In this section, the study group presents some relevant information about
NMD and our reactions to it.
64
NMD Program
- Purpose: "to develop, demonstrate, and deploy an initial land-based national
missile defense (NMD) system to defend against limited strategic missile
attacks and be capable of evolving to counter future threats."
- U.S. defense (all SO states)
- Assured human-in-control
- 3+3
- 3 years (1999) to reach readiness to deploy in 3 years (2002). In the
interim, continue to develop and improve the NMD system
- Readiness to deploy review in 2000
- System architecture: "plug and defend"
- Flexible systems engineering and integration
- Respond to unknowns in threat and constraints
|
The current approach to preparing for NMD deployment introduces new
and very demanding complexities. The current plan calls for bringing the
system to a state of maturity by the end of 1999 such that the system is within
3 years of deployment. In the worst case, that would require deployment in
5 years.
While the readiness review in 2000 would theoretically modify the
expectation, the very high visibility of this program is likely to produce intense
pressures to maintain the schedule. Hence, the program begins with many of
the problems that have beset other HTK programs: compressed schedule,
minimal flight test, and poorly defined test objectives.
In addition, the funding for the program has been erratic at best and the
program management approach depends to an unprecedented degree on an
integrating contractor -- again, an intriguing but unproven approach for a
program that is to do something that has never been done before.
65
NMD Program Structure
|
This rendition of the program structure calls for an integrated systems test
in FY99 on the fifth test flight -- about 1 year after the first intercept attempt,
which occurs on the third test flight.
There is one backup integrated systems test flight available before the
readiness review in 2000.
This schedule appears to be significantly more compressed and optimistic
that the TMD programs schedules that have proven to be excessively
challenging.
66
NMD System Risks
|
|
System Risk |
Concern |
Mitigation
|
|
T&E Program |
Number of tests before deployment
|
increased funding / added more tests / added spares
|
|
System Discrimination
|
Ability of elements to acquire data, fuse data, and discriminate reentry vehicle (RV) in a time constrained environment
|
Increased developemtn, testing and validation of discrimination algorithms
Dual EKV sensor approach
|
|
System Siting
|
Construction timelines
Easements
Environmental Impact Statements
|
Incremental deployment
Congressional waivers
Selected sites / EIS process
|
|
External Integration
|
Stressing timeline of required integration with external agencies
|
Integration plans developed and being implemented
|
The program office recognizes the fact of high risk associated with the
minimal flight test schedule and the very difficult discrimination challenge.
Non-technical program challenges are also recognized. However, the program
has not yet matured to the point of identifying the specific set of risks that need
to be addressed. That activity will have to await the work of the integrating
contractor.
67
NMD Test Risk
- Test and Target Spares
- Spare booster available for all flights
- Front section spares formed from a combination of spare components and
pulling subsystems from succeeding planned flights
- Target spares formed by pulling target object from succeeding planned flights
|
Spare test assets are a partial answer to the high-risk test program.
However, it appears that the current plan for obtaining spares, shown on the
slide, is minimal at best.
68
NMD Risks and Mitigation
System Discrimination (EKV)
- Risks
- Battle Managemment/Command, Control, and Communications (BM/C3)
fusing different types of sensor data
- EKV combining IR sensor images with ground-based interceptor (GBI) IR
discrimination algorithms
- EKV target discrimination
- Mitigation
- Parallel EKV contractor competition
- Transition technology activities
- Rad hardening/mercad telluride technology
- Focal plane/silicon array technology
|
The discrimination problem for NMD is very challenging. The information
on this slide was provided by the NMD JPO. The mitigation techniques
proposed here are noteworthy but are not adequate to cover the range of risks
Already identified.
69
NMD T&E Risk Reduction
|
|
Risk Areas for T&E Resolution
limited system level testing
Threat target realism
Lack of spare test articles
Multiple target tests
NMD interoperability testing
|
BMDO-Proposed T&E Risk-Rcduction Actions
Additional integration facility for pre-IFT test
Target object inventory: RVs, decoys, balloons, and so forth
Spare test expendables
Upgrade launch support at Meck Island
Increased risk-reduction flight tests
More simulation, test, and evaluation process
|
Specific T&E risks are currently being addressed by the NMD JPO with
this set of risk-mitigation measures. While these measures seem necessary,
they do not do much to relieve a very demanding development and test
schedule.
70