A. (U) RESOURCES: ($ in Thousands)

Project Title: Test & Evaluation Support

FY1993 FY1994 FY1995 FY1996 FY1997 FY1998 FY1999 Total

Program Name: Actual Estimate Estimate Estimate Estimate Estimate Estimate Program

0603216C RDT&E 62,552 91,748 163,855 167,900 169,682 203,882 208,582 Continuing

0603217C RDT&E 368,723 186,741 103,097 83,478 83,478 83,478 83,478 Continuing

0603218C RDT&E 13,270 0 0 0 0 0 0 Continuing

0604216C RDT&E 21,700 37,952 34,850 37,510 24,870 0 0 Continuing

B. (U) BRIEF DESCRIPTION OF MISSION REQUIREMENT AND SYSTEM CAPABILITIES:

(U) This effort provides for BMDO planning oversight and coordination of integrated Test and Evaluation activities and inter-element, as well as inter-service Test and Evaluation efforts. Provides Independent Test Evaluation of systems, technology programs and special reviews. Provides for test infrastructure including: The National Test Facility; The Advanced Research Center; Simulation Center; common National Test Bed support; common ground test facilities; high fidelity models and simulation to support system development testing and evaluations including international cooperative with the United Kingdom, France, Israel, and the SHAPE Technical Center (STC); common range support, range upgrades; special test equipment and range instrumentation; Targets, test support assets; and test data documentation, management and storage facilities. Using mobile test assets such as the Airborne Surveillance Testbed (AST), provide critical signature and functional data essential to risk reduction and design of future optical surveillance systems.

(U) This project includes funding in FY93 and FY95 for 3312 and funding in FY93 and FY94 for 3308. Project 3314 is funded in FY93 and FY94 and funding for Operational Testing (3314) in the outyears will be transferred from Program funding lines to 3314 for execution. The following projects are funded in FY93-FY95: 3301, 3302, 3303, 3304, 3305, 3306, 3307, 3309, 3310, 3311, 3313, and 3314. This CDS also provides for the development of the TMD System Exerciser. This integration tool will assist in performing system level interoperability testing.

(U) This project is assigned to the Budget Activity and Program Element codes as identified in this descriptive summary in accordance with existing Department of Defense policy. Further justification of the Budget Activity code assigned to each Program Element is contained within the Brief Description of Element section of each Program Element Summary.

C. (U) PROGRAM ACCOMPLISHMENTS AND PLANS:

(U) FY 1993 Accomplishments:

o ($ 46.722M) Successfully completed the Integrated System Test Capability Proof of Principle development phase; restructured and combined the functions of the Test Data Centers while continuing to receive, store and analyze test data.

o ($ 4.390M) Established BMD Independent Evaluation program and provided OT&E support.

o ($ 60.661M) Provided test resource support including advance scene generation for AIT, SHARP, INETS, MISTI, and SIT, range safety support for Theater Countermeasures Mitigation Program (1A & 1B), provided airborne optical data collection, and range infrastructure support, continued studies, analysis and planning to support selection of TMD range option(s), funded termination of USNS Redstone support.

o ($154.528M) Completed two STARS missions, continued development of TMD targets including test flights.

o ($113.042M) Transferred the National Test Facility executive services responsibilities to US AFSPACECOM and provided infrastructure support to NTF/ARC.

o ($ 37.780M) Provided critical functional and infrared electro-optical data and analysis from 5 BMDO sponsored flight experiments using the Airborne Surveillance Testbed.

o ($ 49.122M) Completed Build I of the High Fidelity BMD System level Simulation and rebaselined the Extended Air Defense Test Bed Development program, and initiated cooperative agreements with France and Shape Technical Center.

(U) FY 1994 Plans:

o ($ 22.700M) Complete global environment for proof of principle demonstration of the Distributed Theater Missile Defense System Level Exerciser and merge BMD BMC3 with ISTC global environment; conduct Proof of Principle demonstration for TMD System Exerciser; provide restructured Data Centers to receive, store, and analyze BMD test data.

o ($ 6.389M) Conduct BMD Evaluation Program including OT&E support.

o ($ 41.260M) Provide resource support for BMDO testing including; deployment of Rapid Optical Beam Steering (ROBS) system to WSMR, completion of IOC at Center for Research Support (CERES), selection of option(s) and initiation of work to establish range capability to support TMD testing, collection of optical data in support of testing and sensor development, provide ground facilities.

