COST ($ In Thousands)

FY 1996 Actual

FY 1997 Estimate

FY 1998 Estimate

FY 1999 Estimate

FY 2000 Estimate

FY 2001 Estimate

FY 2002 Estimate

FY 2003 Estimate

Cost to Complete

Total Cost

 

Quantity of RDT&E Articles

* Articles not separately priced in contract

(U) A. Mission Description and Budget Item Justification: The Airborne Laser (ABL) Program is an ACAT 1D program which will design, build and test a weapon system to acquire, track and kill Theater Ballistic Missiles (TBMs) in the boost phase. Two contractors are successfully executing the Concept Design phase (FY94-FY97) awarded in May 1994. The program recently awarded the ABL Program Definition and Risk Reduction (PDRR) contract to Boeing (Seattle) team in Nov 96, who will design, fabricate, integrate, and test the ABL design. The PDRR phase began in November 1996 and culminates with a lethality demonstration against a boosting TBM representative target. The PDRR phase will integrate and test all key technologies for a fully operational system, allowing the Air Force to advance to EMD in the FY2003 time frame. This program is in budget activity 4 - Demonstration and Validation since it is a major defense acquisition program which has been authorized to enter PDRR as of the Milestone I, Nov 96.

(U) Acquisition Strategy

(U) Milestone (MS) I decision was Nov 96 authorizing entry into PDRR; MS II for Engineering Manufacturing and Development in FY03; MS III Decision for Production in FY05. Program is designed to demonstrate technical risk reduction achievements at key junctures in the PDRR phase. These will form the basis for two Authority-To-Proceed decisions during PDRR. PDRR culminates with a lethality demonstration against a boosting theater ballistic missile in FY02.

(U) FY 1996 ($ in Thousands):

  • (U) $14,400

Continued both contractor Concept Design efforts: hardware/software, risk mitigation, modeling/simulations and specifications

  • (U) $5,960

Government environmental impact study; facility utilization, SPO operational support, modeling/simulations and risk reductions

  • (U) $20,360

Total

 

 

(U) FY 1997 ($ in Thousands):

  • (U) $12,000

Complete both Concept Design contracts

  • (U) $29,300

Initiate Boeing PDRR contract effort for design, fabrication, integration, and test. of ABL

  • (U) $255

Complete Environmental Impact Analysis contract

  • (U) $3,995

FFRDC/SETA support for special studies, simulations and analyses, technical support, risk management, and an independent review team specializing in lasers, aircraft and aircraft integration

  • (U) $8,677
  • (U) $54,227

In-house support for atmospheric characterization tests, labor, training, Integrated Product Team (IPT) participation, and other government agencies

Total

(U) FY 1998 ($ in Thousands):

  • (U) $144,921

Continue Boeing PDRR contract effort for design, fabrication, integration, and test of ABL

  • (U) $700

Portion of PDRR funds for minor modification to Birk facility at Edwards AFB by PDRR contractor. Project number FSPM981305

  • (U) $4,500

FFRDC/SETA support for special studies, simulations and analyses, technical support, risk management, and an independent review team specializing in lasers, aircraft, and aircraft integration

  • (U) $6,965

In-house support for atmospheric characterization tests, labor, training, Integrated Product Team (IPT) participation, and other government agencies

  • (U) $50

Government oversight of contractor modification to Birk facility at Edwards AFB. Project number FSPM981305

  • (U) $157,136

Total

(U) FY 1999 ($ in Thousands):

  • (U) $280,477

Continue Boeing PDRR contract effort for design, fabrication, integration, and test of ABL

  • (U) $1,825

Portion of PDRR funds for minor modification to Birk facility at Edwards AFB by PDRR contractor. Project number FSPM981305

  • (U) $5,500

FFRDC/SETA support for special studies, simulations and analyses, technical support, risk management, and an independent review team specializing in lasers, aircraft, and aircraft integration

  • (U) $8,619

In-house support for atmospheric characterization tests, labor, training, Integrated Product Team (IPT) participation, and other government agencies

  • (U) $175

Government oversight of contractor modification to Birk facility at Edwards AFB. Project number FSPM981305

  • (U) $296,596

Total

(U) B. Program Change Summary ($ in Thousands)

 

 

FY 1996

FY 1997

FY 1998

FY 1999

Total

Cost

(U) Previous President’s Budget

19,954

56,828

96,654

215,404

388,840

(U) Appropriated Value

19,954

56,828

     

(U) Adjustments to Appropriated Value

         

a. Cong Reductions

-424

-1137

   

-1561

b. SBIR

-388

-1391

   

-1779

c. Omnibus or Other Above Threshold Reprogram

-154

     

-154

d. Below Threshold Reprogramming

1494

     

1494

e. Recission

-122

-73

   

-195

(U) Adjustments to Budget Years Since FY1997 PB

   

60,482

81,192

141,674

(U) Current Budget Submit/President’s Budget

20,360

54,227

157,136

296,596

528,319

(U) Change Summary Explanation:

Funding: Added $141,674 over the FYDP to purchase a new 747-400F aircraft in lieu of a used 747-200 for PDRR. This provided cost avoidance in outyears by reducing total number of aircraft to be purchased. In addition, funding was rephased to execute the winning contractor’s PDRR approach.

