| COST ($ In Thousands) | FY 1995 Actual | FY 1996 Estimate | FY 1997 Estimate | FY 1998 Estimate | FY 1999 Estimate | FY 2000 Estimate | FY 2001 Estimate | Cost to Complete | Total Cost | |
| P771 | JTIDS | 10,975 | 9,124 | 11,075 | 9,449 | 9,525 | 9,910 | 10,175 | Continuing | TBD |
(U) A. Mission Description and Budget Item Justification
Joint Tactical Information Distribution System (JTIDS) effort provides the Army, Navy, Air Force, and Marine Theater Command and Control (C2) elements with a secure, jam-resistant, high capacity data link communications system for use in a tactical combat environment. JTIDS is the communications component of the Tactical Digital Information Link (TADIL) designated Link-16, and is synonymous with the TADIL J message standard. The JTIDS family of terminals (Class 2 and 2H for the Air Force, Navy and Marine Corps; and 2M for Army) is a joint development program which employs Time Division Multiple Access (TDMA), and spread spectrum techniques. JTIDS permits rapid and secure exchange of essential command control, and status information with all terminals in the tactical theater. Host platforms (i.e. E-3, E-8, F-15, RIVET JOINT, ABCCC, MAOC, and MCE) program and budget for JTIDS production terminals.
(U) P Y 1995
| (U) 3,700 | PROGRAMS: Efforts associated with Acquisition and Integration of Class 2/2H and Fighter Data Link Terminals.
-- (U) System integration and software development for E-3, E-8, F-15, RIVET JOINT, ABCCC, and MCE. -- (U) Prepare DAB materials and procurement package |
| (U) 2,100 | INTEGRATION/INTEROPERABILITY: Efforts associated with Integration of terminals and insuring Link-16 operates
effectively across all platforms |
| -- (U) Provided support and on-site Enhanced JTIDS System Exerciser (EJSE) operators for host platform developers and integrators. | |||||||
| -- (U Continued Affordability/Manufacturing Technology Demonstration (AMTD) bench tests at Eglin AFB. |
| (U) 3,575 | SUSTAINMENT: Efforts associated with ensuring fielded terminals are supported.
-- (U) Integrated Software Support Activity (ISSA) technical engineering software support at Warner Robins AFB -- (U) Class 2 terminal logistics support (PRE-OP) |
| (U) 1,600 | TEST: Efforts associated with fielding terminals
-- (U) IOT&E for MCEs, JSTARS, RIVET JOINT, Class 2M Terminal -- (U) F-15 Operational Special Project (OSP) Complete -- (U) Verified MIP correction and support E-8, ABCCC and MCE development efforts -- (U) Supported AF host platform participation in joint exercises in Ballistic Missile Defense demonstrations |
| (U) 10,975 | TOTAL |
(U) FY 1996
| (U) 1,402 | PROGRAMS: Efforts associated with Acquisition and Integration of Class 2/2H and Fighter Data Link (FDL) terminals
-- (U) Write and administer contracts for E-3, E-8, F-15, RIVET JOINT, Cobra Ball, ABCCC, MAOC, and MCE platforms. -- (U) F-15 FDL Acquisition and Integration. --- Integration of Link-16 into F-15 C/D and F-15 E. --- FDL System Spec Development. --- Interface Control Document (ICD) Development --- Test Plan Development. --- Technical support to JTIDS Operations at Mountain Home AFB and Nellis AFB. -- (U) Command and Control (C2) Terminal Acquisition Support. --- Determine terminal technical and configuration requirements --- Establish delivery schedule; establish maintenance plans --- Establish maintenance training schedules. |
| (U) 1,233 | INTEGRATION: Efforts associated with integration of terminals into the various platform
-- (U) On-going integration support to AWACS, Rivet Joint, ABCCC, MAOC, MCE, JSTARS, and F-22. -- (U) Technical Improvements: --- Technical support to AF Platforms to integrate Pre-Planned Product Improvements (P3I) --- Assist in processing P3I; -- (U) Field Support for F-15 Operations. --- Provide two sheltered JTIDS systems (SJSs) to Nellis AFB --- Support flight training, exercises, and scenario development/demonstrations --- Support Data Link Utility Evaluation through OSP and follow-on activities --- Support F-15 Electronic Combat Identification (CID) Development Test and Engineering (DT&E) and follow-on activities. -- (U) Provide technical assistance to Boost Phase Intercept Programs. --- High Gear Program: Testing sensor tracking of theater missile --- Airborne Interceptor: Establish procedures for intercepting theater missile. |
| (U) 1,603 | INTEROPERABILITY: Efforts associated with ensuring Link-16 operates effectively across all host platforms.
