FY 2006 E&W Bill Rushes Reprocessing
$5M to each of four sites just to prepare proposals.
DOE program plan by March 2006
Begins site competition in June 2006
Conceptual design in FY2006
Engineering scale demonstration in FY2007
Select technology in 2007
Begin construction in 2010