
|
COST (In Thousands) |
FY 1996 Actual |
FY 1997 Estimate |
FY 1998 Estimate |
FY 1999 Estimate |
FY 2000 Estimate |
FY 2001 Estimate |
FY 2002 Estimate |
FY 2003 Estimate |
Cost to Complete |
Total Cost |
|
|
Total Program Element (PE) Cost |
|||||||||||
Mission Description and Budget Item Justification
: The changing global threat and the new Army Warfighting Doctrine developed to respond to this changing threat all significantly impact the mission of Air Defense Artillery (ADA). This doctrine calls for U.S. forces to be able to win two nearly simultaneous major regional conflicts and to conduct combat operations characterized by rapid response and a high probability of success while minimizing the risk of significant American casualties. ADA must continually be upgraded and modernized in accordance with the ADA missions. The FY 98 budget funds critical improvements to PATRIOT and Stinger. These projects support development of upgrades to current equipment and are appropriately funded in Budget Activity 7.|
COST (In Thousands) |
FY 1996 Actual |
FY 1997 Estimate |
FY 1998 Estimate |
FY 1999 Estimate |
FY 2000 Estimate |
FY 2001 Estimate |
FY 2002 Estimate |
FY 2003 Estimate |
Cost to Complete |
Total Cost |
|
|
PATRIOT Product Improvement Program |
43137 |
46280 |
12388 |
9474 |
5777 |
4768 |
0 |
0 |
0 |
401886 |
A. Mission Description and Justification D036 - PATRIOT Product Improvement Program:
The PATRIOT system is being upgraded through a series of individual materiel changes (MC) culminating in the attainment of the PATRIOT Advanced Capability - 3 (PAC-3) system. The communication upgrades improve PATRIOT’s above and below battalion communication equipment. These changes eliminate PATRIOT peculiar communications equipment and improve PATRIOT’s interoperability between systems and between the services.Acquisition Strategy: The design objective of the PATRIOT system was to provide a baseline system capable of being modified to cope with the evolving threat. This alternative minimizes technological risks and provides a means of enhancing system capability through planned upgrades of deployed systems. The PATRIOT Program consists of two interrelated acquisition programs - The PATRIOT Growth Program and the PAC-3 Missile Program. Growth program modifications are grouped into configurations which are scheduled to be fielded in the same time-frame. Configuration groupings are a convenience for managing block changes of hardware and software and are not a performance-related grouping. However, incremental increases in performance will be determined for each configuration in order to provide benchmarks for configuration testing and for the development of user doctrine and tactics.
FY 1996 Accomplishments:
|
5226 |
P3I test program |
|
|
3978 |
Communications upgrades |
|
|
750 |
Responsive threat analysis |
|
|
33183 |
Anti-Cruise Missile upgrade |
|
|
Total |
43137 |
FY 1997 Planned Program:
|
5326 |
P3I test program |
|
|
5667 |
Communications upgrades |
|
|
750 |
Responsive threat analysis |
|
|
33437 |
Anti-Cruise Missile upgrade |
|
|
1100 |
Small Business Innovation Research/Small Business Technology Transfer (SBIR/STTR) Programs |
|
|
Total |
46280 |
FY 1998 Planned Program:
|
5675 |
P3I test program |
|
|
2960 |
Communication upgrade |
|
|
750 |
Responsive threat |
|
|
3003 |
Horizontal Battlefield Digitization |
|
|
Total |
12388 |
FY 1999 Planned Program:
|
5718 |
P3I test program |
|
|
750 |
Responsive threat |
|
|
3006 |
Horizontal Battlefield Digitization |
|
|
Total |
9474 |
|
B. Project Change Summary |
FY 1996 |
FY 1997 |
FY 1998 |
FY 1999 |
|
FY 1997 President’s Budget |
46477 |
12291 |
9406 |
6481 |
|
Appropriated Value |
47823 |
46280 |
||
|
Adjustments to Appropriated Value |
-4686 |
|||
|
FY 1998 President’s Budget Request |
43137 |
46280 |
12388 |
9474 |
Change Summary Explanation: Funding: FY 1996: Undistributed Congressional reductions/rescissions (-2488); reprogramming to higher priority requirements (-2198).
FY 1998: Funding increase for Horizontal Battlefield Digitization (+2982).