-- (U) AF platform interoperability. --- Support Multi-Service Interoperability Tests. --- Support All Service Combat Identification Evaluation Team (ASCIET) tests. --- Support to Engineering Interoperability Review Groups (IORGS US/UK bilateral) --- Support definition of Link-16 Network Structures to support Interoperability. -- (U) Network Support. --- Air Force Network Design ---- Provide Network Design Expertise. ---- Determine Network Design for Integration Testing. ---- Provide Network Design for Integration Testing. ---- Maintain AF Network Design Aid for Operations. ---- Evaluate Navy Network Design Aid for ACC Users. --- Investigate internet-networking of JTIDS and Transport Control Protocol Internet Protocol Networks. |
| (U) 2,842 | SUSTAINMENT: Efforts associated with ensuring fielded terminals are supported.
-- (U) ISSA technical engineering software support at Warner Robins AFB. -- (U) Class 2/2H Technical Manual updates. -- (U) Class 2 Log support (PRE-OP). -- (U) Maintain and upgrade the SJSs, Link-16 Winnebagos. -- (U) Maintain and upgrade the MULTI-LINK Translator and Display System (MTDS) prototype hardware. |
| (U) 2,044 | TEST: Efforts associated with fielding terminals
-- (U) Support provided by the 46th Test Squadron --- Software Support --- Platform integration support --- Product Improvement and Special Projects Support --- Regression Test and Integration --- Product Improvement/Development Support |
| (U) 9,124 | TOTAL |
| (U) FY1997 | |
| (U) 1,144 | PROGRAMS: Efforts associated with Acquisition and Integration of Class 2/2H and Fighter Data Link.
-- (U) Class 2/2H Terminals. --- Write and administrate contracts for E-3, E-8, F-15, RIVET JOINT, Cobra Ball, ABCCC, MAOC, and MCE platforms. -- (U) F-15 FDL Acquisition and Integration. --- Integration of Link-16 into F-15 C/D and F-15E. --- FDL System Spec Development. --- Interface Control Document (ICD) Development --- Test Plan Development. --- Technical support to JTIDS Operations at Mountain Home AFB and Nellis AFB. -- (U) Command and Control (C2) Terminal Acquisition Support. --- Determine Terminal Technical and Configuration Requirements --- Establish delivery schedule. --- Coordinate Spare Requirements --- Establish Maintenance Plans --- Establish Maintenance Training Schedules. |
| (U) 2,449 | INTEGRATION: Continue efforts associated with integration of terminals into the various platforms.
-- (U) On-going integration support to AWACS, Rivet Joint, ABCCC, MAOC, MCE, JSTARS, and F-22. -- (U) Technical Improvements: --- Technical support to AF Platforms to integrate Pre-Planned Product Improvements (P3I) --- Assist in processing P3I; -- (U) Field Support for F-15 Operations. --- Provide two shelterized JTIDS systems (SJSs) to Nellis AFB --- Support flight training, exercises, and scenario development/demonstrations --- Support Data Link Utility Evaluation through Operational Special Project (OSP) and follow-on activities --- Support F-15 Electronic Combat Identification (CID) DT&E and Follow-on Activities. -- (U) Provide technical assistance to Boost Phase Intercept Programs. --- High Gear Program: Testing sensor tracking of Theater Missile --- Airborne Interceptor: Establish procedures for intercepting Theater Missile. |
| (U) 3,689 | INTEROPERABILITY: Efforts associated with ensuring Link-16 operates effectively across all Host Platforms.
