Program Element: 0604216C/0604225C Project: 2207
PE Title: Theater Missile Defense (U) Budget Activity: 04/05 Project Title: PATRIOT ONLY (ERINT NOT INCLUDED) Dem/Val / EMD (U)
February 1994
POPULAR NAME: PATRIOT ONLY (ERINT NOT INCLUDED)
A. (U) SCHEDULE/BUDGET INFORMATION: ($ in Thousands)
BUDGET FY 1993 FY 1994 FY 1995 FY 1996 FY 1997 FY 1998 FY 1999 Program Total
Dem/Val EMD Dem/Val EMD Dem/Val EMD Dem/Val EMD Dem/Val EMD Dem/Val EMD Dem/Val EMD
Major Contract 63,870 0 48,074 37,367 52,340 192,400 25,960 181,220 0 95,330 0 27,840 0 0
Support Contract 3,500 0 3,060 1,260 2,800 2,900 900 4,300 0 5,400 0 5,600 0 0
In-House Support 10,400 0 11,350 1,470 8,000 15,300 3,900 10,600 0 13,100 0 4,300 0 0
GFE/Other 16,700 0 18,200 2,000 6,100 6,600 200 9,500 0 20,400 0 6,700 0 0
Total 94,470 0 80,684 42,097 69,240 217,200 30,960 205,620 0134,230 0 44,440 0 0 4,253M
SCHEDULE FY 1993 FY 1994 FY 1995 FY 1996 FY 1997 FY 1998 FY 1999 Complete
Program GEM MS III IPR PAC-3 Missile C-1 Software PDB-4 Software PAC-3 Missile PDB-5 Software
Milestones MS IV Release (1Q) Release (1Q) MS III (4Q) Release (4Q)
ASARC (1Q) PAC-3 Missile
DAB (2Q) LRIP (1Q)
Engineering RE III System CDI-II System
Milestones Evaluation Evaluation (1Q)
(1Q)
T&E Dem/Val Flight C-2 CDT&E (2Q) C-2 FOT (1Q) EMD Flight TestsC-3 CDT&E (1Q)
Milestones Tests (1-4Q) EMD Flight EMD Flight Tests(1-3Q) C-3 FOT (3Q)
Tests (2-4Q) (1-4Q) IOT&E (2Q)
Contract PAC-3 Missile RE-III Prod. PAC-3 Missile PAC-3 Missile
Milestones EMD Contract Contract (2Q) LRIP Contract Prod. Contract
(3Q) (1Q) (4Q)
Note: Costs do not include procurement.
B. (U) BRIEF DESCRIPTION OF MISSION REQUIREMENT AND SYSTEM CAPABILITIES:
(U) PATRIOT is a long-range, mobile, field Army and Corps air defense system, which uses guided
missiles to simultaneously engage and destroy multiple targets at varying ranges. Current threat theater
ballistic missiles (TBMs) with significantly improved range and accuracy have increased the threat
against PATRIOT air defense sites or defended assets. This could result in the destruction of air
defense sites and provide the enemy air superiority once an attack is initiated. The current PATRIOT
missile requires improved performance and increased accuracy to counter the evolving threat and to
increase its contribution to the lower tier of the theater segment of a theater missile defense (TMD)
system. The PATRIOT missile program, which entered production in 1979, is a major defense acquisition
program (MDAP). It has successfully evolved through two major improvement programs, PATRIOT Anti-Tactical Missile (ATM) Capability (PAC) 1 and 2. Also, as a result of analysis of PATRIOT operations in
Desert Storm, the Quick Response Program (QRP) was initiated to incorporate several near-term
hardware/software changes to upgrade PATRIOT performance. The PAC-3 Growth Program is the latest
evolution of the phased material change improvement program to PATRIOT. The material changes represent
capability improvements to address the PAC-3 Operational Requirements Document (ORD) and are planned over
a multi-year period. Fielding will range from the already funded QRP beginning in FY 1993 for near-term
deployment, to the Configuration 3 of the PAC-3 Program ending in FY 1999 for the far-term deployment.
The program elements funded by the Ballistic Missile Defense Organization (BMDO) for TMD improvements
are: radar enhancements (QRP); guidance enhancement missile (GEM); multimode missile or ERINT; radar
enhancements phase III; remote launch; communications upgrades; and THAAD integration/cueing.
(U) The major technical issue associated with this program, as with other interceptor programs, is the
lethality of the missile. Two missiles are competing for selection as the PAC-3 missile. ERINT,
developed by Loral Vought Systems, is a BMDO-sponsored advanced technology program to exploit hit-to-kill
technology. The Multimode Missile, developed by Raytheon, is a variant of the PATRIOT missile and
incorporates an active Ka-band seeker, improved propulsion system, and aimable warhead. A selection
decision on the PAC-3 missile is scheduled for second quarter of FY 1994. In the event that ERINT is
selected as the PAC-3 missile, integration studies are being conducted to develop a definitive concept
for a fully integrated PATRIOT/ERINT system of sufficient depth to support program planning, cost
estimating, development, and testing.
(U) This project is assigned to the Budget Activity and Program Element codes as identified in this
descriptive summary in accordance with existing Department of Defense policy. Further justification of
the Budget Activity code assigned to each Program Element is contained within the Brief Description of
Element section of each Program Element Summary.
