Program Element: 0604216C Project Number: 2308

PE Title: Theater Missile Defense (U) Budget Activity: 04

Dem / Val (U)

February 1994





A. (U) RESOURCES: ($ in Millions)

Project Title: HAWK System BM/C3

FY1993 FY1994 FY1995 FY1996 FY1997 FY1998 FY1999 Total

Program Name: Actual Estimate Estimate Estimate Estimate Estimate Estimate Program

0208060C PROC 0 0 3,831 5,131 20,530 0 0 Completed

0604216C RDT&E 0 29,629 26,800 23,000 0 0 0 Completed

B. (U) BRIEF DESCRIPTION OF MISSION REQUIREMENT AND SYSTEM CAPABILITIES:

(U) This project will provide a basic tactical missile defense (TMD) capability for the Marine Corps to provide for a point defense of vital assets in the amphibious operating area of mature and contingency theaters. This TMD capability will be accomplished through product improvements to the AN/TPS-59 radar and the HAWK missile system. Additionally, the development of the Air Defense Communications Platform (ADCP) is included in this project. This project was not affected by the Bottom Up review (BUR)

(U) The AN/TPS-59 modifications include adding a ballistic missile detection and tracking capability, increasing the detection probability on low radar cross section (RCS) targets, and improving the overall system reliability and transportability.

(U) The ADCP development provides the communications capability required to provide AN/TPS-59 cueing data to the HAWK system and to other interceptor systems via the Joint Tactical Information Distribution System (JTIDS).

(U) The HAWK upgrades include processing changes to allow for remote cueing from theater sensors and software changes to perform ballistic missile engagements.

(U) This project is assigned to the Budget Activity and Program Element codes as identified in this descriptive summary in accordance with existing Department of Defense policy. Further justification of the Budget Activity code assigned to each Program Element is contained within the Brief Description of Element section of each Program Element Summary.

C. (U) PROGRAM ACCOMPLISHMENTS AND PLANS:

(U) FY 1993 Accomplishments:

o Conducted AN/TPS-59 system design review (SDR).

o Began AN/TPS-59 hardware fabrication and software coding efforts.

o Awarded HAWK TMD modification contract to Raytheon.

o Awarded ADCP TMD software contract to Advanced Programming Concepts.

o Held ADCP Milestone I review.

(U) FY 1994 Plans:

o Conduct AN/TPS-59 design reviews.

o Begin AN/TPS-59 system integration effort.

o Conduct ADCP design reviews.

o Conduct HAWK engineering change proposal (ECP) test readiness review.

o Conduct HAWK ECP operational testing.

o Conduct ADCP test readiness review.

(U) FY 1995 Plans:

o Complete AN/TPS-59 system integration effort.

o Initiate AN/TPS-59 contractor's developmental tests.

o Conduct ADCP integration and testing.

o Approve HAWK ECP for production.



(U) Program Plan to Completion:

o Complete AN/TPS-59 and ADCP operational testing during FY 96.

o Conduct Milestone III reviews for AN/TPS-59 and ADCP in FY 96.

D. (U) WORK PERFORMED BY:

(U) In House:

o Marine Corps Systems Command - Quantico, VA

o U.S. Army Missile Command - Redstone Arsenal, AL

o Naval Surface Warfare Center - Crane, IN



(U) Major Contractors:

o Raytheon - Bedford, MA

o Martin-Marietta - Syracuse, NY

o Sensis - Syracuse, NY

o Advanced Programming Concepts - San Antonio, TX

E. (U) COMPARISON WITH FY 1994 DESCRIPTIVE SUMMARY:

1. TECHNICAL CHANGES: This program was part of 2106 and 2213 in FY94.

2. SCHEDULE CHANGES: This program was part of 2106 and 2213 in FY94.

3. COST CHANGES: This program was part of 2106 and 2213 in FY94.

F. (U) PROGRAM DOCUMENTATION:

o BMDO GPMD 4Q/1993

o AN/TPS-59 Acquisition Decision Memorandum (ADM) 3Q/1992

o AN/TPS-59 Mission Needs Statement (MNS) 3Q/1992

o ADCP MNS 3Q/1992

o HAWK MNS 3Q/1992

o AN/TPS-59 Operational Requirements Document (ORD) 3Q/1994

o ADCP ORD 1Q/1994

o HAWK ORD 1Q/1994

o AN/TPS-59 Acquisition Program Baseline Agreement (APBA) 4Q/1994

o ADCP APBA 2Q/1994

o HAWK APBA 1Q/1994

G. (U) RELATED ACTIVITIES:

o 1215 Ascent/Boost Phase Technology PE No. 6.3

o 2207 PATRIOT PE No. 6.4/6.5

o 2213 Sea-based Area TBMD PE No. 6.4/6.5

o 3300 Test and Evaluation Support PE No. 6.3

There is no unnecessary duplication of effort within BMDO or the DoD.

H. (U) OTHER APPROPRIATION FUNDS:

o Procurement:FY1995 $$3.83M; FY 1996 $5.131M; FY 1997 $20.530M

o C1067 Aviation Radar Product Improvement

o C1120 Air Defense Missile Systems Project

I. (U) INTERNATIONAL COOPERATIVE AGREEMENTS: None





J. (U) MILESTONE SCHEDULE:

o AN/TPS-59 preliminary design review (PDR) 2Q/FY94

o AN/TPS-59 critical design review (CDR) 4Q/FY94

o AN/TPS-59 operational testing 2Q/FY96 - 3Q/FY96

o AN/TPS-59 Milestone III review 4Q/FY96

o ADCP PDR 2Q/FY94

o ADCP CDR 3Q/FY94

o ADCP Milestone II decision 1Q/FY96

o ADCP operational testing 2Q/FY96 - 3Q/FY96

o ADCP Milestone IIIA 1Q/FY96

o ADCP Milestone IIIB 4Q/FY96

o HAWK ECP operational evaluation 2Q/FY94

o HAWK ECP approval 4Q/FY94