Schedule: No change.

Technical: The Air Force is procuring a new 747-400F aircraft for PDRR testing instead of 747-200 aircraft. This allows commonality between the research and development and production efforts. Both test aircraft can now be refurbished and delivered to ACC in production configuration.

(U) C. Other Program Funding Summary ($ in Thousands)

 

 

FY 1996

FY 1997

FY 1998

FY 1999

FY 2000

FY 2001

FY 2002

FY 2003

To

Compl

Total

Cost

(U) PE 0603605F Advance Weapons Technology Project 3647 - High Energy Laser Technologies

11,601

11,401

10,021

7,674

7,414

7,570

7,820

8,000

TBD

TBD

 

(U) D. Schedule Profile

 

FY 1996

FY 1997

FY 1998

FY 1999

 

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

(U) Concept Design Review 1

 

X

                           

(U) PDRR Request For Proposal Release

   

X

                         

(U) Concept Design Review 2

       

X

                     

(U) Award PDRR Contract

       

X

                     

(U) Flight-weighted Laser Module Demo

                 

X

         

(U) Preliminary Design Review

                   

X

         

(U) Begin PDRR Aircraft Modification

                         

X

   

(U) Lethality Demonstration FY02

                               

(U) Milestone II FY03

                               

(U) Milestone III FY05

                               

(U) A. Project Cost Breakdown ($ in Thousands)

FY 1996

FY 1997

FY 1998

FY 1999

(U) Major Contracts (PDRR contract and Concept Design)

14,400

41,300

145,621

282,302

(U) Support Contracts (Technical Support, Analysis)

4,000

4,250

4,500

5,500

(U) In-House/Misc Support/Salaries/TDY/IPTs

1,960

8,677

7,015

8,794

         

(U) Total

20,360

54,227

157,136

296,596

(U) B. Budget Acquisition History and Planning Information ($ in Thousands)

Performing Organizations:

Contractor or Government Performing Activity

Contract Method/Type or Funding Vehicle

Award or Obligation Date

Performing Activity EAC

Project Office

EAC

Total

Prior to

FY 1996

 

Budget

FY 1996

 

Budget

FY 1997

 

Budget

FY 1998

 

Budget

FY 1999

 

Budget to Complete

 

Total Program

 

Product Development Organizations

Boeing Defense & Space Group Seattle, WA

CPAF

12 Nov 96

1,117,612

1,117,612

0

0

29,300

145,621

282,302

TBD

1,117,612

                       

Concept Design Contract (Rockwell International, CA)

CPFF

9 May 94

21,595

21,595

8,095

7,200

6,000

   

0

21,595

Concept Design Contract (Boeing Defense & Space Group, WA)

CPFF

9 May 94

21,589

21,589

7,689

7,200

6,000

   

0

21,589

Support and Management Organizations

Technical Support Contracts

       

2,096

4,000

4,250

4,500

5,500

TBD

TBD

                       

Government In-House and Other External Support

       

5,220

1,960

8,477

6,415

4,664

TBD

TBD

Test and Evaluation Organizations

Air Force Flight Test Center and Air Force Operational Test and Evaluation Center

           

200

600

4,130

TBD

TBD

(U) B. Budget Acquisition History and Planning Information Continued ($ in Thousands)

Government Furnished Property: None.

 

 

Item

Description

Contract Method/Type or Funding Vehicle

Award or Obligation Date

 

Delivery

Date

Total

Prior to

FY 1996

 

Budget

FY 1996

 

Budget

FY 1997

 

Budget

FY 1998

 

Budget

FY 1999

 

Budget to Complete

 

Total Program

 

Product Development Property

                     

Support and Management Property

                     
                     

Subtotal Product Development

15,784

14,400

41,300

145,621

282,302

TBD

1,160,796

Subtotal Support and Management

7,316

5960

12,727

10,915

10,164

TBD

TBD

Subtotal Test and Evaluation

200

600

4,130

TBD

TBD

Total Project

23,100

20,360

54,227

157,136

296,596

TBD

TBD

THIS PAGE INTENTIONALLY LEFT BLANK