EMD Contracting Strategy
Rolling downselect to one contractor team
Two contracts--both awarded at start of EMD
- RDT&E, Cost Plus Award Fee
- SVs 1-3 and Increment 3 ground system
- Award fee to include corporate commitment
- Production, Fixed Price
- SVs 7 +
- On-orbit “tire warranty”--Gov’t sets minimums
Follow-on contract
- Replenishment
- On-orbit “tire warranty”--Gov’t sets minimums
To be refined with SBIRS Low contractors during PD