COST ($ In Thousands) FY 1995 Actual FY 1996 Estimate FY 1997 Estimate FY 1998 Estimate FY 1999 Estimate FY 2000 Estimate FY 2001 Estimate Cost to Complete Total Cost
485L Ground Theater Air Control Sys (GTACS) 6,555 242 622 723 802 826 836 Continuing TBD

(U) A. Mission Description and Budget Item Justification

Ground Theater Air Control System (GTACS) provides the means through which the Air Component Commander exercises control of his forces to accomplish his assigned mission. This program provides for major improvements to the existing Tactical Air Control System (TACS) which was designed in the 1960s and is now unsupportable. The GTACS RDT&E program consists primarily of the Modular Control Equipment (MCE) Pre-Planned Product Improvements (P3I) program which replaces obsolete equipment (operator consoles, shelters, computers, radios, etc.) in the GTACS. The modernization upgrades C2 interoperability, flexibility, mobility, communications and worldwide operations. The P3I program is structured into multiple phases. Phase one consisted of the integration of secure anti-jam UHF radios, an upgrade to the weapons control and Joint Tactical Air Operations data link software (S/W), and development of a Chemical, Biological and Radiological protection capability. These improvements have already been incorporated into the MCE production line. The current R&D includes the integration of a Joint Tactical Information Distribution System (JTIDS)/Tactical Digital Information Link-J (TADIL-J) capability, the integration of an Automated Air Tasking Order (AATO) capability, integration of secure anti-jam VHF (SINCGARS) radios and upgrades to the Ground Mobile Forces/Satellite Communications digital communications interfaces. This program also includes production funding for JTIDS terminals, JTIDS Modules (JMs), JTIDS Interface Boxes (JIBs) and Operations Modules (OM) Interface Kits, all of which are required to integrate JTIDS/COMM into the MCE. The planned phase includes a software interoperability upgrade to the TADIL-J Reissue 2 baseline, which works towards a Theater Missile Defense capability and the implementation of the Interim JTIDS Message Specification. This program is in budget activity 7 - Operational System Development, Research Category 6.6 because the Ground Theater Air Control System (GTACS) is a fielded, operational system currently undergoing major modifications/upgrades

(U) FY 1995 ($ in Thousands)

(U) 720 Completed MCE P3I OM Interface Kit development.
(U) 580 Completed JIB development.
(U) 810 Continued JM development. Effort completed 1 QTR FY96.
(U) 2,354 Started development of interoperability upgrades to the MCE P3I system.
(U) 2,091 Continued program support, test, and other miscellaneous efforts.
(U) 6,555 Total

(U) FY 1996 ($ in Thousands)

(U) 152 Continue development of interoperability upgrades to the MCE P3I system.
(U) 90 Continue program support, test, and other miscellaneous efforts.
(U) 242 Total

(U) FY 1997 ($ in Thousands)

(U) 274 Continue development of interoperability upgrades to MCE P3I system.
(U) 348 Continue program support, test, and other miscellaneous efforts.
(U) 622 Total

B. Program Change Summary ($ in Thousands)

FY 1995 FY 1996 FY 1997 Total

Cost

(U) Previous President's Budget (FY1997) 6,922 290 651 TBD
(U) Appropriated Value 7,383 290
(U) Adjustments to Appropriated Value
a. General Congressional Reductions -461 -6
b. Below Threshold Reprogramming -212
c. SBIR -146
d. Omnibus / Other Above Threshold Reprogramming
(U) Adjustments to Budget since FY96 PB -9 -42 -29
(U) Current Budget Submit/President's Budget 6,555 242 622 TBD

(U) Change Summary Explanation:

Funding: FY97 reduction (-29) is due to a revised inflation rate.

Schedule: None

Technical: None

(U) C. Other Program Funding Summary ($ in Thousands)

FY 1995 FY 1996 FY 1997 FY 1998 FY 1999 FY 2000 FY 2001 To

Compl

Total

Cost

(U) Other Procurement AF Total 54,121 18,197 10,007 28,357 24,724 21,190 20,063 Cont TBD
Budget Activity 3, WSC 833040 47,955 7,472 4,011 22,847 22,897 20,649 20,063 Cont TBD
Budget Activity 3, WSC 834010 0 0 0 0 0 0 0 0 TBD
Budget Activity 3, WSC 83790A 0 0 0 0 0 0 0 0 0
Budget Activity 4, WSC 84590A 6,166 0 0 0 0 0 0 0 6,166
Budget Activity 6, WSC 86190A 0 10,725 5,993 5,510 1,827 541 0 Cont TBD

(U) D. Schedule Profile

FY 1995 FY 1996 FY 1997

1 2 3 4 1 2 3 4 1 2 3 4
(U) MCE P3I OM Interface Kit First

Article Award

*
(U) MCE P3I OM Interface Kit

Development

*
(U) MCE P3I OM Interface EMD

DT&E

x
(U) MCE P3I OM Interface Kit Follow-

on Production Award

x
(U) MCE P3I OM Interface Kit Article

IOT&E

x
(U) MCE P3I Initial Operational

Capability (IOC)

x
(U) JIB Development Complete x
(U) JM Development Award
(U) JM Development Complete x
(U) AATO Development Complete x
(U) AATO IOC x

(U) A. Project Cost Breakdown ($ in Thousands)

FY 1995 FY 1996 FY 1997
(U) Product Development 4,217 152 274
(U) Support and Management 1,618 90 148
(U) Test and Evaluation 720 0 200
(U) Total 6,555 242 622

(U) B. Budget Acquisition History and Planning Information ($ in Thousands)

Not Applicable.