o ($118.400M) Provide STORM and HERA targets, facilities, and resources to support THAAD, PATRIOT, and ERINT flight test programs; complete STARS ODES demonstration flight.

o ($ 78.000M) Provide Infrastructure support to National Test Bed to include NTF and ARC/SC.

o ($ 22.000M) Provide airborne sensor support to gather electro-optical data and demonstrate critical optical sensor and system functions on TMD and NMD technology flight experiments using the Airborne Surveillance Testbed (AST).

o ($ 27.692M) Complete EADTB integration testing and software acceptance for initial operations capability, complete hardware installations of the STC node of the EADTB, and continue to support annual CINC experiments program with EADSIM. Document L2SS for future use and shut down.



(U) FY 1995 Plans:

o ($ 31.300M) Develop interface for TMD System Exerciser; conduct TMD system level interoperability testing with System Exerciser; complete System Exerciser Environment for BMD integration in ISTC environment; provide Data Center support to receive, store, and analyze BMDO test data.

o ($ 7.000M) Conduct BMDO evaluation program including OT&E program

o ($ 55.560M) Provide test resources including range instrumentation, range development, infrastructure support, optical data collection, ground test facilities.

o ($100.100M) Provide targets, target facilities, and target resources to support BMDO flight testing.

o ($ 55.000M) Provide Infrastructure support to National Test Bed to include NTF and ARC/SC.

o ($ 22.000M) Provide airborne sensor support to gather electro-optical data and demonstrate critical optical sensor and system functions on TMD and NMD technology flight experiments using the Airborne Surveillance Testbed (AST).

o ($ 30.400M) Complete software development and testing for EADTB FOC, and complete verification, validation and accreditation of EADSIM and EADTB.

(U) Program Plan to Completion: This is a continuing program.

D. (U) WORK PERFORMED BY:

o US. Army Space and Strategic Defense Command, Huntsville, AL

o USAF Phillips Laboratory, Albuquerque, NM

o USAF Arnold Engineering Development Center, Tulahoma, TN

o USAF Space Command, Colorado Springs, CO

o National Test Facility, Falcon AFB, CO

o Naval Research Laboratory, Washington, DC

o Naval Sea Systems Command

o MIT/Lincoln Labs, Boston, MA

o John Hopkins Applied Physics Lab

o Martin Marietta

o Sandia National Laboratories, Albuquerque, NM

E. (U) COMPARISON WITH FY 1994 DESCRIPTIVE SUMMARY:

1. TECHNICAL CHANGES: Emphasis has shifted from an NMD (Strategic) focus to a TMD focus, based upon the outcome of the Bottom Up Review

2. SCHEDULE CHANGES: Previously this work was distributed among multiple associated/related PMAs. Support for NMD activities have been delayed or deleted. TMD activities have been programmed consistant with program schedules.

3. COST CHANGES: Previously this work was distributed among multiple associated/related PMAs. Major reductions have been made in the T&E cost associated with NMD, a FY95-FY99 reduction of $1,168M. TMD T&E costs have increased to support increased TMD programs.

F. (U) PROGRAM DOCUMENTATION:

o Programmatic status reports

o Technical/Mission reports for analysis, assessment, and review tasks

o BMD Directive 3240, 5000, 5000.2

o Targets Master Plan

o Test and Evaluation Master Plan

o Independent Evaluation Plan

G. (U) RELATED ACTIVITIES: All BMDO sponsored data collection, experiments, tests, high fidelity modeling, and simulation efforts.

H. (U) OTHER APPROPRIATION FUNDS: None

I. (U) INTERNATIONAL COOPERATIVE AGREEMENTS:

o Memorandum of Agreement (MOA) between BMDO and Israeli Ministry of Defense (MOD)

o Letter of Agreement (LOA) between SSDC and UK MOD

o Contract between SSDC and Israeli MOD

J. (U) MILESTONE SCHEDULE:

o TMD System Exerciser POP Build 3Q/1994

o Complete System Evaluation Plan 3Q/1994

o Initial Operational Capability ROBS 4Q/1994

o EADTB IOC 4Q/1994

o Multiple PATRIOT/ERINT target launches/tests FY 1994

o MSX Targets 1Q/1995

o Multiple PATRIOT/THAAD/Navy Lower Tier target launches/tests FY 1995

o Range support for TCMP FY 1995

o TMD System Exerciser FY 1996