COST (In Thousands) FY 1995 Actual FY 1996 Estimate FY 1997 Estimate FY 1998 Estimate FY 1999 Estimate FY 2000 Estimate FY 2001 Estimate Cost to Complete Total Cost
Total Program Element (PE) Cost 35890 63057 30959 11720 9330 19187 37046 0 Continuing Continuing
D036 PATRIOT Product Improvement Program 23354 46477 12291 9406 6481 5792 4785 ----- 0 365294
D038 Avenger Product Improvement Program 7726 2918 0 0 0 0 0 ----- 0 32476
D303 Stinger Product Improvement Program 4810 13662 18668 2314 2849 12439 28465 ----- Continuing Continuing
D633 THAAD P3I 0 0 0 0 0 0 1898 ----- Continuing Continuing
D634 THAAD GBR P3I 0 0 0 0 0 956 1898 ----- Continuing Continuing

Mission Description and Budget Item Justification: The changing global threat and the new Army Warfighting Doctrine developed to respond to this changing threat all significantly impact the mission of Air Defense Artillery (ADA). This doctrine calls for US forces to be able to win two nearly simultaneous major regional conflicts and to conduct combat operations characterized by rapid response and a high probability of success while minimizing the risk of significant American casualties. ADA must continually be upgraded and modernized in accordance with the ADA missions. FY 96 is the last year of funding for AVENGER upgrades. The FY 97 budget funds critical improvements to major acquisition programs of PATRIOT and STINGER. The projects support development of upgrades to current equipment and are appropriately funded in Budget Activity 7.

COST (In Thousands) FY 1995 Actual FY 1996 Estimate FY 1997 Estimate FY 1998 Estimate FY 1999 Estimate FY 2000 Estimate FY 2001 Estimate Cost to Complete Total Cost
D036 PATRIOT Product Improvement Program 23354 46477 12291 9406 6481 5792 4785 0 365294

A. Mission Description and Budget Item Justification D036 - PATRIOT Product Improvement Program: The PATRIOT system is being upgraded through a series of individual materiel changes (MMC) culminating in the attainment of the PATRIOT Advanced Capability - 3 (PAC-3) system. The communication upgrades improve PATRIOT's above and below battalion communication equipment. These changes eliminate PATRIOT peculiar communications equipment and improve PATRIOT's interoperability between systems and between the services.

Acquisition Strategy: The design objective of the PATRIOT system was to provide a baseline system capable of being modified to cope with the evolving threat. This alternative minimizes technological risks and provides a means of enhancing system capability through planned upgrades of deployed systems. The PATRIOT Program consists of two interrelated acquisition programs - The PATRIOT Growth Program and the PAC-3 Missile Program. Growth program modifications are grouped into configurations which are scheduled to be fielded in the same time-frame. Configuration groupings are a convenience for managing block changes of hardware and software and are not a performance-related grouping. However, incremental increases in performance will be determined for each configuration in order to provide benchmarks for configuration testing and for the development of user doctrine and tactics.

FY 1995 Accomplishments:

11443 P3I Test Program
9368 Communications Upgrades
1793 P3I Test Program Sets
750 Responsive Threat Analysis
Total 23354

FY 1996 Planned Program:

5733 P3I Test Program
5083 Communications Upgrades
750 Responsive Threat Analysis
33769 PAC 2 Anti-Cruise Missile Upgrade
131 Revised Economic Assumption (Not available for execution)
1011 SBIR/STTR
Total 46477

FY 1997 Planned Program:

5600 P3I Test Program
5941 Communications Upgrades
750 Responsive Threat Analysis
Total 12291

B. Project Change Summary FY 1995 FY 1996 FY 1997
Previous President's Budget (FY 1996) 24294 12823 12626
Appropriated Value (FY 1995) 23809
Adjustment to FY 1995 -455
Appropriated Amount (FY 1996) 46946
Adjustment to FY 1996 -469
Adjustments to Budget Year (FY 1997) since

FY 1996 President's Budget

-335
Current President's Budget Submit 23354 46477 12291

Change Summary Explanation:

Funding: FY 1995: Below Threshold Reprogramming (-455).

FY 1996 Revised Economic Assumption not available for execution (-469).

FY 1997 Revised Economic Assumption (-335)

C. Other Program Funding Summary FY 1995 FY 1996 FY 1997 FY 1998 FY 1999 FY 2000 FY 2001 To

Complete

Total

Cost

Missile Procurement, Army
Budget Activity 2 - PATRIOT (C49100) 8799 4924 2862 0 0 0 0 0 9636859
Budget Activity 3 - PATRIOT Mod (C50700) 25916 6767 11464 14737 15956 36538 19729 0 484732

D. Schedule Profile FY 1995 FY 1996 FY 1997

1 2 3 4 1 2 3 4 1 2 3 4
Contractor Test & Evaluation X
Development Test & Evaluation X

A. Project Cost Breakdown FY 1995 FY 1996 FY 1997
Contract Engineering Support 11580 38115 2000
Program Management Support 4588 2227 1791
Developmental Test and Evaluation 7186 6135 8500
Total 23354 46477 12291

B. Budget Acquisition History and Planning Information

Performing Organizations

Contractor or Government Performing Activity Contract Method/Type or Funding Vehicle Award or Obligation Date Performing Activity EAC Project Office EAC Total Prior to FY 1995 FY 1995 FY 1996 FY 1997 Budget to Complete Total Program

Product Development Organizations

Raytheon
DAAH0182CA181 3722 3722
DAAH0187CA025 22455 22455
DAAH0189C0458 23228 23228
DAAH0192C0036 5000 5000
Small Contracts 1168 1168
General Electric
DAAH0187CA006 4824 4824
Brunswick Corp
DAAH0189C0167 3100 3100
Martin Marietta
DAAH0192C0301 SS/CPFF 15Jul92 5463 5463 2963 800 100 3863
Raytheon
DAAH0191C0602 SS/CPIF 22Apr92 20702 20702 18302 4775 23077
DAAH0192C0006 SS/CPAF 27Jan92 56460 56460
DAAH0195C0043 SS/CPAF 01Feb95 6005 3646 2000 4234 15885
PAC 2 Anti-Cruise 34369 34369

Support and Management Organizations

CAS
DAAH0187CA008 2270 2270
DAAH0190C0487 6266 6266
DAAH0194C0105 C/CPAF 31Jan94 2093 3251 791 791 1058 7984
In-house Support 9480 1337 1436 1000 2912 16165

Test and Evaluation Organizations

Missile Command 1095 2322 1962 2100 5478 11862
White Sands Missile Range 1095/MIPR 2841 2847 3200 6208 15096
Other Govt Agen MIPR 2023 1326 3200 6574 13123
RDEC and Other Govt Agen 95377 95377

Government Furnished Property: None.

Subtotal Product Development 141222 11580 38115 2000 4234 197151
Subtotal Support and Management 20109 4588 2227 1791 3970 32685
Subtotal Test and Evaluation 95377 7186 6135 8500 18260 135458
Total Project 256708 23354 46477 12291 26464 365294