EVOLVED EXPENDABLE LAUNCH VEHICLE (EELV)
PRE-EMD MODULE CALL FOR IMPROVEMENT
ANNEX 3
DESIGN REVIEW DEFINITIONS
This page intentionally left blank.
Annex 3 - Design Review Definitions
This annex defines the Downselect Design Review and Tailored Critical Design Review
requirements.
1.0 Downselect Design Review (DDR)
1.1 Objective. A Downselect Design Review will be conducted to provide information
to support the downselect to one contractor for EMD. The system design will be
sufficiently mature to enter EMD and will provide high confidence that the key
performance parameters will be met. The DDR will confirm the contractor has plans and
processes in place to smoothly transition from Pre-EMD to EMD.
1.2 Requirements. As a minimum, the DDR will include all design disciplines, all
primary system functions, and key EELV system products and processes. This review
will ensure:
1.2.1 System, subsystem, and functional issues have been resolved;
1.2.2 Requirements flow from the SPD to the system, development, and product
specifications;
1.2.3 An audit trail is maintained with changes substantiated;
1.2.4 System design compatibility with external interfaces (people, products, and
processes) has been established;
1.2.5 System design, interface requirements, and design constraints are consistent with
DT&E results;
1.2.6 Environmental, safety, and health considerations have been integrated into the
system design;
1.2.7 Sufficient detailed design has been accomplished to support implementation of the
contractor's site activation approach upon commencement of the EMD Module. Time-critical facility design has been completed;
1.2.8 Sufficient detailed design has been accomplished to initiate fabrication, coding,
assembly, and integration of ground/flight systems hardware and software;
1.2.9 Manufacturing plans, processes, and capabilities are sufficient to support EMD
production of ground systems equipment and flight development hardware;
1.2.10 All risk mitigation plans are complete;
1.2.11 All trades have been completed;
1.2.12 The EMD implementation approach is reviewed; and
1.2.13 Life Cycle Cost Estimates at the 85% confidence level are complete.
2.0 Tailored Critical Design Review
2.1 Objective. A Tailored Critical Design Review will be conducted to verify system
design is complete and ready for manufacturing and coding. The TCDR will be
conducted for the total system to the Configuration Item (CI) level.
2.2 Requirements. In addition to satisfying the DDR requirements, this review will
ensure:
2.2.1 Detail design of the CIs satisfy the performance and design requirements of the
development specification;
2.2.2 Detail design compatibility among the CIs and other items of equipment, facilities,
computer software and personnel has been established;
2.2.3 The preliminary product specifications are reviewed;
2.2.4 Integrated Logistics Support planning is adequate; and
2.2.5 Results of the producibility analyses conducted on system hardware are assessed.