FY 1999: Funding increase for Horizontal Battlefield Digitization (+2993).
|
C. Other Program Funding Summary Missile Procurement, Army |
FY 1996 |
FY 1997 |
FY 1998 |
FY 1999 |
FY 2000 |
FY 2001 |
FY 2002 |
FY 2003 |
To Complete |
Total Cost |
|
Budget Activity 2 - PATRIOT (C49100) |
4924 |
0 |
349109 |
369885 |
459233 |
445367 |
433145 |
396760 |
|
12087483 |
|
Budget Activity 3 - PATRIOT Mod (C50700) |
6767 |
23442 |
20825 |
15575 |
19589 |
24310 |
19894 |
16544 |
39645 |
565916 |
|
D. Schedule Profile |
FY 1996 |
FY 1997 |
FY 1998 |
FY 1999 |
||||||||||||
|
1 |
2 |
3 |
4 |
1 |
2 |
3 |
4 |
1 |
2 |
3 |
4 |
1 |
2 |
3 |
4 |
|
|
Development Test & Evaluation |
X |
|||||||||||||||
|
A. Project Cost Breakdown |
FY 1996 |
FY 1997 |
FY 1998 |
FY 1999 |
|
Contract Engineering Support |
37376 |
37926 |
6963 |
4006 |
|
Program Management Support |
1301 |
1436 |
1691 |
1291 |
|
Developmental Test and Evaluation |
4460 |
5818 |
3734 |
4177 |
|
SBIR/STTR |
1100 |
|||
|
Total |
43137 |
46280 |
12388 |
9474 |
B. Budget Acquisition History and Planning Information
Performing Organizations
|
Contractor or Government Performing Activity |
Contract Method/Type or Funding Vehicle |
Award or Obligation Date |
Performing Activity EAC |
Project Office EAC |
Total Prior to FY 1996 |
FY 1996 |
FY 1997 |
FY 1998 |
FY 1999 |
Budget to Complete |
Total Program |
|
Product Development Organizations |
|||||||||||
|
Raytheon |
|||||||||||
|
DAAH0182CA181 |
3722 |
3722 |
|||||||||
|
DAAH0187CA025 |
22455 |
22455 |
|||||||||
|
DAAH0189C0458 |
23228 |
23228 |
|||||||||
|
DAAH0192C0036 |
5000 |
5000 |
|||||||||
|
Small Contracts |
1168 |
1168 |
|||||||||
|
General Electric |
|||||||||||
|
DAAH0187CA006 |
4824 |
4824 |
|||||||||
|
Brunswick Corp. |
|||||||||||
|
DAAH0189C0167 |
3100 |
3100 |
|||||||||
|
Martin Marietta |
|||||||||||
|
DAAH0192C0301 |
SS/CPFF |
15Jul92 |
5463 |
5463 |
3763 |
100 |
3863 |
||||
|
Raytheon |
|||||||||||
|
DAAH0191C0602 |
SS/CPIF |
22Apr92 |
20702 |
20702 |
23077 |
23077 |
|||||
|
DAAH0192C0006 |
SS/CPAF |
27Jan92 |
56460 |
56460 |
|||||||
|
DAAH0195C0043 |
SS/CPAF |
01Feb95 |
6005 |
4093 |
513 |
1000 |
1000 |
1690 |
14301 |
||
|
PAC 2 Anti-Cruise |
33183 |
32637 |
65820 |
||||||||
|
TPS |
200 |
200 |
|||||||||
|
RL-CEU |
4576 |
2960 |
7536 |
||||||||
|
Horiz Btlfld Digit |
3003 |
3006 |
6009 |
||||||||
|
SBIR/STTR |
1100 |
1100 |
|||||||||
|
Support and Management Organizations |
|||||||||||
| CAS | |||||||||||
|
DAAH0187CA008 |
2270 |
2270 |
|||||||||
|
DAAH0190C0487 |
6266 |
6266 |
|||||||||
|
DAAH0194C0105 |
C/CPAF |
31Jan94 |
5344 |
791 |
791 |
791 |
422 |
8139 |
|||
|
In-House Support |
10817 |
510 |
1436 |
900 |
500 |
1163 |
15326 |
||||
|
Test and Evaluation Organizations |
|||||||||||
|
Missile Command |
1095 |
2322 |
1098 |
1882 |
1000 |
700 |
1312 |
8314 |
|||
|
White Sands Missile Range |
1095/MIPR |
|
|
|
2841 |
1370 |
2596 |
1534 |
1737 |
2843 |
12921 |
|
Other Govt Agen |
MIPR |
2023 |
1992 |
1340 |
1200 |
1740 |
3115 |
11410 |
|||
|
RDEC and Other Govt Agent |
95377 |
95377 |
|||||||||
Government Furnished Property: None.