C. (U) PROGRAM ACCOMPLISHMENTS AND PLANS:
(U) FY 1993 Accomplishments:
o Continued PAC-3 missile review process.
o Initiated Phase III Radar integration testing.
o Continued Remote Launch development.
o Completed multimode missile propellant formulation and characterization.
o Conducted two GEM flight tests.
o Completed two test flights of the multimode seeker.
o Provided Multimode Missile data to support PAC-3 missile decision process and Cost and Operational Effectiveness Analysis (COEA).
o Continued to execute PATRIOT-ERINT Integration Program.
(U) FY 1994 Plans:
o Complete PAC-3 missile review process.
o Complete Post Deployment Build-4 (PDB-4) software testing.
o Complete Multimode Missile propellant, case, and motor development and tests.
o Complete Multimode Missile improved warhead development and test.
o Plan and schedule PAC-3 missile controlled test vehicle flights.
o Complete Radar Enhancements Phase III subsystem testing and integration.
o Complete GEM flight test program and conduct production decision review.
o Continue Remote Launch development.
o Provide any additional Multimode Missile data required to support the PAC-3 Informed Missile Decision process (ASARC/DAB).
o Complete the PATRIOT-ERINT integration program.
o Complete Producibility Engineering and Planning (PEP) and Manufacturing Plan.
o Continue logistics planning/LSA/LSAR/training and technical manual support.
o Initiate system integration and testing.
o Initiate hardware/software developmental testing.
(U) FY 1995 Plans:
o Begin GEM delivery.
o Conduct Phase III Radar production decision review.
o Obtain Configuration 1 software release.
o Complete PDB-4 software testing.
o Complete Remote Launch integration and testing.
o Initiate PAC-3 Missile EMD flight test program.
o Continue system integration and testing.
o Continue hardware/software developmental testing.
o Continue logistics planning/LSA/LSAR/training and technical manual support.
(U) Program Plan to Completion: This is a continuing program.
D. (U) WORK PERFORMED BY:
(U) In-house:
o Program Executive Office, Missile Defense - Arlington, VA
o Project Manager, PATRIOT/Product Manager, PATRIOT ATM - Redstone Arsenal, AL
o U.S. Army Missile Command Research, Development, and Engineering Center - Redstone Arsenal, AL
o U.S. Army Armament Research and Development Center - Picatinny Arsenal, NJ
o Harry Diamond Laboratories - Adelphi, MD
o Ballistic Research Laboratory - Aberdeen Proving Ground, MD
o U.S. Army Air Defense School - Fort Bliss, TX
(U) Contractors:
o Raytheon Corporation (prime) - Andover, MA
o Martin-Marietta - Syracuse, NY
o Thiokol - Ogden, UT
o Telefunken System Technik - Germany
E. (U) COMPARISON WITH FY 1994 DESCRIPTIVE SUMMARY:
1. TECHNICAL CHANGES: None
2. SCHEDULE CHANGES: None
3. COST CHANGES: None
F. (U) PROGRAM DOCUMENTATION:
o ATMD O&O Plan - 8/90
o PAC-3 ORD - 5/92
o Cost/Schedule Status Report - monthly
G. (U) RELATED ACTIVITIES:
o 1502 Lethality and Target Hardening PE No. 6.3
o 2208 ERINT PE No. 6.3
o 2210 THAAD PE No. 6.4/6.5
o 2212 Corps SAM PE No. 6.3/6.4/6.5
o 3300 Test and Evaluation Support PE No. 6.3
o NATO Cooperative Programs
o Joint Tactical Missile Defense Program
H. (U) OTHER APPROPRIATION FUNDS: Procurement: FY93: $75.2M; FY94: $120.719M; FY95: $255.063M; FY96:
$435.622M; FY97: $386.515M; FY98: $470.651M; FY99: $439.878M.
I. (U) INTERNATIONAL COOPERATIVE AGREEMENTS:
o Extended Air Defense Memorandum of Agreement between the United States and the Federal Republic of
Germany, 17 May 89, with Annex A: Multimode Seeker Demonstration
J. (U) TEST AND EVALUATION DATA:
o Multimode seeker Dem/Val flight tests 2Q/FY92 - 1Q/FY94
o PAC-3 ASARC 1Q/FY94
o PAC-3 DAB 2Q/FY94
o Conduct IPF/PEP production transition 1Q/FY94 - 3Q/FY96
o PDB-4 software system demonstrations 2Q/FY94 - 4Q/FY94
o Phase III radar mod kit PPQT 3Q/FY94 - 4Q/FY94
o PATRIOT-ERINT Integration Program 2Q/FY91 - 4Q/FY94
o PAC-3 missile EMD flight test program 2Q/FY95 - 3Q/FY97
o PDB-4 software release 1Q/FY96
o Initiate long lead procurement PAC-3 missile 4Q/FY96
o PAC-3 missile IOTE 2Q/FY97
o PAC-3 missile Milestone III FRP decision 4Q/FY97
o PDB-5 software Follow-on Test (FOT) 3Q/FY98
o PDB-5 software release 4Q/FY98