NATIONAL MISSILE DEFENSE (NMD)


DoD ACAT ID Program Prime Contractor
Total Number of Interceptors:20 (Capability 1)LSI: - Boeing North American
Total Life Cycle Cost (TY$):$26,600M* 
Pro Rata Interceptor Cost (TY$):$1,150 M 
Deployment Readiness Review:3QFY00 
Capability 1 IOC:FY05 
*Assumes an FY05 deployment. The figure quoted includes the cost of operating the system for 20 years as well as development, production, and construction costs.


SYSTEM DESCRIPTION & CONTRIBUTION TO JOINT VISION 2010

The mission of the National Missile Defense (NMD) system is to defend all fifty United States against a limited strike of Intercontinental Ballistic Missiles (ICBMs). The initial deployment (Capability 1) is intended to defend against attacks by adversaries from "rest-of-world," or "rogue nations," with a residual capability against small-scale unauthorized or accidental launches. The system must perform detection, discrimination, battle management, and intercept functions, which require the integration of multiple sensor, communications, command and control, and weapon systems. Capability 2 will be an improved configuration that would exceed the values of the User's threshold operational requirements, but fall short of the objective value. Capability 3 would meet the objective values of the User's operational requirements. The objective capability may take an additional three to five years after the initial deployment of NMD.

The NMD system is an integrated collection of subsystems, referred to as "Elements," that perform dedicated functions during an ICBM engagement. The System will include a Battle Management, Command, Control, and Communications (BMC3) element, four types of long-range sensors (the Defense Support Program and Space Based Infrared System satellites, Upgraded Early Warning Radar (UEWR), and a Ground Based X Band Radar (XBR)) and arsenal of Ground Based Interceptors (GBI). The BMC3 at the Cheyenne Mountain Operations Center will perform engagement planning and situation assessment while keeping a "human-in-control," and serve to integrate the GBI and sensor operations through the In-Flight Interceptor Communications System (IFICS). The GBI is a silo-based, three-stage, commercial-off-the-shelf, ICBM-class missile that delivers a separating Exoatmospheric Kill Vehicle (EKV) to an "acquisition point" above the atmosphere en route to engage a threat target. At this point, in a manner similar to upper-tier theater missile defense systems, the EKV uses an infrared seeker to acquire and track the target, firing divert thrusters (for terminal guidance and control) to achieve a direct hit on the targeted reentry vehicle (RV). After the intercept, ground radar continue to collect data so that a kill assessment can be made to evaluate the success or failure of the engagement.

By design, NMD embodies the Joint Vision 2010 operational concept of precision engagement: NMD is an integrated system of subsystem elements, relying on information superiority to provide responsive command and control to engage attacking ICBMs. It performs kill assessment to evaluate the success of an engagement, and is capable of executing multiple engagements. By providing defense for the nation, NMD also incorporates the operational concept of full-dimensional protection.


BACKGROUND INFORMATION

In early 1996, the DoD completed a comprehensive review of its theater and national ballistic missile defense programs. The review shifted the NMD program from a Technology Readiness Program (1993-1996) to a Deployment Readiness Program (1996-2003), with the potential for a deployment decision in 2000. The previous acquisition strategy for NMD, referred to as the "3+3" program, has been modified based on redirection from the Secretary of Defense. The revised strategy retains a two-phased approach: (1) development; and (2) possible deployment, based on the threat and the demonstrated technological feasibility of the system to defeat that threat. A decision to deploy, based on the recommendation of the Deployment Readiness Review (DRR), planned for June 2000, would allow the program to plan for the fielding of a Capability 1 architecture by 2005 instead of 2003. The specific decisions to be made at the DRR are the commitment to deployment, element site selection, and authorization to proceed to contract award for site construction. Two other key decision points have been added on the path to the 2005 deployment. An FY01 decision will consider the building and/or upgrading of required ground radar systems and the integration of command and control software into the Cheyenne Mountain Operations Center. An FY03 decision will determine if the weapon system is ready for limited production and deployment. If no deployment decision is made, the program will still continue development with an eventual focus on a more capable NMD (Capability 2) system.