-- (U) AF Platform Interoperability. --- Support multi-service interoperability tests. --- Support All Service Combat Identification Evaluation Team (ASCEIT) tests. --- Support to Engineering Interoperability Review Groups (IORGS US/UK bilateral) --- Support definition of Link-16 network structures to support Interoperability. --- Develop Enhanced Position Location Radio System (EPLRS)/Link-16 gateway -- (U) Network Support. --- Air Force Network Design ---- Provide network design expertise. ---- Determine network design for integration testing. ---- Provide network design for integration testing. ---- Maintain AF network design aid for operations. ---- Evaluate Navy network design aid for ACC users. --- Investigate internet-networking of JTIDS and transport control internet protocol networks. |
| (U) 1,507 | SUSTAINMENT: Efforts associated with ensuring fielded terminals are supported.
-- (U) ISSA technical engineering software support at Warner Robins AFB. -- (U) Maintain and upgrade the SJSs, Link-16 Winnebagos. -- (U) Maintain and upgrade the MULTI-LINK Translator and Display System (MTDS) prototype hardware. |
| (U) 2,286 | TEST: Efforts associated with fielding terminals
-- (U) Support provided by the 46th Test Squadron --- Software support --- Platform integration support --- Product improvement and special projects support --- Regression test and integration --- Product improvement/development support |
| (U) 11,075 | TOTAL |
(U) B. Program Change Summary ($ in Thousands)
| FY 1995 | FY 1996 | FY 1997 | Total
Cost | |
| (U) Previous President's Budget (FY 1996) | 10,978 | 10,146 | 9,594 | 30,718 |
| (U) Appropriated Value | 11,634 | |||
| (U) Adjustments to Appropriated Value | ||||
| a. General Congressional Reduction | -444 | -596 | -519 | |
| b. Small Business Innovative Research | -215 | -217 | ||
| c. Omnibus and Other Above Threshold Reprogrammings | -209 | |||
| (U) Adjustments to Budget Years Since FY96 PB | 2,000 | |||
| (U) Current Budget Submit/President's Budget | 10,975 | 9,124 | 11,075 | 31,280 |
(U) Change Summary Explanation:
Funding: FY 1997 increased $2M for development of an EPLRS/Link-16 gateway.
Schedule: Joint STARS IOT&E slipped from Feb 96 to May 96 due to test re-structuring.
Technical: None
(U) C. Other Program Funding Summary ($ in Thousands)
| FY 1996 | FY 1997 | FY 1998 | FY 1999 | FY 2000 | FY 2001 | To
Complete |
Total
Cost | |
| (U) Other Proc AF, PE 27419F (ABCCC) | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 4,800 |
| (U) Other Proc AF, PE 27417F (AWACS) | 24,200 | 33,600 | 4,300 | 3,300 | 300 | 0 | 0 | 99,100 |
| (U) Other Proc AF, PE 27581F (JSTARS) | 5,500 | 5,600 | 3,400 | 3,500 | 3,500 | 2,000 | 0 | 39,400 |
| (U) Other Proc AF, PE 27412F (MCE) | 0 | 0 | 6,500 | 22,100 | 15,000 | 0 | 0 | 150,400 |
| (U) Other Proc AF, PE 35154F (AIA) | 2,000 | 4,400 | 6,300 | 6,400 | 6,500 | 6,200 | 0 | 31,800 |
- (U) Related RDT&E:
(U)- Program Element #64770F E-8 (Joint STARS)
(U)- Program Element #27417F, E-3 (AWACS)
(U)- Program Element #27412F Modular Control Equipment (MCE)
(U)- Program Element #27419F Airborne Battlefield Command and Control Center (ABCCC)
(U)- Program Element #35154F AIA.
