RDT&E BUDGET ITEM JUSTIFICATION SHEET (R-2 Exhibit)
March 1996

RDT&E Defensewide / BA 04 (Dem/Val) PE: 0603871C (Proj: 3265)

PE Title: NMD Tech. (U)

Project Number / Title:
3265 User Interface

FY1995FY1996FY1997FY1998FY1999FY2000 FY2001
Program Name:ActualEstimateEstimate EstimateEstimateEstimateEstimate To
Complete
Total
Program
0603871C RDT&E1,2263,0002,7802,7801,222900 892ContinuingContinuing

A. (U) MISSION DESCRIPTION AND BUDGET ITEM JUSTIFICATION:

(U) Development of an effective NMD program requires a close user interface to ensure user and developer consistency with respect to operational requirements, concepts of operation, and integration of multi-service systems. This project supports BMDO's NMD interface with the military operational community through an integrated support and development effort. Through this project the CINCs develop and refine operational requirements, concepts of operation (CONOPS), develop BM/C3 architectures, and formulate and test operational concepts for employment of NMD. User assessments will be performed on each BM/C3 increment capability developed by the BM/C3/SE&I development effort. Analysis, simulations and tests are performed to address system effectiveness of proposed NMD system architectures against near and far term ballistic missile threats. Strategic command and control simulation (C2 Sim) are performed with CINCs to identify roles, missions and requirements for NMD. NMD strategic C2 Sims are the vehicle by which the operational concepts are developed, verified, and integrated into the overall BMD system deployment strategy and planning. Long term objectives are to ensure the successful transition of NMD systems to the user. This project develops information critical to the successful accomplishment of several other NMD projects: 1267 (Ground Based Interceptor), 1151 (Sensors), 1460 (NMD BMC3), 3152 (System Engineering), and 3160 (Deployment Planning).

(U) PROGRAM ACCOMPLISHMENTS AND PLANS:

(U) In FY95 much effort was devoted to refining operational requirements and concept of operations documents. Support included activities required for wargaming, CINC/Services operational evaluation requirements definition of R&D activities, and mission analysis for BMD. Support was also provided to the Army's CONOPS development planning for User Operational Evaluation Systems (UOES). FY95 through FY98 activities will focus on NMD wargames, requirements documentation, and user CONOPS.

(U) FY 1995 Plans and Accomplishments:

o ($ 0.318M) Coordinated and worked with the multi-service users to refine Operational Requirements Documents (ORDs) and provide input to the NMD Maturity Matrix (NMM).

o ($ 0.508M) Coordinated and worked with the multi-service user to refine NMD CONOPS based on results of the Early Warning Radar (EWR) experiments.

o ($ 0.400M) Developed operational requirements and CONOPS for conducting strategic C2 Sims and NMD mission analysis to support deployment readiness.

(U) FY 1996 Plans:

o ($0.784M) Update ORDs based on results of NMD threat assessment and mission analysis.

o ($1.238M) Refine NMD CONOPS using simulations and progress of BM/C3 and SMTS programs.

o ($0.978M) Develop operational requirements and CONOPS for conducting strategic C2 Sims and NMD mission analysis to support deployment readiness.

Provide technical management for NMD C2 Sim architecture and requirements as well as C2 Sim analysis.

Provide input to the NMD Threat Assessment Report and supporting analysis.

Provide user assessments and BM/C3 increment capabilities.

(U) FY 1997 Plans:

o ($0.651M) Continue work with the multi-service users to refine ORDs based on results of NMD threat assessment and NMD mission analysis

o ($1.369M) Refine CONOPS for NMD based on radar Hardware-in-the-Loop (HWIL) simulations testing and flight testing.

o ($0.760M) Develop operational requirements and CONOPS for conducting strategic C2 Sims and NMD mission analysis to support deployment readiness.

Provide user assessments and BM/C3 increment capabilities.

(U) FY 1998 Plans:

o ($0.639M) Continue work with the multi-service users to refine ORDs based on results of NMD threat assessment and NMD mission analysis.

o ($1.331M) Refine CONOPS for NMD based EKV flight testing with BMC3 on-line and in-line.

o ($0.810M) Develop operational requirements and CONOPS for conducting strategic C2 Sims and NMD mission analysis to support deployment readiness.

Provide user assessments and BM/C3 increment capabilities.

(U) Acquisition Strategy: The NMD User Interface function is provided through a combination of Service and BMDO staff. This contract provides development and refinement of operational requirements, CONOPS, development of BM/C3 architectures, and formulation and test of operational concepts for employment of NMD.

B. (U) PROGRAM CHANGE SUMMARY:

FY1995FY1996FY1997FY1998 TOTAL COST
Previous President's Budget1,2481,4431,5301,5305,751
Current Budget Submit1,2263,0002,7802,7809,786

Change Summary Explanation:

Funding: With the shift to a deployment readiness program focus, extensive user involvement is required to ensure incremental element development on a path to an objective system deployment capability. This results in an accelerated milestone schedule culminating in an FY99 system test.

Schedule: None

Technical: More personnel required to support FY99 System Demonstration Test.

C. (U) OTHER PROGRAM FUNDING SUMMARY:

Related RDT&E:Funding Dependency? (Yes1/No)
1151 Sensors (Active & Passive), PE 0603871CNo
1267 Ground Based Interceptor, PE 0603871CNo
1460 NMD BMC3, PE 0603871CNo
3152 NMD System Engineering, PE 0603871CNo
3160 Deployment Planning, PE 0603871CNo
3352 Modeling & Simulation, PE 0603871CNo

1Funding data for related RDT&E efforts that have a funding dependency can be found in the respective project summary/program element.

D. (U) Schedule Profile

FY1995FY1996FY1997FY1998
1234123412 341234
Engineering Milestonexa,b,fxb,c,d,exb,f,g xb,c,d,exa,e,fxb,c,d,exe,f,g xb,c,d,exa,fxb,c,dxe,f,g xb,c,dxa,fxb,c,dxe,f,g xb,c,d
T&E Milestonexhxi xjxkxlxmxn xoxp
Tech Demo Milestonexqxqxq xqxqxqxq xqxqxqxq
Contract Milestonexr

a Update Capstone ORD

b Update NMD System Engineering Notebook/Interface Definition Note (NSEN/IDN)

c Update System Requirements Documents (SRDs)

d Update Element Requirements Documents (ERDs)

e Update Interface Requirements Documents (IRDs)

f Update NMM

g Update Integrated Test Requirements Documents

h Integrated Ground Test (IGT)-1

i IGT-2

j Integrated Flight Test (IFT)-1

k ISTC-1

l IFT-2

m ISTC-2

n IGT-1A

o IFT 3

p IFT 4

q C2 Sims/Workshops

r SEIC/BMC3 Contract Award

Planned Milestone Beyond FY98:

C2 SimsFY99-01 Tri-Annually
Update NSEN/IDNFY99-01 Semi-Annually
Update SRDsFY99-01 Semi-Annually
Update ERDsFY99-01 Annually
Update IRDsFY99-01 Annually
Update NMMFY99-01 Semi-Annually
Update Integrated Test Requirements DocumentsFY99-01 Annually
Update Capstone ORD1Q/FY99-01
IGT-2A (start)1Q/FY99
IGT-2A (complete)3Q/FY99
IFT-53Q/FY99
IGT-32Q/FY00
SEIC/BMC3 Contract Recompete3Q/FY00