The Secretary also directed the Department to take no programmatic steps that would preclude the potential to deploy earlier than FY05. As part of the NMD redirection, more than $6 billion in additional funding was programmed to support development and initial deployment.

In the spring of 1998, the Ballistic Missile Defense Organization awarded the Lead System Integrator (LSI) contract to Boeing North American. The LSI serves as the prime contractor for NMD system development. The LSI contractor will be responsible for integrating the elements of NMD (radar, interceptors, and the BMC3). In addition, the LSI will demonstrate the system capability through integrated ground and flight testing. In December 1998, Boeing selected Raytheon as the EKV contractor. A Boeing designed EKVwould be held in abeyance, as a risk reduction activity, until completion of data reduction of Integrated Flight Test-4. Plans for this kill vehicle are undefined at this time.

The LSI will also serve as the key player in developing the necessary plans for fielding the system, should the decision be made to do so.


TEST & EVALUATION ACTIVITY

The system is currently in the Initial Development phase. It is during this phase that an initial NMD capability will be developed and its technological maturity demonstrated. This period will culminate in the DRR, which will determine whether the NMD Capability 1 system is technologically ready, if warranted by the emerging threat, to proceed to deployment. The previous TEMP is being revised. The purpose of the new TEMP is to define the specific progression of the T&E program from the present to an IOC in 2005. The revision will be accomplished in two phases. Phase I addresses the changes to pre-DRR ground and flight testing, brought on by the advent of the LSI and the down-select to a single EKV contractor. The Phase I TEMP was approved by OSD on December 21, 1999. The Phase II edition will provide a detailed T&E roadmap, to include modeling and simulation, for the evolution of the NMD system to the Capability 1 deployment. The Phase II document is expected at OSD in 3QFY00.

Near-term NMD T&E planning focuses on the ability to provide accurate test information and data in support of the DRR, and the ability of the system to achieve the following objectives:

Capability 1 system elements are derived from previous technology programs and will be integrated and tested in a series of Integrated Flight Tests (IFTs). Initially using surrogates to approximate NMD elements (as needed), then progressing to prototypes, IFTs are designed to collect data that address system issues and key technical parameters, verify the performance of NMD elements, and demonstrate overall system effectiveness. IFT-5, the final test to demonstrate overall system performance before the DRR, is scheduled for 3QFY00, and will play a key role in demonstrating that overall system objectives are met. The following table shows the major milestones in the flight testing program.

CURRENT SCHEDULE OF MAJOR FLIGHT TEST MILESTONES

Capability Level

Event

Planned Date

Purpose

Capability 1

IFT-3

October 1999

First intercept of a target in the exoatmosphere using range instrumentation and EKV guidance-achieved an intercept.

Capability 1

IFT-4

January 2000

First intercept attempt using NMD system prototype elements or surrogates, except the In Flight Interceptor Communications System and objective booster-failed to achieve an intercept.

Capability 1

IFT-5

3QFY00

First intercept attempt with all NMD prototype or surrogate elements integrated together except the objective booster.

Capability 1

IFT-7

2QFY01

First intercept attempt with objective, off-the-shelf booster.

Capability 1

IFT-14

2QFY03

First flight test against dedicated LFT&E target (Uses production representative EKV).

Capability 1

IFT-19

1QFY05

First IOT&E flight test.

Capability 2

TBD

TBD after FY05

First intercept at enhanced deployed capability on path to User's objective operational requirements.

Capability 3

TBD

TBD after 2007

Demonstrate intercept at objective Capability 3 performance level.

The initial flight test, IFT-1, was attempted in January 1997, but the Payload Launch Vehicle, the surrogate for the missile booster, failed to launch and the test was aborted. Since then, the NMD T&E program has performed two integrated flight tests: IFT-1A and IFT-2. IFT-1A, executed in June 1997, and IFT-2, executed in January 1998, were deemed highly successful. Both IFT-1A and IFT-2 were non-intercept, fly-by tests, designed to assess EKV seeker discrimination and homing algorithm design. Boeing and Raytheon built the EKVs for IFT-1A and IFT-2, respectively. IFT-3 and IFT-4 were previously planned to be intercept attempts by Boeing and Raytheon in support of an EKV contractor down-select prior to IFT-5. At the recommendation of the LSI, the NMD Joint Program Office (JPO) opted to down-select to a single EKV design prior to IFT-3. This approach has the advantage of three possible intercept flights with the selected EKV prior to the DRR, but added the risk of no attempts prior to down-select.