|
Subtotal Product Development |
152802 |
37376 |
39026 |
6963 |
4006 |
1690 |
241863 |
|
Subtotal Support and Management |
24697 |
1301 |
1436 |
1691 |
1291 |
1585 |
32001 |
|
Subtotal Test and Evaluation |
102563 |
4460 |
5818 |
3734 |
4177 |
7270 |
128022 |
|
Total Project |
280062 |
43137 |
46280 |
12388 |
9474 |
10545 |
401886 |
|
COST (In Thousands) |
FY 1996 Actual |
FY 1997 Estimate |
FY 1998 Estimate |
FY 1999 Estimate |
FY 2000 Estimate |
FY 2001 Estimate |
FY 2002 Estimate |
FY 2003 Estimate |
Cost to Complete |
Total Cost |
|
|
Stinger Product Improvement Program |
16061 |
18277 |
5024 |
1957 |
27982 |
27984 |
39406 |
39456 |
Continuing |
Continuing |
A. Mission Description and Budget Item Justification: D303-Stinger Product Improvement Program: This project provides a product evolution of the STINGER-RMP to improve countermeasures capability via externally loaded software, which is downloaded from a reprogrammable module in the gripstock. This concept allows for timely upgrades to correct system deficiencies, rapid reaction to new threats or threat countermeasures, development of specialty software programs where full capability may not be desired, and accommodation of new missions. The Block I upgrade project, which adds a roll sensor and enhanced software, extends the missile service life, solves the recognized system performance deficiencies in countermeasures and other engagement conditions, and increases terminal accuracy. The Block II program is a development of an advanced infrared (IR) Focal Plane Array Seeker which improves the performance of the missile against an expanded target and in background clutter. The program develops the improved missile for adaptation to any or all of the STINGER firing platforms, extends the missile service life and establishes a government post deployment software support posture. The Block II Engineering, Manufacturing, Development (EMD) program provides for development to a performance specification, design qualification of guidance section conducted as part of the production qualification, and platform integration. A portion of funds in FY 1996 and FY 1997 will be used to develop MIL-STD 1760 launcher electronics to be fielded with the Apache Longbow Helicopter air-to-air requirements, based on Joint Service (U.S. Air Force and U.S. Army) doctrine. The air-to-air requirement satisfies three tasks: self protection, protect force, and augmentation of air defense forces. Funding in FY 1996 and FY 1997 in this project also supports an eight nation Memorandum of Understanding (MOU) signed by the Office of Secretary of Defense in 1994 for the conduct of a two-year competitive Feasibility Study on NATO Very Short Range Air Defense Systems (VSHORADS) and Short Range Air Defense Systems (SHORADS). The output of the Feasibility Study will form the basis for the development of a VSHORADS/SHORADS NATO Staff Requirement and information to support the development of a follow-on system to STINGER.
Acquisition Strategy: The Block I development program is a Sole Source (SS)/Cost Plus Incentive Fee (CPIF) contract awarded in 1992. The Block II development began FY 1993 as Technology Base Broad Agency announcement with a SS/Cost Plus Fixed Fee (CPFF) contract. Current SS/CPFF contract awarded 1996 for pre-EMD, EMD start FY 2000, MS IIIa FY 2005, and FUE FY 2007. A SS/CPIF contract for MIL-STD Launcher electronics development is planned for mid-FY 1997. The VSHORADS/SHORADS Competitive/Firm Fixed Price (FFP) contract was awarded to two international consortia. The United Kingdom was designated as the Pilot Nation, serving as Contracting Authority.
