities, in the event that the preferred locations are not available
in the time period required to support the EELV program. These facilities are
described below.
Horizontal Integration Facility. An alternate location for construction of the
HIF is adjacent to the CPF Complex (Buildings 38800/38804/38805).
U.S. Air Force Roll-On/Roll-Off Dock. If the Port of Canaveral Dock is not
available to support EELV, the existing Air Force Roll-On/Roll-Off Dock would
be modified. Limited dredging activities may be required in previously
dredged areas. The dock would be modified to accommodate the turning
radius of the transport vehicle/dolly in the egress area.
Construction Phase
The majority of new construction, except for construction of the HIF, would
occur within the previously disturbed SLC-37 area or along existing road
corridors. The entire area of SLC-37 inside the new security fence would be
cleared of vegetation (approximately 25 to 30 acres for Pad 37A and 55
acres for Pad 37B). Construction equipment laydown areas, personal vehicle
parking, temporary mobile offices (trailers), maintenance facilities, and other
ancillary construction areas would be sited in previously disturbed areas (see
Figure 2.1-11). The construction laydown areas would be located between
Pads 37A and 37B.
Earthwork for construction would be performed in accordance with the
construction Storm Water Pollution Prevention Plan and the SPCC plan.
To contain collected wastewater, a temporary truck washdown area with an
impoundment would be provided within the boundaries of the construction
laydown areas.
Approximately 80 acres of land, including the area for construction of the HIF
and electric substation, would be disturbed during construction. Depending
upon the final design and grading plans, 5,000 to 9,000 cubic yards of
material would be excavated and 110,000 to 180,000 cubic yards of fill would
be required. Fill material would come from borrow areas located off station.
Unsuitable cut material would be removed from the project area to a spoil site
on Cape Canaveral AS, or to other approved locations. Appropriate erosion
control would be implemented at the stockpile. Construction materials
generally would be trucked through Gate 1 over Samuel C. Phillips Parkway
to SLC-37.
During the construction period, approximately 3,300 gpd of water would be
required for general activities (e.g., site washdown, cement mixing, personnel
requirements). Wastewater generation would average approximately
2,000 gpd. In addition, approximately 5,000 to 8,000 tons of solid waste
would be generated, of which an estimated 3 to 5 percent would be recycled.
Removal of construction debris would be the responsibility of the construction
contractor; any hazardous materials found during construction (e.g.,
asbestos, lead-based paint) would be abated in accordance with applicable
regulations.
From 1998 through 2000, construction traffic entering and exiting project
construction sites on Cape Canaveral AS under Concept B is estimated to
generate an average of 1,400 daily vehicle trips, with 150 trips expected
during the peak hour. Construction traffic entering and exiting project
construction sites during the peak construction period in June 1999 is
expected to be 2,550 trips, with 270 trips occurring during the peak hour.
2.1.2.8 Project Location and Access - Vandenberg AFB.
EELV launch
operations would be conducted at the 100-acre SLC-6 at South Vandenberg
AFB. The SLC-6 site was originally constructed in 1970 for the Titan IIIM
manned launch vehicle that was to be used for the Manned Orbital
Laboratory (MOL) program. After the MOL program was cancelled, SLC-6
was modified for the space shuttle program, but was never used for this
program. Most of the facilities are currently in mothball status.
Some of the other facilities are currently being used by the California
Commercial Spaceport and a launch contractor.
Access to the SLC would be primarily through the Vandenberg AFB South
Gate entrance via SR 246, then over Air Force-controlled secondary
roadways, including Arguello Boulevard, and Bear Creek and Coast roads
(Figure 2.1-12).
2.1.2.9 Support Structures/Operations - Vandenberg AFB. Launch rates
associated with Concept B are provided in Table 2.1-8. Approximately 400
personnel are expected to be required to support EELV launch operations by
2007. Launch site operations would be as described in Section 2.1.2.3 and
would occur in the structures listed in Table 2.1-10. Figures 2.1-12 and
2.1-13 provide the general location of facilities at Vandenberg AFB and the
site layout plan for SLC-6, respectively. Most of the SLC-6 area would be
utilized for launch operations.
Under Concept B, the projected activities associated with EELV would
generate the following average utility demands at Vandenberg AFB during
the projected peak launch year (2007):
- Water - 18,100 gpd
- Wastewater - 18,000 gpd
- Solid waste - 0.8 ton per day
- Electricity - 89,500 kWH per day.
Based upon employment projections and project activities, Concept B would
generate an average of 1,280 vehicle trips daily, with 270 trips occurring
during the peak hour.