IFT-3 was conducted on October 2, 1999. It was the first attempt at intercepting a threat-like ICBM test target. The target complex, which consisted of an RV and a large balloon decoy, was launched by a Minuteman based Multi-Service Launch System from Vandenberg AFB, CA. The GBI surrogate, the Payload Launch Vehicle (PLV), was launched about twenty minutes later from Meck Island in the Kwajalein Atoll, about 4,200 miles west of Vandenberg. While the test examined all aspects of the NMD system design to some degree, its principal focus was the EKV. The EKV was boosted to its deployment location by the PLV and guided to its initial acquisition position by range instrumentation and Global Positioning System data downloaded from the target RV. After separation from the PLV, the EKV oriented itself to look at known star configurationsto correct for any attitude bias. Errors induced in the inertial navigation system during this orientation process , coupled with incorrect star data that was loaded into the system pre-flight, subsequently induced additional aiming errors into the EKV. Given these errors, when the EKV aimed itself toward the expected target location, nothing appeared in the field of view. After executing its search routine, it acquired the large balloon and subsequently the rest of the target complex. From that point, the EKV discriminated the RV from the other objects and diverted to an intercept. The large balloon aided in acquisition of the target. It is uncertain whether the EKV could have achieved an intercept in the absence of the balloon, although analysis of the data indicates that achievement of the intercept cannot be discounted.

IFT-4 was conducted on January 18, 2000. It was the first flight test for which the LSI assumed complete responsibility. Previous flight tests were run by the Government. IFT-4 attempted to demonstrate the functionality of all of the NMD elements, although the PLV was again used to launch the EKV and the In Flight Interceptor Communications System was not fully exercised. Additionally, mid-range target tracking was accomplished using beacon tracking or GPS data from the target RV. The interceptor Weapon Task Plan initial targeting coordinates and In Flight Target Updates were created using the GPS data, which is significantly more accurate than similar data from the Early Warning X-Band Radar. IFT-4 failed to achieve an intercept. Forensic analysis of the test data is ongoing to understand the cause(s) of the missed intercept.

Integrated Ground Tests (IGTs) will be conducted utilizing the Integrated System Test Capability (ISTC), a computer-based hardware/software-in-the-loop test tool that uses actual NMD element data processors and software in an integrated configuration. Unlike the range-constrained IFTs, IGTs will look at the total engagement space in a tactical environment. They will also: (1) validate the functional interfaces between the elements; (2) subject those interfaces to stressing environments and tactical scenarios; and (3) evaluate target-intercept boundary conditions. In short, IGTs will enable identification of "unknown unknowns" in an interactive system context, and verify the interoperability of NMD elements.

Prior to the formalization of the NMD program, IGTs-1 and 2 were informally conducted to verify the development of the ISTC and assess preliminary functional interactions and interfaces among NMD element representations. IGT-1A was the first formal ground test designed to demonstrate successful exchange of messages between the BMC3 and the prototype XBR, (the Ground Based Radar Prototype (GBR-P)). IGT-1A was conducted from April to May 1998, using ISTC Configuration Build 4.0.2, which incorporated BMC3 Capability Increment-2 and GBR-P Increment-1 processors. The IGT-1A threat scenarios were representative of IFT scenarios, derived from measurements by range sensor data recorded during IFT-1A. All IGT-1A objectives were successfully accomplished. IGT-3 added a UEWR processor to the GBR-P and BMC3 network and exchanged information using the Capability Increment-3 message set. There were 75 good run-for-record test runs conducted from February 1-18, 1999. All objectives were achieved, although the UEWR was sometimes overwhelmed by the number of cues it received from the BMC3. Also, the UEWR did not always track all of the objects that it should have. In addition, during six control tests, significant unexpected variability was exhibited in system performance.

