SBLRD Risk Summary
Cost
- Numerous cost estimates conducted by Program Management Office (PMO) to explore alternate strategies, all exceed current POM funding
Performance/Technical
- Laser: power increase, uncooled optics, autonomous resonator alignment
- Beam control and tracking optics: autonomous alignment & boresighting
- Vehicle Integration: particularly vibration isolation, software, & weight
Schedule
- Almost totally set by budget add above POM
- Major driver of technical and cost risk
Other
- Funding priorities and stability
- Laser Test Facility
- ABM Treaty
Overall Program Risk for 2005 Launch Assessed by PMO as High