FY 1996 Accomplishments:
|
2007 |
Conducted testing of Block I Phase II Software |
|||
|
1019 |
Completed Block I Phase II Software Design; performed Block I Software Critical Design Review and release Engineering Change Proposal |
|||
|
493 |
Initiated Block I performance assessment |
|||
|
4238 |
Fabricated/tested second Block II Seeker Head |
|||
|
FY 1996 Accomplishments: (continued) |
||||
|
3088 |
Initiated Block II electronics state-of-the-art packaging (miniaturization) of electronics section |
|||
|
1434 |
Upgraded Block II Seeker to correct limitations discovered in initial development |
|||
|
1040 |
Initiated development of contractor Block II Simulation and defined Platform versus Block II interfaces |
|||
|
1127 |
Initiated development of Stinger Universal Electronics for MIL-STD 1760 launcher which supports digital electronic-based systems. |
|||
|
575 |
Conducted Bradley linebacker concept studies |
|||
|
200 |
VSHORADS/SHORADS international proposal evaluation/negotiations/contract awards |
|||
|
840 |
VSHORADS/SHORADS technology and subsystem development |
|||
|
Total |
16061 |
|||
FY 1997 Planned Program:
|
702 |
Complete Block I performance assessment |
|
|
2435 |
Initiate development of Unmanned Aerial Vehicle (UAV) specific software |
|
|
|
531 |
UAV software performance analysis |
|
3898 |
Produce prototype Block II electronics state of the art packaging (miniaturization) of electronics section |
|
|
4811 |
Integration of Block II tactical-sized guidance assembly |
|
|
2191 |
Perform valuation of Block II guidance assembly |
|
|
2202 |
VSHORADS/SHORADS system variants development and evaluation of system variants |
|
|
1061 |
Continue development of MIL-STD 1760 Launcher electronics |
|
|
446 |
Small Business Innovation Research/Small Business Technology Transfer (SBIR/STTR) Programs |
|
|
Total |
18277 |
FY 1998 Planned Program:
|
1450 |
Finalize Block II packaging and fabricate one tactical size guidance section |
|
|
1464 |
Design and package Block II control section |
|
|
460 |
Initiate development of contractor hardware-in-the-loop flight simulations |
|
|
1650 |
Complete VSHORADS/SHORADS Feasibility Study and Forward NATO Staff Requirement |
|
|
Total |
5024 |
FY 1999 Planned Program:
|
735 |
Design/fabricate/evaluate three Block II launch tube and end cap units |
|
|
840 |
Continue Contractor Hardware-in-the Loop Flight Simulations |
|
|
382 |
Block II airframe dynamic analysis/performance prediction |
|
|
Total |
1957 |
|
B. Project Change Summary |
FY 1996 |
FY 1997 |
FY 1998 |
FY 1999 |
|
FY 1997 President’s Budget |
13662 |
18668 |
2314 |
2849 |
|
Appropriated Value |
14046 |
18277 |
||
|
Adjustments to Appropriated Value |
2015 |
|||
|
FY 1998 President’s Budget Request |
16061 |
18277 |
5024 |
1957 |
Change Summary Explanation: Funding: FY 1996: Funding reprogrammed for OSD International MOU program, Bradley concept studies, and launcher electronics design (+2743); project decrement for undistributed congressional reductions and rescissions (-728).
FY 1998: Funding reprogrammed to support Block II development effort (+2710).
FY 1999: Funding reprogrammed to higher priority requirements (-892).
Schedule: None
Technical: Block II EMD risk reduction initiatives FY 1998-99
|
C. Other Program Funding Summary |
FY 1996 |
FY 1997 |
FY 1998 |
FY 1999 |
FY 2000 |
FY 2001 |
FY 2002 |
FY 2003 |
To Compl |
Total Cost |
|
Missile Procurement, Army |
||||||||||
|
Budget Activity 2 - Stinger (C18500) |
1143340 |
|||||||||
|
Budget Activity 3 - Stinger Mods (C20000) |
9804 |
29742 |
8710 |
14403 |
24086 |
34519 |
40108 |
31872 |
Cont’d |
Cont’d |
|