There were 50 acceptable runs-for-record for IGT-4, conducted during August 9-18, 1999. IGT-4 was not intended to assess the performance of the C1 architecture. The test successfully demonstrated integration of the BMC3, GBR-P/XBR, and UEWR. There was no direct communication between the BMC3 and the EKV. The UEWR was more successful in maintaining connections to the BMC3 than it had been in IGT-3. The run-to-run variability was significantly smaller in IGT-4 than it had been in IGT-3.

There were 55 acceptable runs-for-record for IGT-5, conducted during October 12-19, 1999. The test continued to successfully demonstrate integration of the BMC3, GBR-P/XBR, and UEWR. In addition, IGT-5 provided a preliminary assessment of the NMD performance against a subset of C-1 requirements. Of the six different types of scenario examined in IGT-5, only one scenario type had nominal performance. Most of the problems in the other scenarios were due to the lack of maturity of the NMD system representations used in IGT-5.

Computer models and simulations will provide representations of elements that are not mature enough for the test program. The principal simulation tool providing DRR support is the LSI Integration Distributed Simulation (LIDS). Modeling and simulation will be employed to effectively repeat hypothetical experiments in order to improve the statistical sample or determine the values of key technical parameters possibly overlooked or unmeasured.

All NMD flight testing will be in compliance with the Anti-Ballistic Missile (ABM) Treaty and other applicable treaties at the time of testing. Kwajalein Missile Range (KMR) and White Sands Missile Range are authorized to launch interceptors under the ABM treaty, but only KMR is configured to accept incoming strategically representative target flights. Accordingly, flight tests will use target suites launched from Vandenberg and directed towards KMR.

The LFT&E Working Group, a subgroup of the NMD Lethality IPT, has developed the LFT&E strategy for NMD. LFT&E activities include flight testing, sub-scale light-gas-gun testing, and simulation analyses. Sled tests are also being considered for low-end intercept velocities. Three dedicated LFT&E flight tests are planned to be conducted.

The NMD T&E program also includes a number of pre-DRR lethality test and analysis activities to support the development and accreditation of first-principles physics codes, commonly known as hydrocodes, for application to NMD. This testing will also support the development and accreditation of the lethality simulation known as Parametric Endoatmospheric/Exoatmospheric Lethality System. These simulation tools will be used for analyses in both pre- and post-DRR timeframes. The activities include: (1) target aerothermal shield damage analyses; (2) hydrocode analyses that define kill criteria for the respective EKV designs proposed by Boeing and Raytheon; (3) light-gas-gun impact testing for hydrocode validation; (4) kill-enhancement device testing; and (5) light-gas-gun testing to develop and validate material equations of state at high velocities. The analysis activities are currently ongoing. Twenty light-gas-gun tests planned for hydrocode validation were successfully completed in FY99. Testing to develop equations-of-state (the characterization of the physical phenomena that occurs during impact) is in its initial stages.

NMD Y2K vulnerability assessment addressed all aspects of the program, including the system elements (especially the BMC3 system), the flight and ground testing supporting systems, and the models and simulations used to predict performance. All NMD mission critical deployable systems, as well as science and technology support systems, were declared Y2K Compliant by the Ballistic Missile Defense Organization Y2K Compliance Review Board in July, 1999. The process of Y2K compliance includes assessment, renovation, validation, and implementation phases. The NMD program office will continue to work with the LSI to ensure Y2K compliance of the deployable systems through a configuration management process as hardware/software development continues. The program also conducted a Y2K Operational Evaluation Test of system prototypes to preclude a Y2K anomaly during any flight testing after January 1, 2000. Associated elements for conduct of IFTs and IGTs also underwent extensive Y2K testing. Two Y2K Operational Evaluation tests were conducted within the flight and ground test schedules. The first occurred at the ISTC prior to pre-mission testing for IFT-4. The second was conducted at KMR in early January 2000 during the pre-mission checkout for IFT-4. During the pre-mission dry runs and readiness tests, participating elements and the mission control support tested Y2K dates. This testing verified: (1) interface hardware and software; (2) sub-system functions; and (3) that the adequacy of operator training and procedures are not affected by Y2K dates. Testing through IFT-4 has not identified any Y2K problems.