2.1.2.10 Project Construction Activities - Vandenberg AFB.
At
Vandenberg AFB, construction would begin after EMD award (June 1998)
and would be completed by February 2001. Construction personnel
requirements would average 173, with a maximum of 350 personnel required
during peak construction activities between January and March 2000.
Proposed construction activities at Vandenberg AFB are described below.
Existing Facility Modification
SLC-6. The MST, bridge cranes, launch mount and exhaust ducts, and LO2
and LH2 storage areas would be modified. Other modifications would include:
- A launch table and FUT would be constructed on the launch pad.
- The fuel holding area, oxidizer storage area, and payload
changeout room would be demolished.
- A Theodolite Building would be constructed east of the launch
pad.
- Chain-link fencing would be installed around the Integrated
Processing Facility (IPF) to form a security boundary. This would
require clearance of vegetation for 30 feet on both sides of the
fence.
South Vandenberg AFB Boat Dock. Modifications would consist of dredging
approximately 20,000 cubic yards of sediment from the existing harbor
channel. Dredging would be accomplished to the previously dredged depth.
Disposal of material would be conducted in accordance with U.S. Army Corps
of Engineers (USACE) permit requirements.
Building 836. Building 836 would be utilized for receiving, inspection, and
storage of CBCs and upper stages. Minor interior modifications would be
required.
Building 375, Integrated Processing Facility and Building 1032
(Astrotech). The IPF would require minor exterior and interior modifications.
The Astrotech facility would likely require construction of a new high bay for
encapsulation of heavy payloads.
Buildings 330, 398, and 520. These facilities would be utilized for storage
and refurbishment of GSE. Minor interior modifications would be required at
all three facilities.
Building 1670. Building 1670 would be utilized for SRM storage and
processing. Minor interior modifications would be required.
Infrastructure. Utility modifications would occur within previously disturbed
areas of SLC-6.
New Facilities
New Horizontal Integration Facility. A new HIF would be constructed in the
northern portion of SLC-6. This area was the laydown area used during the
initial construction of SLC-6 and is now a parking lot. Approximately 14 acres
would be disturbed during construction.
Alternative Facilities
Two alternative facilities have been identified for Concept B activities at
Vandenberg AFB, in the event that the preferred facilities are not available in
the time period required to support the EELV program. These facilities are
described below.
Building 2520. If Building 375 is not available for payload encapsulation
activities, Building 2520 would be utilized for unbagging of payload fairings
and encapsulation of small and medium payloads.
Building 7525. If Building 330 is not available to support EELV, Building
7525 would be utilized for GSE storage and refurbishment, and sandblasting
and painting activities. If Building 836 is not available for storage of flight
hardware, Building 7525 would be utilized for this purpose. The extent of
modifications required has not yet been determined.
Construction Phase
Most of the construction activities would take place within the previously
disturbed SLC-6 area or along existing road corridors. SLC-6 consists of
100 acres of semi-improved grounds within a perimeter fence. Construction
equipment laydown areas, personal vehicle parking, temporary mobile offices
(trailers), maintenance facilities, and other ancillary construction areas would
be sited in previously disturbed areas, to the north of the construction site.
Earthwork for construction would be performed in accordance with the
construction Storm Water Pollution Prevention Plan and the SPCC plan.
To contain collected wastewater, a truck washdown area and impoundment
within the boundaries of the construction laydown areas would be provided.
Depending upon the final design and grading plans, 4,500 to 7,500 cubic
yards of material would be excavated, and 80,000 to 135,000 cubic yards of
fill would be required. Fill material would come from the Vandenberg AFB
Manzanita Borrow Area. Unsuitable cut material would be removed from the
project area to the Manzanita spoil site, or to other approved locations. Top-soil
would be removed and stockpiled on site for re-spreading on disturbed
areas for revegetation and erosion control after completion of construction.
Appropriate erosion control would be implemented at the stockpile.
Construction materials generally would be trucked through the Coast Gate,
then over Coast Road to SLC-6.
During the construction period, approximately 2,100 gpd of water would be
required for general activities (e.g., site washdown, cement mixing, personnel
requirements). Wastewater generation would average approximately 1,400
gpd. In addition, approximately 2,200 to 3,800 tons of solid waste would be
generated, of which it is estimated that 3 to 5 percent would be recycled.
Removal of construction debris would be the responsibility of the construction
contractor; any hazardous materials found during construction (e.g.,
asbestos, lead-based paint) would be abated in accordance with applicable
regulations.
From 1998 to 2001, construction traffic entering and exiting project
construction sites on Vandenberg AFB under Concept B is estimated to
generate an average of 1,100 daily vehicle trips, with 115 trips expected
during the peak hour. Construction traffic entering and exiting project
construction sites during the peak construction period between January and
March 2000 is expected to be 2,200 trips, with 230 trips occurring during the
peak hour.