Revised SBIRS Low Baseline
Revised SBIRS Low Baseline in coord
- Maintains objective FY04 first launch
- Twelve month launch gap between L2 and L3
- Provides on-orbit evaluation of operational performance (OA) prior to full launch campaign
- Full deployment achieved in FY08 vs FY07
- Satellites 1-3 are APPN 3600, 4+ are APPN 3020
- Modified LRIP to avoid production gap
- Sats 1-6 plus build, up to SV AI&T, for 7-15
- Beyond LRIP = SV AI&T + rest of Blk I launches