Budget Activity 3 - BSFV-E Mods (C21500) |
1500 |
7118 |
3701 |
10 |
16866 |
26866 |
Cont’d |
Cont’d |
|
D. Schedule Profile |
FY 1996 |
FY 1997 |
FY 1998 |
FY 1999 |
||||||||||||
|
1 |
2 |
3 |
4 |
1 |
2 |
3 |
4 |
1 |
2 |
3 |
4 |
1 |
2 |
3 |
4 |
|
|
Block I CDR Software ECP |
X |
|||||||||||||||
|
Block I Performance Assessment |
X |
|||||||||||||||
|
Complete Block I Flight Tests |
X |
|||||||||||||||
|
Initiate Future Software Development |
X |
|||||||||||||||
|
Initiate Block II Guidance Section
Integration Design |
X |
|||||||||||||||
|
Complete Block II Tactical Size Electronics |
X |
|||||||||||||||
|
Complete Block II Guidance Section Integration |
X |
|||||||||||||||
|
Complete Integration of Guidance Hardware with Contractor Simulation |
X |
|||||||||||||||
|
FY 1996 |
FY 1997 |
FY 1998 |
FY 1999 |
|
|
Project Management In-House |
821 |
1199 |
414 |
75 |
|
RDEC Engineering Support |
2334 |
3843 |
200 |
159 |
|
Major Development Contractor |
11097 |
10448 |
2760 |
1723 |
|
Contracted Services |
727 |
97 |
||
|
Other Government Agencies |
42 |
42 |
||
|
UK MOU Contractor |
643 |
1732 |
1207 |
|
|
UK Management Office |
106 |
176 |
124 |
|
|
UK MOU U.S. Program Support |
291 |
294 |
319 |
|
|
SBIR/STTR |
446 |
|||
|
Total |
16061 |
18277 |
5024 |
1957 |
B. Budget Acquisition History and Planning Information
Performing Organizations
|
Contractor or Government Performing Activity |
Contract Method/Type or Funding Vehicle |
Award or Obligation Date |
Performing Activity EAC |
Project Office EAC |
Total Prior to FY 1996 |
FY 1996 |
FY 1997 |
FY 1998 |
FY 1999 |
Budget to Complete |
Total Program |
|
|
Product Development Organizations |
||||||||||||
|
Hughes Msl Sys |
||||||||||||
|
DAAH0192C0213 |
SS-CPIF |
Apr 92 |
20606 |
18224 |
2382 |
20606 |
||||||
|
Future S/W Upgrd |
TBD |
TBD |
2105 |
2105 |
||||||||
|
DAAH0193CR127 |
SS-CPIF |
Apr 93 |
4629 |
4629 |
4629 |
4629 |
||||||
|
DAAH0196C0180 |
SS-CPFF |
Mar 96 |
6750 |
7196 |
13946 |
|||||||
|
BLOCK II 98-99 |
SS-CPIF |
TBD |
2760 |
1723 |
4483 |
|||||||
|
Block II EMD |
SS-CPIF |
TBD |
125805 |
125805 |
||||||||
|
DAAH0195C0028 |
SS-CPFF |
Sep 96 |
1965 |
1965 |
||||||||
|
SUE Dev |
SS-CPIF |
Apr 97 |
841 |
841 |
||||||||
|
Targets Mgt Ofc |
MIPR |
Apr 94 |
2100 |
2100 |
||||||||
|
Targets Mgt Ofc |
MIPR |
Various |
12013 |
12013 |
||||||||
|
BSFV Aggregate |
Various |
Various |
7025 |
7025 |
||||||||
|
Block I Aggregate |
Various |
Various |
8152 |
50 |
52 |
8254 |
||||||
|
PMO/RDEC |
Allot/1095 |
Various |
3155 |
4902 |
614 |
234 |
54936 |
63841 |
||||
|
Blk II Contracted Svcs (Aggregate) |
Various |
Various |
181 |
8836 |
9017 |
|||||||
|
SUE Aggregate |
Various |
Various |
102 |
45 |
147 |
|||||||
|
Other Govt Agen |
MIPR |
Various |
42 |
42 |
3238 |
3322 |
||||||
|
SBIR/STTR |
446 |
446 |
||||||||||
|
British Aerospace |
C-FFP |
Jul 96 |
322 |
866 |
604 |
1792 |
||||||
|
Thomson-CSF |
C-FFP |
Aug 96 |
321 |
866 |
603 |
1790 |
||||||
|
UK Ministry of Defense (Mgt Ofc) |
MOU/1095 |
Dec 95 |
106 |
176 |
124 |
406 |
||||||
|
SBIR/STTR |
446 |
446 |
||||||||||
|
Support and Management Organizations |
||||||||||||
|
DLA90093D0011 |
SS-FFP |
Aug 96 |
575 |
575 |
||||||||
|
U.S. Prog Spt MOU VSHORAD/ SHORADS |
1095 |
Dec 95 |
291 |
294 |
319 |
904 |
||||||
|
Test and Evaluation Organizations: None |
||||||||||||
Government Furnished Property:
Not applicable|
Subtotal Product Development |
40311 |
15195 |
17983 |
4705 |
1957 |
204828 |
284979 |
|
Subtotal Support and Management |
866 |
294 |
319 |
1479 |
|||
| Subtotal Test and Evaluation | |||||||
|
Total Project |
40311 |
16061 |
18277 |
5024 |
1957 |
204828 |
286458 |
THIS PAGE INTENTIONALLY LEFT BLANK