TEST & EVALUATION ASSESSMENT

Despite the revised program, the aggressive schedule established for the NMD Program presents a major challenge. The NMD program will have to compress the work of 10 to 12 years into 8 or less years. As a result, many of the design and T&E activities will be performed concurrently. Program delays also caused the conduct of IFT-3 to slip to October 1999. This represents almost a 20-month slip over the last two years and demonstrates an extremely high-risk schedule. Additionally, the failure of IFT-4 to achieve an intercept may result in a further setback to the NMD schedule. The revised program has alleviated some of the long-term risk by deferring and staging the decision process as described earlier. However, since the DRR date has not been deferred, undo pressure has been placed on the program to meet an artificial decision point in the development process. The DRR will be a "come as you are" type of review which will examine the maturity and potential of the program at that point. This is driving the program to be "schedule" rather than "event" driven. This pattern has historically resulted in a negative effect on virtually every troubled DoD development program. In spite of this intense pressure, the program manager is doing an excellent job in trying to efficiently and effectively manage the preparation for the DRR and ultimately the deployment.

The complex operating characteristics and environments of the NMD T&E Program make it necessary to plan and conduct IFTs that are restricted in scope. DRR information based on a few flight tests with immature elements will be limited. Although IFT-3 was an important test in ballistic missile defense and demonstrated a newtechnology, it had significant limitations to operational realism, as noted throughout this report.

Due to the restrictions on realistic operational flight testing, the T&E program will rely heavily on ground testing and the execution of simulations for assessing the maturity and performance of the NMD system concept. The LIDS model development is proceeding much slower than planned. It is extremely doubtful that the model will be completed in time to allow for a rigorous system analysis for the DRR, resulting in limited analysis. A "beta" version of the software is promised to be ready by the end of February 2000. Service Operational Test Agencies may have to rely on alternative low fidelity models to assess the potential system effectiveness.

The FY98 DOT&E Annual Report identified a number of risks that could have significant impact on the NMD T&E program's ability to test, analyze, and evaluate system performance. The degree to which those risk areas have changed from the last reporting cycle are addressed below:


VALUE ADDED

DOT&E has been a significant contributor through the IPT process to formulate the NMD T&E program on practically a daily basis. We have been one of the principal stimuli to the JPO's plan to develop a comprehensive integrated HWIL effort. This will enable an effective and efficient ground testing capability, which will significantly reduce the risk of successful flight testing.

At DOT&E's recommendation, the JPO is proposing to alter the 2003 weapon decision to seek low rate rather than full-rate production authorization. It will permit dedicated LFT&E flight tests to be performed with production representative EKVs and allow the IOT&E to be conducted prior to full-rate production. This will reduce the risk of prematurely committing to the production in large quantities of interceptors that may not have sufficient lethality to defeat threat RVs.

Many of DOT&E's concerns and recommendations have likewise been independently captured in the second Welsh panel report.


RECOMMENDATIONS

The DRR is currently firmly scheduled in June 2000 rather than after completion of the analysis of IFT-5. This is a strongly "schedule driven" (vice "event driven") approach, thereby placing unrealistic pressure on the JPO. IFT-5 will be the first intercept attempt with all NMD elements integrated except the booster. DOT&E is recommending that preparations for the DRR allow time for a thorough analysis of the IFT-5 test data in order to inform the DRR decision, especially in light of the failure of IFT-4 to intercept the target. This would provide a clear technical understanding of the results and avoid forcing the DRR before the analysis is complete.

Several factors drive the need for an improved hardware-in-the-loop approach. They include the failed IFT-4 intercept, the role of the large balloon in supporting an intercept and speculation on the EKV's ability to discriminate countermeasures. DOT&E strongly recommends an intensive effort to develop a flexible, comprehensive hardware-in-the-loop facility that presents a high fidelity representation of the threat target for designing and testing of the EKV.