(U) D. Schedule Profile
| FY 1995 | FY 1996 | FY 1997 |
| 1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 | 1 | 2 | 3 | 4 | |
| (U) Acquisition Milestones | ||||||||||||
| - Milestone III FRP Class 2/2H | XX | |||||||||||
| - LRIP Decision Class 2M | XX | |||||||||||
| - Milestone III FRP 2M | XX | |||||||||||
| (U) T&E Milestones | ||||||||||||
| - F-15 OSP Complete | XX | |||||||||||
| - MCE IOT&E | XX | |||||||||||
| - JSTARS IOT&E | XX | |||||||||||
| - MS OT-III | XX | |||||||||||
| - RIVET JOINT IOT&E | XX | |||||||||||
| - IOT&E Class 2M | XX | |||||||||||
| (U) Contract Milestones | ||||||||||||
| - FRP Class 2/2H | XX | |||||||||||
| - LRIP Contract Award Class 2M | XX | |||||||||||
| - FRP Class 2M | XX | |||||||||||
(U) A. Project Cost Breakdown ($ in Thousands)
| FY 1995 | FY 1996 | FY 1997 | |
| (U) Programs | 3,700 | 1,402 | 1,144 |
| (U) Integration | 2,100 | 1,233 | 2,449 |
| (U) Interoperability | *Note 1 | 1,603 | 3,689 |
| (U) Sustainment | 3,575 | 2,842 | 1,507 |
| (U) Test | 1,600 | 2,044 | 2,286 |
| (U) Total | 10,975 | 9,124 | 11,075 |
NOTE 1: In FY 1995 Interoperability is included in the Integration line.
(U) B. Budget Acquisition History and Planning Information ($ in Thousands)
Performing Organizations:
| Contractor or Government Performing Activity | Contract Method/Type or Funding Vehicle |
Award or Obligation Date |
Performing Activity EAC |
Project Office EAC |
Total
Prior to FY 1995 |
Budget
FY 1995 |
Budget
FY 1996 |
Budget
FY 1997 |
Budget to Complete | Total Program |
| Product Development Organizations |
| GEC-MARCONI | FFP | DEC 85 | 80,727 | 80,727 | 59,143 | 1,027 | 280 | 2,297 | Continue | TBD |
| LOCKHEED | FFP | JUN 93 | 3,373 | 3,373 | 3,373 | 1,288 | 0 | 0 | Continue | 3,373 |
| GEC-MARCONI | FFP | JUN 93 | 850 | 850 | 850 | 0 | 0 | 0 | Continue | 850 |
| CACD | FFP | JUN 93 | 1,072 | 1,072 | 1,072 | 0 | 0 | 0 | 0 | 1,072 |
| MCAIR | CPFF | MAR 94 | 2,434 | 2,434 | 2,434 | 0 | 0 | 0 | 0 | 2,434 |
| RADC | PO/616 | Various | Various | Various | 1,913 | 757 | 0 | 0 | 0 | 2,670 |
| WR-ALC | PO/616 | Various | Various | Various | 1,405 | 1,104 | 457 | 254 | 0 | 3,220 |
| NADEP | MIPR | Various | Various | Various | 413 | 382 | 0 | 0 | 0 | 795 |
| ACSI | FFP | SEP 94 | 445 | 445 | 445 | 0 | 0 | 0 | 0 | 445 |
| Support and Management Organizations |
| ESC | Various | Various | 26,600 | 26,600 | 16,390 | 1,119 | 2,937 | 2,335 | Continue | TBD |
| CONTRACTOR SUPPORT | Various | Various | 52,457 | 52,457 | 35,741 | 1,649 | 1,825 | 1,989 | Continue | TBD |
| MITRE | FPLOE | Various | 89,854 | 89,854 | 70,590 | 4,604 | 3,072 | 2,450 | Continue | TBD |
| Test and Evaluation Organizations |
| MT HOME AFB | PO/616 | Various | Various | Various | 83 | 333 | 416 | |||
| EGLIN AFB | PO/616 | Various | Various | Various | 50 | 553 | 1,750 | Continue | TBD |
Government Furnished Property: N O T A P P L I C A B L E
| Subtotal Product Development | 71,048 | 3,270 | 737 | 2,551 | Continue | TBD |
| Subtotal Support and Management | 122,721 | 7,372 | 7,834 | 6,774 | Continue | TBD |
| Subtotal Test and Evaluation | 133 | 333 | 553 | 1,750 | Continue | TBD |
| Total Project | 193,902 | 10,975 | 9,124 | 11,075 | Continue | TBD |